Perkembangan pesat dalam industri konstruksi, khususnya di Indonesia, mendorong peningkatan jumlah pembangunan infrastruktur. Fokus utama proyek konstruksi adalah mencapai hasil optimal dalam aspek biaya dan waktu. Penelitian ini
mengevaluasi penggunaan metode hollow core slab (HCS) sebagai alternatif efisien untuk Pelat beton, dibandingkan dengan metode konvensional. Penyusunan proyek akhir yang berjudul “Analisis Biaya Dan Waktu pada Gedung Pringgodigdo Universitas Airlangga dengan Metode Hollow Core Slab” ini
menggunakan data Gedung Pringgodigdo UNAIR Surabaya. Proyek ini berlokasi di Kampus B UNAIR Surabaya Fakultas Hukum dengan luas bangunan 23.379,9 m2. Proyek
ini seluruh pekerjaan elemen struktur beton menggunakan metode cor konvensional, sedangkan pelaksanaan yang digunakan dalam penyusunan proyek akhir adalah metode
Hollow Core Slab. Dengan data yang ditinjau pada proyek akhir hanya struktur bangunan gedung lantai 1 hingga 12.
Hasil analisis menunjukkan bahwa bangunan dengan metode HCS membutuhkan biaya lebih kecil yaitu Rp44.145.221.887,- sedangkan konvensional membutuhkan biaya sebesar Rp39.712.133.399,-. Selain itu juga waktu pengerjaan menggunakan metode HCS lebih cepat dengan selisih 13 hari dibandingkan sistem kovensional.
============================================================
Rapid development in the construction industry, especially in Indonesia, has led to an increase in infrastructure projects. The main focus of construction projects is to
achieve optimal results in terms of cost and time. This study evaluates the use of the hollow core slab (HCS) method as an efficient alternative to conventional concrete slabs.
The final project, titled "Cost and Time Analysis of Pringgodigdo Building Universitas Airlangga Using the Hollow Core Slab Method," uses data from the Pringgodigdo Building at UNAIR Surabaya. This project is located at Campus B UNAIR
Surabaya, Faculty of Law, with a building area of 23,379.9 m². The entire structural concrete work of the project uses the conventional casting method, while the implementation used in the final project is the Hollow Core Slab method. The data reviewed in the final project focuses only on the building structure from the 1st to the 12th floor.
The analysis results show that buildings using the hollow core slab method require a higher cost of Rp44.145.221.887,-, while conventional method requires a cost of Rp Rp39.712.133.399,-. Additionally, the construction time with HCS method is faster by 13 days compared to the conventional system.
Item Type: | Thesis (Diploma) |
---|---|
Uncontrolled Keywords: | waktu pekerjaan, hollow core slab, biaya pelaksanaan, Implementation time, hollow core slab, implementation cost |
Subjects: | T Technology > TH Building construction > TH1461 Concrete construction. T Technology > TH Building construction > TH437 Building--Cost control. |
Divisions: | Faculty of Vocational > Civil Infrastructure Engineering (D4) |
Depositing User: | Salmanta Rida Devina |
Date Deposited: | 12 Aug 2024 04:52 |
Last Modified: | 12 Aug 2024 04:52 |
URI: | http://repository.its.ac.id/id/eprint/112777 |
Actions (login required)
View Item |