Analisa Percepatan Pembangunan Towermill Pada Proyek Feedmill Di Kabupaten Ngawi Pt. Langgeng Makmur Perkasa Menggunakan Metode Cpm Dan Pert

Darmanto, Dimas Ragil (2022) Analisa Percepatan Pembangunan Towermill Pada Proyek Feedmill Di Kabupaten Ngawi Pt. Langgeng Makmur Perkasa Menggunakan Metode Cpm Dan Pert. Diploma thesis, Institut Teknologi Sepuluh Nopember.

[thumbnail of 10111810013005-Undergraduate_Thesis.pdf] Text
10111810013005-Undergraduate_Thesis.pdf
Restricted to Repository staff only

Download (19MB)

Abstract

Ketepatan waktu adalah salah satu kunci sebuah pelaksanaan konstruksi dikatakan berhasil sesuai dengan jadwal yang telah direncanakan. Penjadwalan proyek dengan berpikir secara mendalam melalui persoalan-persoalan yang ada, masuk ke dalam jalur logika serta menyusun berbagai tugas untuk menghasilkan suatu kegiatan yang lengkap dan menuliskan bermacam-macam kegiatan dengan pikiran yang logis dan rangkaian waktu yang tepat.PT Widodo Makmur Unggas Tbk. melakukan pembangunan Pabrik Feedmill yang berada di Desa Sidolaju, Kecamatan Widodaren, Kabupaten Ngawi, Jawa Timur dengan Total durasi dari proyek pembangunan Tower Feedmill adalah 359 hari dengan total kontrak sebesar Rp 613.784.802.000.00, akan tetapi terjadi keterlambatan dikarenakan adanya pemutusan kerja sama operasi (KSO). Berdasarkan uraian di atas, penulis mencoba melakukan analisa percepatan yaitu proses mempercepat waktu pelaksanaan proyek menggunakan penjadwalan metode CPM yang berguna untuk mengetahui kegiatan yang memiliki kepekaan sangat tinggi atas keterlambatan penyelesaian, maka akan memperlambat penyelesaian waktu proyek secara keseluruhan, meskipun kegiatan lain tidak mengalami keterlambatan dan metode PERT yang berguna untuk membantu merencanakan proyek yang besar dan kompleks, metode ini dimulai dengan evaluasi program secara keseluruhan dan menekankan analisis mendalam terhadap setiap program sebelum program / proyek dimulai. Dalam pengerjaan analisa percepatan ini dilakukan visualisasi proyek yang dibantu dengan Aplikasi Naviswork dan BIM. Dalam penelitian ini akan dipilih alternatif jalur kritis dengan percepatan waktu yang paling optimum. Berdasarkan penelitian yang dilakukan didapatkan durasi total pekerjaan 311 hari dengan percepatan 48 hari atau 8 minggu dari durasi total pekerjaan pada data yang didapatkan.
==============================================================================================================================
Timeliness is one of the keys to a successful construction implementation according to the planned schedule. Scheduling projects by thinking deeply through existing problems, entering into logical paths and compiling various tasks to produce a complete activity and writing various activities with logical thoughts and the right time series. PT Widodo Makmur Unggas Tbk. carried out the construction of a Feedmill Factory located in Sidolaju Village, Widodaren District, Ngawi Regency, East Java with a total duration of the Feedmill Tower construction project is 359 days with a total contract of Rp. (KSO). Based on the description above, the author tries to do an acceleration analysis, namely the process of accelerating project execution time using the CPM method scheduling which is useful for knowing activities that have very high sensitivity to late completion, it will slow down the completion of the overall project time, although other activities do not experience delays and PERT method is useful for helping plan large and complex projects, this method starts with an evaluation of the entire program and emphasizes in-depth analysis of each program before the program / project starts. In this acceleration analysis, project visualization is carried out assisted by Naviswork and BIM applications. In this study, an alternative critical path with the most optimum time acceleration will be selected. Based on the research conducted, the total duration of work was 311 days with an acceleration of 48 days or 8 weeks from the total duration of work in the data obtained.

Item Type: Thesis (Diploma)
Additional Information: RSIS 690.54 Dar a-1 2022
Uncontrolled Keywords: ketepatan waktu, penjadwalan, percepatan, CPM, PERT. timeliness, schedulling, acceleration , CPM and PERT.
Subjects: T Technology > TA Engineering (General). Civil engineering (General)
Divisions: Faculty of Vocational > 22301-Civil Infrastructure Engineering (D4)
Depositing User: Mr. Marsudiyana -
Date Deposited: 13 Jul 2026 04:12
Last Modified: 13 Jul 2026 04:12
URI: http://repository.its.ac.id/id/eprint/134782

Actions (login required)

View Item View Item