Ridhoni, Faricha Aulia (2026) Analisis Perbandingan Waktu dan Biaya Pekerjaan Bekisting Konvensional dan Aluminium Formwork dengan Pendekatan Building Information Modelling (BIM) 4D Pada Proyek Pembangunan Gedung Health Science Universitas Airlangga. Diploma thesis, Institut Teknologi Sepuluh Nopember.
|
Text
2035221025-Undergraduate_Theses.pdf Restricted to Repository staff only Download (9MB) | Request a copy |
Abstract
Pada proyek gedung bertingkat, pekerjaan bekisting berpengaruh terhadap kualitas beton, durasi pekerjaan struktur, biaya pelaksanaan, dan limbah material. Kondisi eksisting proyek menggunakan bekisting konvensional yang memerlukan fabrikasi di lapangan, durasi relatif lebih lama, serta berpotensi menghasilkan permukaan beton yang kurang seragam dan limbah material lebih tinggi. Aluminium formwork digunakan sebagai alternatif karena menggunakan panel modular dengan sistem knock-down, dapat digunakan berulang, menghasilkan permukaan beton lebih rapi, dan mempercepat siklus pekerjaan. Penelitian ini bertujuan membandingkan metode pelaksanaan, waktu, dan biaya pekerjaan bekisting konvensional dan aluminium formwork dengan pendekatan Building Information Modeling (BIM). BIM 3D digunakan untuk pemodelan dan quantity take off, sedangkan BIM 4D digunakan untuk mengintegrasikan model dengan jadwal serta memvisualisasikan tahapan pelaksanaan. Berdasarkan asumsi waktu kerja 8 jam perhari, aluminium formwork membutuhkan 296 hari kerja, sedangkan bekisting konvensional membutuhkan 331 hari kerja, sehingga lebih cepat 35 hari atau 10,57%. Dari aspek biaya, aluminium formwork membutuhkan Rp. 74.668.862.574,87, sedangkan bekisting konvensional Rp. 64.668.867.028,48, sehingga selisih Rp. 9.999.995.546,38 atau 7%. Hasil penelitian menunjukkan bahwa aluminium formwork lebih efektif dari aspek waktu, sedangkan bekisting konvensional lebih ekonomis dari aspek biaya. Pemilihan metode perlu mempertimbangkan target waktu, biaya, tingkat pengulangan struktur, kondisi proyek, ketersediaan tenaga kerja, dan penggunaan ulang material.
=====================================================================================================================================
In multi-story building projects, formwork operations influence concrete quality, the duration of structural work, implementation cost, and material waste. Under existing conditions, the project employs conventional formwork, which requires on-site fabrication, results in a relatively longer duration, and has the potential to produce less uniform concrete surfaces along with a higher volume of material waste. Aluminium formwork is employed as an alternative,
as it utilizes modular panels with a knock-down system, can be reused repeatedly, produces a neater concrete surface, and accelerates the work cycle. This study aims to compare the implementation method, time, and cost of conventional formwork and aluminium formwork using a Building Information Modeling (BIM) approach. 3D BIM is used for modeling and quantity takeoff, while 4D BIM is used to integrate the model with the schedule and to visualize the implementation stages. Based on the assumption of an 8-hour working day, aluminium formwork requires 296 working days, whereas conventional formwork requires 331 working days, making it 35 days, or 10.57%, faster. In terms of cost, aluminium formwork requires IDR 74.668.862.574,87, while conventional formwork requires IDR 64.668.867.028,48, resulting in
a difference of IDR 9.999.995.546,38, or 7%. The results indicate that aluminium formwork is more effective in terms of time, whereas conventional formwork is more economical in terms of cost. The selection of method needs to take into account the time target, cost, degree of structural repetition, project conditions, labor availability, and material reuse.
| Item Type: | Thesis (Diploma) |
|---|---|
| Uncontrolled Keywords: | Aluminium Formwork, Bekisting Konvensional, Biaya, Waktu, Buidling Information Modelling (BIM) |
| Subjects: | T Technology > TH Building construction > TH437 Building--Cost control. T Technology > TH Building construction > TH438.13 Building information modeling. |
| Divisions: | Faculty of Civil Engineering and Planning > Civil Engineering > 22301-(D4) Diploma 4 |
| Depositing User: | Faricha Aulia Ridhoni |
| Date Deposited: | 31 Jul 2026 04:27 |
| Last Modified: | 31 Jul 2026 04:27 |
| URI: | http://repository.its.ac.id/id/eprint/140153 |