Nurfitriaina, Azzura (2025) Implementasi Network Planning Pada Proyek XYZ Dengan Pendekatan Critical Chain Project Management (CCPM). Other thesis, Institut Teknologi Sepuluh Nopember.
|
Text
5020211069-Undergraduate_Thesis.pdf - Accepted Version Restricted to Repository staff only Download (5MB) | Request a copy |
Abstract
Proyek reparasi kapal sering mengalami keterlambatan yang menyebabkan peningkatan biaya dan gangguan operasional. Proyek pada perusahaan XYZ mengalami keterlambatan dari rencana awal 50 hari menjadi 62 hari. Keterlambatan ini disebabkan oleh faktor eksternal seperti cuaca buruk, keterlambatan pengadaan komponen, serta pengulangan pekerjaan akibat kesalahan teknis. Perusahaan semula menggunakan metode Critical Path Method (CPM) untuk menjadwalkan proyek, namun tidak tersedia data hasil identifikasi jalur kritis yang dibutuhkan untuk analisis. Oleh karena itu, penulis melakukan penjadwalan ulang dengan membangun kembali jaringan aktivitas menggunakan metode CPM untuk memperoleh jalur kritis secara mandiri. Selanjutnya, penjadwalan proyek juga dianalisis menggunakan metode Critical Chain Project Management (CCPM) untuk mengoptimalkan durasi dengan mempertimbangkan penambahan buffer, serta metode Program Evaluation Review Technique (PERT) untuk menganalisis peluang penyelesaian proyek. Hasil penelitian menunjukkan bahwa terdapat tujuh aktivitas kritis yang mempengaruhi durasi dan biaya proyek, yaitu Docking, Hydro test steering system, Fire fighting system test, Overhaul main & auxiliary engine, Pembersihan got kamar mesin, Pembersihan condensor & seal main air receiver, dan Undocking. Hasil perhitungan menunjukkan bahwa proyek reparasi kapal XYZ memiliki durasi 50 hari dan biaya total sebesar Rp571.200.000 menggunakan metode CPM, serta durasi 45 hari dengan biaya total sebesar Rp605.100.000 menggunakan metode CCPM. Dari analisis probabilitas menggunakan metode PERT, peluang penyelesaian proyek tepat waktu pada metode CPM mencapai 96,49% sedangkan pada metode CCPM sebesar 68,44%. Penelitian ini merekomendasikan metode penjadwalan dengan mempertimbangkan efisiensi waktu maupun biaya sesuai prioritas proyek.
===============================================================================================================================
Ship repair projects are often prone to delays, which can lead to increased costs and disruptions in operations. At company XYZ, the project experienced a delay from the original 50-day schedule to 62 days. This delay resulted from uncontrollable external factors such as unfavorable weather, late spare part deliveries, and rework due to technical errors. The company initially used the Critical Path Method (CPM) for scheduling; however, the critical path data required for analysis was not available. Therefore, the researcher reconstructed the project schedule using CPM to independently identify the critical path. Further analysis was conducted using the Critical Chain Project Management (CCPM) method, which shortens task durations, avoids multitasking, and adds buffers. Additionally, the Program Evaluation Review Technique (PERT) was applied to evaluate the probability of completing the project on time.The results identified seven critical activities affecting the project’s duration and cost: Docking, Hydro test of the steering system, Fire fighting system test, Overhaul of main and auxiliary engines, Bilge cleaning in the engine room, Cleaning the condenser and sealing the main air receiver, and Undocking. The calculation results show that the ship repair project at XYZ has a duration of 50 days and a total cost of Rp571.200.000 using the CPM method, and a duration of 45 days with a total cost of Rp605.100.000 using the CCPM method. Based on PERT analysis, the probability of on-time completion using CPM was 96.49%, while CCPM showed a probability of 68.44%. This research recommends selecting a scheduling method aligned with project priorities, whether focusing on time certainty or cost efficiency.
| Item Type: | Thesis (Other) |
|---|---|
| Uncontrolled Keywords: | Manajemen Proyek, Buffer, CPM, CCPM, PERT, Project Management, Buffer, CPM, CCPM, PERT |
| Subjects: | T Technology > T Technology (General) > T56.8 Project Management |
| Divisions: | Faculty of Marine Technology (MARTECH) > Ocean Engineering > 38201-(S1) Undergraduate Thesis |
| Depositing User: | Azzura Nurfitriaina |
| Date Deposited: | 15 Jul 2025 06:42 |
| Last Modified: | 15 Jul 2025 06:42 |
| URI: | http://repository.its.ac.id/id/eprint/119786 |