PENGARUH PEMANFAATAN GOT MIRING SEBAGAI PEMBANGKIT LISTRIK TENAGA MIKRO HIDRO PADA NILAI MANFAAT BIAYA (BENEFIT COST RATIO) SALURAN B.LT-9 DI DESA PLADEN KECAMATAN JEKULO KABUPATEN KUDUS

ULFIANA, DESYTA (2016) PENGARUH PEMANFAATAN GOT MIRING SEBAGAI PEMBANGKIT LISTRIK TENAGA MIKRO HIDRO PADA NILAI MANFAAT BIAYA (BENEFIT COST RATIO) SALURAN B.LT-9 DI DESA PLADEN KECAMATAN JEKULO KABUPATEN KUDUS. Undergraduate thesis, Institut Teknologi Sepuluh Nopember.

[img]
Preview
Text
3112100053-Undergraduate_Theses.pdf - Published Version

Download (3MB) | Preview

Abstract

Pembangkit listrik tenaga mikrohidro (PLTMH) adalah suatu pembangkit listrik skala kecil dengan kapasitas daya yang dihasilkan kurang dari 100 kW. Pembangkit ini memanfaatkan energi potensial jatuhan air yang diubah menjadi energi listrik. Saluran irigasi B.Lt-9 di Desa Pladen mengairi DI Logung Timur seluas 701 Ha. Saluran ini memiliki got miring dengan beda elevasi dasar saluran kurang lebih 4,9 meter yang berpotensi untuk dimanfaatkan sebagai PLTMH. Desa Pladen sedang mengalami kekurangan energi akibat kurangnya pasokan listrik dari PLN. Pembuatan pembangkit listrik tenaga mikro hidro pada saluran ini dapat memberikan manfaat tambahan pada got miring dan menjadi solusi alternatif untuk mengatasi permasalahan kekurangan listrik tersebut. Dalam hal ini, pemanfaatan got miring sebagai pembangkit listrik tenaga mikro hidro dapat memberikan pengaruh pada nilai manfaat biaya saluran irigasi B.Lt-9. Nilai manfaat biaya (benefit cost ratio) adalah nilai perbandingan antara nilai manfaat yang diperoleh dengan total pembiayaan. Daerah irigasi Logung memiliki 3 kali masa tanam dalam setahun dengan pola tanam padi-padi-palawija. Daerah irigasi ini memiliki produktivitas padi 7,5 ton/Ha dan produktivitas palawija 5 ton/Ha. Nilai manfaat biaya saluran B.Lt-9 sebelum ii perencanaan PLTMH dengan keuntungan berupa hasil panen sawah adalah 66,7. Dengan debit andalan sebesar 0,209 m3/detik dan tinggi jatuh efektif 4,845 meter serta menggunakan turbin Crossflow SJWG- 20/6.6, pemanfaatan got miring sebagai PLTMH berpotensi menghasilkan daya sebesar 7,956 kW. Nilai manfaat biaya PLTMH dengan keuntungan hasil penjualan energi listrik sebesar 64062,295 kWh selama satu tahun adalah 1,01. Sedangkan nilai manfaat biaya saluran setelah perencanaan PLTMH adalah sebesar 60,28. Maka, dari hasil tersebut proyek PLTMH ini layak secara ekonomi. ===== Micro hydro power plant is a small scale water power plant with a capacity of power less than 100 kW. It utilizes the potential energy of the falling water and convert it into electrical energy. Irrigation canal B.Lt-9 in the Desa Pladen irrigate Logung irrigation area of 701 Ha. It has a chute that has different elevation of canal bottom more or less 4,9 metres that is potential to build a micro hydro power plant on it. Desa Pladen was having lack of energy due to a lack of electricity supply from PLN. The construction of micro hydro power plant on the canal can provide additional benefits on chute and become an alternative solution to resolve the problem of lack of electricity. It can give effect on the benefit cost ratio of the irrigation canal B.Lt-9. Benefit cost ratio is the value of a comparison between the value of the benefits obtained with total financing. Logung irrigation area has 3 times of growing season in a year with the planting patterns of rice-rice-beans. The benefit of canal is from harvesting rice with the rice productivity is 7.5 tons/Ha and corn productivity is 5 ton/Ha. Benefit cost ratio of the canal B.Lt- 9 before utilization of chute is 66,7. The power plant is designed using 0,209 m3/s of flow discharge, 4,845 m of net head, and Crossflow turbine SJ-WG-8/6.6. It can potentially generate power of 7,956 kW. Benefit cost ratio of micro hydro power plant which is has benefit from selling 64062,295 kWh a year of electrical energy is 1,01. While the benefit cost ratio of the canal after the utilization of chute as micro hydro power plant is 60.28. Thus, the micro hydro power plant project is economically feasible.

Item Type: Thesis (Undergraduate)
Uncontrolled Keywords: Got miring, nilai manfaat biaya, pembangkit listrik tenaga mikro hidro, saluran irigasi, Benefit cost ratio, chute, irrigation canals, micro-hydro power plant
Subjects: T Technology > TJ Mechanical engineering and machinery > TJ164 Power plants--Design and construction
Divisions: Faculty of Civil Engineering and Planning > Civil Engineering > (S1) Undergraduate Theses
Depositing User: - Davi Wah
Date Deposited: 03 Jan 2017 04:27
Last Modified: 27 Dec 2018 04:34
URI: http://repository.its.ac.id/id/eprint/1267