PT X memproduksi ratusan hingga ribuan tipe filter sesuai demand yang masuk dari customer. Kondisi tersebut mengharuskan mesin pembuat filter rokok di PT X untuk mengganti proses produksinya dari spesifikasi sebelumnya menjadi spesifikasi yang baru. Proses yang dilakukan untuk menyiapkan mesin dari proses produksi sebelumnya menjadi proses produksi selanjutnya dikenal dengan istilah changeover. Durasi yang diperlukan untuk mengerjakan satu kali proses changeover di PT X mencapai lebih dari 20 jam. Lamanya proses changeover tersebut, berdampak pada turunnya output yang dihasilkan oleh mesin hingga 90% untuk satu kali proses.
Penelitian tugas akhir ini dilakukan untuk menganalisis penyebab tingginya waktu changeover pada mesin pembuat filter rokok. Metode yang dapat digunakan untuk menganalisis penyebab tingginya waktu changeover serta mengetahui cara mereduksinya adalah SMED atau single minute exchange of die. Metode tersebut terdiri dari empat tahap, pada tahap preliminary stage digunakan metode time and motion study, untuk selanjutnya diidentifikasi aktivitas apa saja yang menyebabkan lamanya durasi changeover, sedangkan untuk motion study selanjutnya divisualisasikan menggunakan spaghetti diagram untuk mengetahui apa saja aktivitas setup yang memiliki jumlah movement paling banyak serta memiliki jarak tempuh paling besar dan diidentifikasi kemungkinan faktor penyebabnya. Pada tahap kedua dan ketiga dilakukan pemisahan aktivitas internal dan eksternal serta mengubah aktivitas eksternal yang masih dilakukan secara internal menjadi aktivitas eksternal untuk mengetahui opportunity waktu yang dapat direduksi. Tahap yang terakhir yaitu merampingkan seluruh aspek setup dengan cara menstandardisasikan prosedur kerja serta melakukan improvements. Berdasarkan data time and motion study yang telah diperoleh, proses yang dilakukan selanutnya yaitu menganalisis faktor penyebab lamanya waktu changeover menggunakan metode 8 waste, root cause analysis, dan FMEA. Hasil yang didapatkan setelah mengimplementasikan beberapa upaya perbaikan yaitu, penurunan waktu changeover hingga 70% dari 26 jam menjadi 5 jam 20 menit.
====================================================================================================================================
PT X produces hundreds to thousands of filter types according to incoming demand from customers. This condition requires the cigarette filter making machine at PT X to change its production process from the previous specification to the new specification. The process carried out to prepare the machine from the previous production process to the next production process is known as changeover. The duration required to do one changeover process at PT X reaches more than 20 hours. The length of the changeover process has an impact on the decrease in output produced by the machine up to 90% for one process.
This final project research was conducted to analyze the cause of high changeover time in cigarette filter making machine. One method that can be used to analyze the causes of high changeover time and find out how to reduce it is SMED or single minute exchange of die. The method consists of four stages, in the preliminary stage the time and motion study method is used, to further identify what activities cause the long duration of changeover, while the motion study is then visualized using a spaghetti diagram to find out what setup activities have the highest number of movements and have the greatest distance to travel and identify possible causal factors. In the second and third stages, the separation of internal and external activities is carried out and external activities that are still carried out internally are converted into external activities to determine the opportunity time that can be reduced. The last stage is to streamline all aspects of the setup by standardizing work procedures and making improvements. Based on the time and motion study data that has been obtained, the next process is to analyze the factors that cause the long changeover time using the 8 wastes method, root cause analysis, and FMEA. The results obtained after implementing several improvement efforts are a 70% reduction in changeover time from 26 hours to 5 hours 20 minutes.

Item Type: Thesis (Other)
Uncontrolled Keywords: Changeover, Setup, Single Minute Exchange of Die
Subjects: T Technology > TJ Mechanical engineering and machinery > TJ174 Maintenance and repair of machinery
T Technology > TS Manufactures > TS183 Manufacturing processes. Lean manufacturing.
Divisions: Faculty of Industrial Technology and Systems Engineering (INDSYS) > Mechanical Engineering > 21201-(S1) Undergraduate Thesis
Depositing User: Tasya Putri Rahmadini
Date Deposited: 09 Aug 2023 07:58
Last Modified: 09 Aug 2023 07:58
URI: http://repository.its.ac.id/id/eprint/103502

Actions (login required)

View Item View Item