Analisa Percepatan Waktu Dan Biaya Dengan Metode Time Cost Trade Off (Tcto) Pada Proyek Pembangunan Gedung Dprd Surabaya

Putro, Alfathan Ario (2022) Analisa Percepatan Waktu Dan Biaya Dengan Metode Time Cost Trade Off (Tcto) Pada Proyek Pembangunan Gedung Dprd Surabaya. Diploma thesis, Institut Teknologi Sepuluh Nopember.

[thumbnail of 10111810013010-Undergraduate_Thesis.pdf] Text
10111810013010-Undergraduate_Thesis.pdf
Restricted to Repository staff only

Download (16MB) | Request a copy

Abstract

Proyek konstruksi membutuhkan suatu metode perancanaan untuk pelaksanaan kegiatan dan penggunaan sumber daya dengan tujuan proyek dapat diselesaikan sesuai waktu yang ditentukan dengan sumber daya sehemat mungkin. Salah satu metode untuk melakukan percepatan proyek konstruksi adalah metode Time Cost Trade Off (TCTO). Time Cost Trade Off (TCTO) merupakan metode yang memiliki tujuan mempercepat durasi proyek dengan penambahan jam kerja, menambah jumlah pekerja, dan menambah alat berat pada kegiatan di jalur kritis. Tugas Akhir ini meninjau proyek pembangunan Gedung DPRD Surabaya sebagai studi kasus untuk melakukan analisa percepatan waktu dan biaya. Gedung DPRD Surabaya memiliki luas 657,6 m2 dan terdiri dari 8 lantai dan 1 basement. Proyek ini dimulai pada bulan Desember 2017 dan rampung pada bulan Oktober 2019 dengan durasi total proyek sebesar 312 hari kalender dengan nilai proyek sebesar Rp18.434.625.063. Skenario percepatan (crashing) yang digunakan pada analisa Time Cost Trade Off (TCTO) pada Tugas Akhir ini adalah penambahan tenaga kerja dan alat berat, dan penambahan shift kerja. Percepatan dilakukan pada item pekerjaan yang berada di lintasan kritis dengan nilai bobot dan durasi yang besar agar menemukan waktu dan biaya yang optimal. Hasil dari analisa percepatan dengan metode Time Cost Trade Off (TCTO) dengan alternatif penambahan shift kerja didapatkan waktu percepatan menjadi 175 hari dari durasi normal 312 hari sehingga dipercepat selama 137 hari dengan total biaya sebesar Rp19.178.140.302. Sedangkan, dengan alternatif penambahan tenaga kerja dan alat berat didapatkan waktu percepatan menjadi 178 hari sehingga dipercepat selama 134 hari dengan total biaya sebesar Rp19.185.769.683.
==============================================================================================================================
Construction projects require a planning method for the implementation of activities and use of resources, with the project's aim being complete within the specified time with the least possible resources. One of the methods to accelerate construction projects is the Time Cost Trade Off (TCTO) method. Time Cost Trade Off (TCTO) is a method that aims to accelerate project duration by increasing working hours, increasing the number of workers, and adding heavy equipment to activities on the critical path. This final project reviews the Surabaya DPRD construction project as a case study to analyze time and cost acceleration. The Surabaya DPRD building has an area of 657.6 m2 and consists of 8 floors and one basement. This project started in December 2017 and was completed in October 2019 with a total project duration of 312 calendar days with a project value of Rp. 18.434.625.063. The acceleration scenario (crashing) used in the Time Cost Trade Off (TCTO) analysis in this Final Project is the addition of labor and heavy equipment and the addition of work shifts. Acceleration is carried out on work items on a critical path with a large weight value and the longest duration to find the optimal time and cost. The results of the acceleration analysis using the Time-Cost Trade-Off (TCTO) method using the alternative of adding work shifts, the acceleration time is 175 days from the normal duration of 312 days, so it is accelerated to 137 days with a total cost of Rp19.178.140.302. Meanwhile, with the alternative addition of labor and heavy equipment, the acceleration time is 178 days, so it is accelerated for 134 days with a total cost of Rp19.185.769.683.

Item Type: Thesis (Diploma)
Additional Information: RSIS 692.5 Put a-1 2022
Uncontrolled Keywords: Time Cost Trade Off (TCTO), Crashing, Percepatan Waktu, Durasi, Lintasan Kritis. Time Cost Trade Off (TCTO), Crashing, Acceleration, Duration, Critical Path.
Subjects: T Technology > TA Engineering (General). Civil engineering (General)
Divisions: Faculty of Vocational > 22301-Civil Infrastructure Engineering (D4)
Depositing User: Mr. Marsudiyana -
Date Deposited: 13 Jul 2026 04:30
Last Modified: 13 Jul 2026 04:30
URI: http://repository.its.ac.id/id/eprint/134784

Actions (login required)

View Item View Item