Dewaji, Muhammad Rofiq (2022) Analisis Kinerja Waktu Dan Biaya Proyek Revitalisasi RCC RU VI Balongan Dengan Metode Probabilistic Earned Value. Other thesis, Institut Teknologi Sepuluh Nopember.
|
Text
03111840000136-Undregraduate_thesis.pdf Restricted to Repository staff only Download (2MB) | Request a copy |
Abstract
Proyek Revitalisasi RCC RU VI Balongan direncanakan selesai dalam waktu 363 hari dengan biaya sebesar Rp201.635.083.031. Dalam pelaksanaannya, proyek ini memiliki banyak kendala yang memungkinkan pelaksanaan proyek tersebut mengalami keterlambatan dan kerugian. Oleh karena itu, diperlukan analisis kinerja waktu dan biaya, serta memprediksi waktu dan biaya agar dapat menentukan langkah apa yang dilakukan jika terjadi keterlambatan dan pengeluaran yang berlebih dari suatu proyek. Unsur ketidakpastian atau risiko yang terdapat dalam pekerjaan proyek juga harus diperhatikan agar pada saat pengukuran kinerja dan prediksi waktu dan biaya didapatkan hasil analisis yang lebih akurat. Salah satu cara untuk mengetahui kinerja proyek adalah dengan menggunakan pendekatan Probabilistic. Metode yang digunakan dalam tugas akhir ini adalah Probabilistic Earned Value. Metode ini bertujuan untuk mengurangi hambatan atau gangguan pada kegiatan proyek, sehingga prediksi kondisi menjadi lebih akurat. Data yang dibutuhkan antara lain rincian anggaran biaya, time schedule, laporan bulanan, dan biaya aktual. Dari data yang didapatkan tersebut kemudian dilakukan analisis waktu, biaya, varians dan indikator kinerja proyek, serta estimasi biaya untuk menyelesaikan proyek tanpa dan dengan pendekatan probabilistic. Prakiraan biaya penyelesaian sisa pekerjaan atau Estimate to Complete (ETC) dan biaya penyelesaian proyek atau Estimate at Complete (EAC) ditinjau dari tiga kondisi yang berbeda yaitu dalam kondisi optimistic, most likely, dan pessimistic. Dari hasil analisis yang ditinjau setiap bulan diketahui nilai kinerja waktu dengan nilai SPI diperoleh hasil semua kurang dari 1 yang berarti proyek mengalami keterlambatan dari perencanaan awal, serta kinerja biaya dengan nilai CPI diperoleh hasil semua lebih dari 1 yang berarti biaya pelaksanaan proyek lebih kecil dari perencanaan awal. Hasil perhitungan Time Estimated (TE) diperoleh waktu perkiraan akhir adalah 405 hari, dimana proyek mengalami keterlambatan dari jadwal yang direncanakan yaitu 363 hari. Hasil perhitungan Estimate to Complete (ETC) Probabilistic adalah Rp75.555.411.474, serta hasil perhitungan Estimate at Completion (EAC) Probabilistic adalah Rp197.022.299.560 yang menunjukkan bahwa biaya lebih kecil dari nilai kontrak proyek yaitu Rp201.635.083.030. Hasil perbandingan menunjukkan terdapat beberapa nilai ETC dan EAC Probabilistic yang lebih besar dari ETC dan EAC Deterministic. Hal tersebut menunjukkan bahwa perlunya memperhitungkan unsur ketidakpastian dalam melakukan pengendalian proyek agar perhitungan prediksi biaya penyelesaian proyek lebih akurat, serta meminimalisir terjadinya gangguan keuangan proyek.
======================================================================================================================================
The RCC Revitalization RU VI Balongan Project is planned to be completed within 363 days at a cost of Rp. 201.635.083.031. In its implementation, this project has many obstacles that allow the implementation of the project to experience delays and losses. Therefore, it is necessary to analyze time and cost performance, as well as predict time and costs in order to determine what steps to take if there are delays and excessive expenditures from a project. The element of uncertainty or risk contained in project work must also be considered so that when measuring performance and predicting time and costs, more accurate analysis results are obtained. One way to determine project performance is to use a probabilistic approach. The method used in this final project is Probabilistic Earned Value. This method aims to reduce obstacles or disruptions to project activities, so that condition predictions become more accurate. The data needed include details of the budget, time schedule, monthly reports, and actual costs. From the data obtained, then an analysis of time, cost, variance and project performance indicators is carried out, as well as cost estimates to complete the project without and with a probabilistic approach. Estimates of the cost of completing the remaining work or Estimate to Complete (ETC) and project completion costs or Estimate at Complete (EAC) are viewed from three different conditions, namely in optimistic, most likely, and pessimistic conditions. From the results of the analysis that is reviewed every month, it is known that the time performance value with the SPI value is obtained all results are less than 1 which means the project is experiencing delays from the initial planning, and the cost performance with the CPI value is obtained all results are more than 1 which means the project implementation costs are smaller than the planning. beginning. The results of the Time Estimated (TE) calculation obtained that the final estimated time was 405 days, where the project experienced delays from the planned schedule, which was 363 days. The result of the Estimate to Complete (ETC) Probabilistic calculation is Rp. The comparison results show that there are several ETC and EAC Probabilistic values that are greater than the Deterministic ETC and EAC. This shows that it is necessary to take into account the element of uncertainty in project control so that the prediction of project completion costs is more accurate, and minimizes the occurrence of project financial disturbances.
| Item Type: | Thesis (Other) |
|---|---|
| Uncontrolled Keywords: | Kinerja Biaya, Kinerja Waktu, Probabilistic Earned Value, Earned Value Analysis, Cost Performance, Time Performance, Probabilistic Earned Value |
| Subjects: | T Technology > TF Railroad engineering and operation > TF193 Estimates, costs, etc. |
| Divisions: | Faculty of Civil, Planning, and Geo Engineering (CIVPLAN) > Civil Engineering > 22201-(S1) Undergraduate Thesis |
| Depositing User: | Mr. Marsudiyana - |
| Date Deposited: | 14 Jan 2026 03:17 |
| Last Modified: | 14 Jan 2026 03:17 |
| URI: | http://repository.its.ac.id/id/eprint/129594 |
Actions (login required)
![]() |
View Item |