Pengembangan Model Sistem Dinamik Untuk Meningkatkan Rasio Pemenuhan Energi Listrik Melalui Pengembangan Pembangkit Listrik Tenaga Bayu (PLTB)

Permatasari, Septica Tiara Indah (2024) Pengembangan Model Sistem Dinamik Untuk Meningkatkan Rasio Pemenuhan Energi Listrik Melalui Pengembangan Pembangkit Listrik Tenaga Bayu (PLTB). Other thesis, Institut Teknologi Sepuluh Nopember.

[thumbnail of 5026201031-Undergraduate_Thesis.pdf] Text
5026201031-Undergraduate_Thesis.pdf - Accepted Version
Restricted to Repository staff only until 1 October 2026.

Download (5MB) | Request a copy

Abstract

Latar Belakang: EBT (Energi Baru Terbarukan) merupakan sumber energi alternatif yang tidak terbatas dan tidak akan habis meskipun digunakan secara terus menerus. Salah satu potensi EBT di Indonesia yang belum dimanfaatkan secara optimal yaitu energi angin. Pemanfaatan energi angin dilakukan melalui pembangunan pembangkit listrik. Menurut Laporan Rencana Usaha Penyediaan Tenaga Listrik (RUPTL) PLN tahun 2021-2030, salah satu lokasi potensial di Jawa Timur yang dapat dibangun Pembangkit Listrik Tenaga Bayu (PLTB) adalah Banyuwangi.
Permasalahan: Meningkatnya jumlah penduduk di Banyuwangi menyebabkan kebutuhan akan energi listrik terus meningkat. Peningkatan kebutuhan energi listrik tersebut menyebabkan semakin terbatasnya cadangan sumber energi seperti minyak bumi dan batu bara. Akibatnya, permintaan listrik yang tidak diimbangi oleh supply listrik yang cukup akan berdampak pada kurangnya produksi listrik yang dihasilkan.
Tujuan: Tujuan penelitian ini diharapkan dapat menghasilkan pemodelan sistem dinamik, merancang skenario serta memberikan rekomendasi dalam meningkatkan rasio pemenuhan energi listrik melalui pengembangan Pembangkit Listrik Tenaga Bayu (PLTB).
Metode: Tahapan dalam mengerjakan tugas akhir ini berpedoman pada metode Sistem Dinamik. Pemodelan sistem dinamik digunakan untuk mengetahui faktor-faktor yang berpengaruh khususnya dalam meningkatkan rasio pemenuhan energi listrik melalui pengembangan Pembangkit Listrik Tenaga Bayu (PLTB). Dalam pengembangan model, dilakukan analisis variabel-variabel tersebut dalam bentuk Causal Loop Diagram(CLD) dan Stock and Flow Diagram (SFD). Selanjutnya, dilakukan pengujian menggunakan Behavioral Validation yaitu Mean Comparison (E1) dan Percentage of Error Variance (E2). Terakhir, dilakukan perpanjangan simulasi model dalam 12 tahun ke depan untuk mengembangkan skenario.
Hasil : Skenario yang dilakukan yaitu Do Nothing, pengembangan energi angin dengan menggunakan turbin angin jenis Horizontal Axis Wind Turbine (HAWT) dan pengembangan energi angin dengan menggunakan turbin angin jenis Vertical Axis Wind Turbine (VAWT). Dari ketiga skenario tersebut, penggunaan turbin angin jenis HAWT dan VAWT dapat meningkatkan fulfillment ratio sampai 1.08%, meskipun produksi listrik turbin angin jenis HAWT lebih besar serta biaya yang dibutuhkan lebih tinggi dibandingkan VAWT.
Manfaat : Penelitian tugas akhir ini memiliki manfaat secara teoritis maupun secara praktis. Pada manfaat teoritis, penelitian ini dapat memberikan wawasan sekaligus literatur sistem dinamik dengan studi kasus energi terbarukan. Sedangkan, pada manfaat praktis, penelitian ini dapat menjadi rekomendasi dalam pengambilan kebijakan oleh Manager PT Bayu Energi 3 untuk pengembangan PLTB di Kabupaten Banyuwangi.
===========================================================
Background: Renewable energy is an alternative energy source that is unlimited and will not run out even though it is used continuously. One of the renewable energy in Indonesia that has not been optimally utilised is wind energy. The utilisation of wind energy is done through the construction of power plants. According to the PLN Electricity Supply Business Plan Report for 2021-2030, one of the potential locations in East Java where a wind power plant can be built is Banyuwangi.
Problem: The increasing population in Banyuwangi causes the demand for electrical energy to continue increasing. The increase in demand for electrical energy has led to increase in use of limited reserves of energy sources such as petroleum and coal. As a result, electricity demand that is not balanced by sufficient electricity supply will have an impact on the lack of electricity production generated.
Purpose: The purpose of this research is expected to create dynamic system modelling, design scenarios and provide recommendations in improving the fulfillment ratio of electrical energy through the development of Wind Power Plants.
Methods: The final project follows the Dynamic System method. Dynamic System modelling is used to determine the influential factors, especially in improving the fulfillment ratio of electrical energy through the development of Wind Power Plants. In developing the model, the variables were analysed in the form of Causal Loop Diagram and Stock and Flow Diagram. Furthermore, testing is carried out using Behavioral Validation, namely Mean Comparison (E1) and Percentage of Error Variance (E2). Finally, the model simulation was extended for the next 12 years to develop scenarios.
Results : The scenarios are Do Nothing, wind energy development using Horizontal Axis Wind Turbine (HAWT) and wind energy development using Vertical Axis Wind Turbine (VAWT). Of the three scenarios, the use of HAWT and VAWT wind turbines can improve the fulfillment ratio to 1.08%, although the electricity production of HAWT wind turbines is greater and the costs required are higher than VAWT.
Benefits : This final project research has theoretical and practical benefits. In the theoretical benefits, this research can provide insight as well as dynamic system literature with renewable energy case studies. Meanwhile, on practical benefits, this research can be a recommendation in policy making by the Manager of PT Bayu Energi 3 for the development of Wind Power Plants in Banyuwangi Regency.

Item Type: Thesis (Other)
Uncontrolled Keywords: Renewable Energy, Development of Wind Power Plants, Electricity Fulfillment Ratio Improvement, Dynamics System Model, Energi Terbarukan (EBT), Pengembangan Pembangkit Listrik Tenaga Bayu (PLTB), Peningkatan Rasio Pemenuhan Energi Listrik, Model Sistem Dinamik.
Subjects: T Technology > T Technology (General) > T57.62 Simulation
Divisions: Faculty of Intelligent Electrical and Informatics Technology (ELECTICS) > Information System > 57201-(S1) Undergraduate Thesis
Depositing User: Septica Tiara Indah Permatasari
Date Deposited: 02 Aug 2024 02:11
Last Modified: 02 Aug 2024 02:45
URI: http://repository.its.ac.id/id/eprint/110218