Liem, Kelvin Hermansyah (2024) Evaluasi Dan Perbaikan Manajemen Proyek Pada Fabrikasi Air Receiver Pressure Vessel (Studi Kasus: PT. Boma Bisma Indra). Other thesis, Institut Teknologi Sepuluh Nopember.
Text
02111640000026-Undergraduate_Thesis.pdf - Accepted Version Restricted to Repository staff only until 1 April 2026. Download (4MB) | Request a copy |
Abstract
Pada tugas akhir ini dilakukan penelitian pada PT Boma Bisma Indra di Pasuruan dalam pengerjaannya dalam produksi Pressure Vessel dengan customer PT. Wijaya Karya. Pengerjaan pressure vessel oleh PT Boma Bisma Indra pada tahun 2021 ditargetkan mulai dan selesai dalam waktu tujuh bulan namun setelah diselesaikan dapat diketahui bahwa proyek ini mengalami keterlambatan akibat berbagai permasalahan terutama pada proses fabrikasi. Setelah dilakukan proses pengumpulan data dan wawancara mengenai aktivitas proses fabrikasi, terdapat keterlambatan kedatangan raw material dan sumber daya manusia yang pengalokasiannya masih tidak menggunakan manajemen proyek yang tepat. Penelitian ini bertujuan untuk mengevaluasi keterlambatan proses fabrikasi air receiver pressure vessel dan mendapatkan langkah penanggulangan dan perbaikannya. Metode manajemen proyek digunakan dalam melakukan evaluasi proses fabrikasi air receiver pressure vessel untuk mendapatkan perbaikan pada permasalahan yang terjadi. Langkah pertama adalah mengumpulkan data dan menganalisa data tersebut untuk menentukan major delays. Analisa yang dilakukan dengan mengevaluasi selama proses fabrikasi sehingga bisa didapatkan improvement. Microsoft Project digunakan sebagai alat bantu dalam penyusunan kegiatan fabrikasi ini agar dapat dilakukan pengalokasian sumber daya dan jadwal kerja yang optimal dan pembagian beban kerja yang merata. Hasil dari penelitian ini setelah dilakukannya evaluasi dan perbaikan adalah bahwa pekerjaan proyek air receiver PT WIKA dapat direncanakan waktu pengerjaannya selama 36 minggu berbanding dengan aktual pengerjaan yang membutuhkan waktu selama 61 minggu dan dapat meminimalisir biaya overhead sebesar 42%.
=================================================================================================================================
In this final project, research was carried out at PT Boma Bisma Indra in Pasuruan in its work on the production of Pressure Vessel with customer PT Wijaya Karya. The work on the pressure vessel by PT Boma Bisma Indra in 2021 is targeted to start and finish within seven months, but after completion it can be seen that this project has experienced delays due to various problems, especially in the fabrication process. After the data collection process and interviews regarding the fabrication process activities, there are delays in the arrival of raw materials and human resources whose allocation still does not use proper project management. This study aims to evaluate the delays in the fabrication process of the air receiver pressure vessel and obtain countermeasures and improvements. Project management methods are used to evaluate the fabrication process of air receiver pressure vessels to find improvements to the problems that occur. The first step is to collect data and analyze the data to determine major delays. The analysis is done by evaluating during the fabrication process so that improvements can be obtained. Microsoft Project is used as a tool in the preparation of this fabrication activity so that optimal allocation of resources and work schedules can be made and an even distribution of workload. The results of this study after evaluation and improvement are that the PT WIKA air receiver project work can be planned for 36 weeks compared to the actual work that takes 61 weeks and can minimize overhead costs by 42%.
Item Type: | Thesis (Other) |
---|---|
Uncontrolled Keywords: | Pressure Vessel, Manajemen Proyek, Work Breakdown Structure |
Subjects: | T Technology > TJ Mechanical engineering and machinery |
Divisions: | Faculty of Industrial Technology and Systems Engineering (INDSYS) > Mechanical Engineering > 21201-(S1) Undergraduate Thesis |
Depositing User: | Kelvin Hermansyah Liem |
Date Deposited: | 27 Feb 2024 02:10 |
Last Modified: | 27 Feb 2024 02:10 |
URI: | http://repository.its.ac.id/id/eprint/107711 |