Naufal, Fad'aq Muhammad (2024) Evaluasi Perencanaan Dinding Penahan Tanah Galian Basement dan Pondasi-dalam pada Gedung RSUP Hasan Sadikin, Bandung. Other thesis, Institut Teknologi Sepuluh Nopember.
Text
5012201141-Undergraduated_Thesis.pdf - Accepted Version Restricted to Repository staff only Download (6MB) | Request a copy |
Abstract
Sebagai solusi mengatasi kelangkaan lahan pada wilayah perkotaan, maka tuntutan adanya ruang bawah tanah atau biasa disebut basement dan struktur atas yang bertingkat pada pembangunan gedung-gedung fasilitas kesehatan merupakan suatu keharusan. Salah satu contohnya adalah pembangunan Rumah Sakit Hasan Sadikin (RSHS) yang berlokasi di Jalan Pasteur No. 38, Kel. Pasteur, Kec. Sukajadi, Kota Bandung, Jawa Barat. Bangunan ini terdiri dari struktur atas yang terdiri dari 8 lantai + atap dengan 1 lantai basement dengan galian sedalam 7 meter. Dari data pengujian di lapangan hingga kedalaman -40,00 meter dari muka tanah asli setempat dijumpai tanah keras dengan nilai NSPT. > 60 pukulan/30cm pada kedalaman +/- 14 m. Lapisan tanah permukaan didominasi oleh lempung lanauan – lanau lempungan (0.00 – 10.00m), lapisan di bawahnya didominasi oleh lapisan pasir kerikilan.
Pondasi yang digunakan (bored pile berdiameter 100 cm dengan panjang efektif 11 m pada area Ground Water Tank dan 16 m pada area basement ) mencapai kedalaman ± 20 meter di bawah muka tanah. Selain itu, pada proyek ini juga digunakan dinding penahan tanah berupa contiguous bored pile berdiameter 60 cm dengan kedalaman 14 meter dimulai dari permukaan tanah untuk menahan tekanan tanah pada area galian basement.
Untuk itu, pada tugas akhir ini perlu dilakukan analisis terhadap perencanaan pondasi dan dinding penahan tanah eksisting dengan memperhatikan kondisi tanah dan lingkungan yang ada. Dilakukan pula perencanaan alternatif yaitu desain bored pile untuk konstruksi pondasi dan contiguous bored pile untuk konstruksi penahan tanah yang kemudian akan dibandingkan dengan perencanaan eksisting demi mendapatkan perencanaan terbaik pada Gedung Rumah Sakit Hasan Sadikin. digunakan pondasi tiang berdiameter 100 cm dengan panjang penanaman tiang -33,3 m dari permukaan tanah untuk area GWT, -15,2 m dari permukaan tanah untuk area luar GWT. Sedangkan hasil analisis perencanaan alternatif dinding penahan tanah dengan contiguous bored pile, digunakan diameter 100 cm dengan total panjang 8,3 m pada area GWT dan diameter 60 cm dengan total panjang 5,2 m pada area ramp.
Sehingga perencanaan terbaik untuk struktur bawah Gedung Rumah Sakit Hasan Sadikin ditinjau dari kebutuhan volume materialnya adalah perencanaan alternatif pondasi bored pile dengan total sebanyak 31,98 m3 untuk material besi tulangan dan 3625,62 m3 untuk material beton. Dan perencanaan dinding penahan tanah eksisting yaitu dengan kebutuhan volume sebesar 8,809 m3 untuk material besi tulangan dan 650,7 m3 untuk material beton.
========================================================================================
As a solution to overcome land scarcity in urban areas, the demand for underground spaces, commonly known as basements, and multi-story structures in the construction of healthcare facilities is a necessity. One example is the construction of Hasan Sadikin Hospital (RSHS) located at Jalan Pasteur No. 38, Pasteur Village, Sukajadi District, Bandung City, West Java. This building consists of an 8-floor structure plus a roof with 1 basement floor with a 7-meter deep excavation. From field testing data up to a depth of -40.00 meters from the original ground surface, hard soil was found with an NSPT value > 60 blows/30cm at a depth of +/- 14 meters. The surface soil layer is dominated by clayey silt – silty clay (0.00 – 10.00m), with the underlying layer dominated by gravelly sand.
The foundation used (bored piles with a diameter of 100 cm and an effective length of 11 m in the Ground Water Tank area and 16 m in the basement area) reaches a depth of ± 20 meters below the ground surface. Additionally, this project also uses retaining walls in the form of contiguous bored piles with a diameter of 60 cm and a depth of 14 meters starting from the ground surface to withstand soil pressure in the basement excavation area.
Therefore, in this final project, an analysis of the existing foundation and retaining wall planning considering the soil and environmental conditions is necessary. An alternative planning was also conducted, which includes the design of bored piles for the foundation construction and contiguous bored piles for the retaining wall construction, which will then be compared with the existing planning to obtain the best planning for the Hasan Sadikin Hospital building. The used foundation piles are 100 cm in diameter with a pile embedding length of -33.3 m from the ground surface for the GWT area, and -15.2 m from the ground surface for the area outside the GWT. While the results of the alternative retaining wall planning analysis with contiguous bored piles used a diameter of 100 cm with a total length of 8.3 m in the GWT area and a diameter of 60 cm with a total length of 5.2 m in the ramp area.
Thus, the best planning for the underground structure of the Hasan Sadikin Hospital building in terms of the required material volume is the alternative planning of bored pile foundations with a total of 31.98 m3 for reinforcement material and 3625.62 m3 for concrete material. The existing retaining wall planning requires a volume of 8.809 m3 for reinforcement material and 650.7 m3 for concrete material.
Item Type: | Thesis (Other) |
---|---|
Uncontrolled Keywords: | Basement, Ground Water Tank, Bored pile, Contiguous bored pile, Ground anchor |
Subjects: | T Technology > TA Engineering (General). Civil engineering (General) > TA775 Foundations. |
Divisions: | Faculty of Civil, Environmental, and Geo Engineering > Civil Engineering > 22201-(S1) Undergraduate Theses |
Depositing User: | Fadaq Muhammad Naufal |
Date Deposited: | 06 Aug 2024 01:58 |
Last Modified: | 06 Aug 2024 01:58 |
URI: | http://repository.its.ac.id/id/eprint/110604 |