Maulana, Hanif (2026) Analisis Perbandingan Bekisting Konvensional dengan Bekisting Aluminium ditinjau dari Aspek Waktu dan Biaya dengan BIM (Building Information Modeling) pada Proyek Emerald Tower BNI PIK 2. Other thesis, Institut Teknologi Sepuluh Nopember.
|
Text
2035241088-Undergraduate_Thesis.pdf - Accepted Version Restricted to Repository staff only Download (17MB) | Request a copy |
Abstract
Proyek konstruksi merupakan sektor yang kompleks dan penuh tantangan, terutama dalam pengendalian waktu dan biaya pelaksanaan proyek. Salah satu komponen yang paling menentukan dalam pekerjaan struktur beton adalah sistem bekisting, karena kegunaannya sebagai pencetak beton terus berulang sepanjang siklus konstruksi. Dalam praktiknya,
pemilihan jenis bekisting sangat memengaruhi durasi dan biaya pelaksanaan proyek. Oleh karena itu, penulis melakukan penelitian untuk menganalisis pengaruh pemilihan jenis
bekisting terhadap efisiensi waktu dan biaya pelaksanaan proyek. Pada proyek akhir ini, penulis akan memberikan upaya penerapan membahas perbandingan penggunaan bekisting
konvensional dan bekisting aluminium pada Proyek Emerald Tower BNI PIK 2 ditinjau dari aspek waktu dan biaya dengan penerapan Building Information Modeling (BIM). serta
menggunakan teknologi BIM sebagai kontrol volume pekerjaan dan visualisasi estimasi waktu pekerjaan. Proyek ini mencakup pekerjaan struktur mulai dari lantai dasar hingga lantai 10 yang meliputi pekerjaan kolom, shearwall, balok, dan plat lantai yang memiliki struktur tipikal pada
setiap lantai dengan acuan teori-teori terkait perhitungan waktu dan biaya. Dari hasil analisis proyek akhir ini, Pembangunan Proyek Emerald Tower BNI PIK 2 dengan menggunakan metode BIM dan bekisting konvensional dapat diselesaikan dalam waktu 116 hari kerja dengan biaya sebesar Rp20.488.218.473,75. Sementara itu, penggunaan metode BIM dan bekisting aluminium dapat menyelesaikan proyek dalam waktu 106 hari kerja dengan biaya sebesar RpRp21.119.614.407,23. Dari perbandingan kedua metode tersebut dapat diketahui bahwa penggunaan bekisitng aluminium dapat mempercepat konstruksi sebesar 8,62%, namun
membutuhkan biaya 3,69 % lebih tinggi dibandingkan dengan metode bekisting konvensional.
=================================================================================================================================================
The Construction projects are complex and challenging sectors, especially in controlling the time and cost of project implementation. One of the most determining components in concrete structure work is the formwork system, because its use as a concrete molder continues to be repeated throughout the construction cycle. In practice, the choice of formwork type greatly affects the duration and cost of project implementation. Therefore, the author conducted a study to analyze the effect of formwork type selection on the efficiency of time and cost of project implementation. In this final project, the author will provide an application effort discussing the comparison of the use of conventional formwork and aluminum formwork in the Emerald Tower BNI PIK 2 Project in terms of time and cost aspects with the application of Building Information Modeling (BIM). as well as using BIM technology as a control of work volume and visualization of work time estimates. This project includes structural work from the ground floor to the 10th floor which includes column work, shearwall, beams, and floor slabs that have a typical structure on each floor with reference to theories related to time and cost calculations. From the results of this final project analysis, the construction of the Emerald Tower BNI PIK 2 Project using the BIM method and onventional formwork can be completed within 116 working days at a cost of Rp20.488.218.473,75. Meanwhile, the use of the BIM method and aluminum formwork can complete the project within 106 working days at a cost of Rp21.119.614.407,23. From the comparison of the two methods, it can be seen that the use of aluminum formwork can speed up construction by 8,62%, but requires a 3,69% higher cost compared to the conventional formwork method.
| Item Type: | Thesis (Other) |
|---|---|
| Uncontrolled Keywords: | BIM (Building Information Modeling), Bekisting Aluminium, Penjadwalan Pekerjaan, Estimasi Biaya ======================================================================================================================== BIM (Building Information Modeling), Aluminum Formwork, Job Scheduling, Cost Estimation |
| Subjects: | T Technology > TA Engineering (General). Civil engineering (General) |
| Divisions: | Faculty of Vocational > 22301-Civil Infrastructure Engineering (D4) |
| Depositing User: | Hanif Maulana |
| Date Deposited: | 04 Aug 2026 08:35 |
| Last Modified: | 04 Aug 2026 08:35 |
| URI: | http://repository.its.ac.id/id/eprint/143604 |
Actions (login required)
![]() |
View Item |