Putra, Ilham Prakasa (2017) Perbandingan Biaya Dan Waktu Pemakaian Tower Crane Dan Mobile Crane Pada Proyek Pembangunan RSUD Syarifah Ambami Rato Ebu Bangkalan. Undergraduate thesis, Institut Teknologi Sepuluh Nopember.
Preview |
Text
3114106050 - Undergraduate_Thesis.pdf - Published Version Download (25MB) | Preview |
Abstract
Dalam suatu proyek pekerjaan konstruksi gedung, keuntungan yang didapat serta ketepatan waktu dalam penyelesaian suatu proyek merupakan kunci keberhasilan dari proyek tersebut. Kedua hal tersebut bergantung pada perencanaan yang cermat terhadap metode pelaksanaan , penggunaan alat, maupun penjadwalan. Perencanaan yang kurang baik akan mengakibatkan bermacam-macam persoalan dan masalah yang menjurus pada kerugian. Pemilihan jenis peralatan yang akan digunakan akan mempengaruhi kinerja dari pekerjaan suatu proyek. Peralatan dianggap memiliki kapasitas tinggi bila peralatan tersebut menghasilkan produksi yang tinggi atau optimal tetapi dengan biaya yang rendah. Oleh karena itu diperlukan suatu analisa terhadap pemakaian alat berat yang akan digunakan, sehingga dapat diperoleh alat berat yang paling optimum untuk pekerjaan suatu proyek konstruksi.
Pada proyek pembangunan Gedung Utama dan Poli pada RSUD Syarifah Ambemi Rato Ebu ini, alat berat yang digunakan untuk pekerjaan struktur beton adalah Tower Crane (TC) dan Concrete Pump (CP). Sedangkan Mobile Crane direncanakan sebagai pengganti Tower Crane dalam pelaksanaan pekerjaan struktur. Langkah perhitungan dibagi menjadi dua tahap, yaitu perhitungan waktu pelaksanaan peralatan dan perhitungan biaya peralatan. Untuk menghitung waktu pelaksanaan langkah yang diambil adalah menghitung dan menentukan beban kerja alat, kapasitas dan produktivitasnya dari perlatan yang digunakan. Sedangkan dalam menentukan biaya pelaksanaan yang diperhitungkan adalah biaya sewa, biaya mobilisasi dan demobilisasi, biaya peralatan penunjang serta biaya operasi alat yang meliputi bahan bakar, pelumas, pemeliharaan dan operator. Dari perhitungan waktu dan biaya pelaksanaan alat dan ditinjau dari segi waktu dan biaya pelaksanaan.
Dari hasil perhitungan yang telah dilakukan didapatkan bahwa lama waktu pekerjaan struktur dengan menggunakan kombinasi Tower crane + Concrete pump adalah 191 jam dengan biaya pelaksanaan sebesar Rp.367.972.958. sedangkan lama waktu pekerjaan struktur dengan menggunakan kombinasi Mobile crane + Concrete pump adalah 199 jam dengan biaya pelaksanaan sebesar Rp.134.252.745. Sehingga dapat disimpulkan bahwa waktu tercepat untuk pelaksanaan pekerjaan pengecoran dan pengangkatan material adalah kombinasi pemakaian Tower crane + Concrete pump dengan selisih waktu pemakaian 8 jam, sedangkan untuk biaya termurah adalah kombinasi pemakaian Mobile crane + Concrete pump dengan selisih biaya Rp.232.720.213.
=========================================================
In a building construction project, the benefits and timeliness in completing a project is key to the success of the project. Both of these rely on careful planning to the implementation method, the use of the tool, as well as scheduling. Improper planning will lead to a variety of issues and problems that lead to losses. Selection of the type of equipment to be used will affect the performance of work on a project. Equipment is considered to have a high capacity when the equipment produces a high production or optimal but at a lower cost. Therefore we need an analysis of the use of heavy equipment to be used, so as to obtain the most optimum machine for the job of a construction project.
On development projects in the Main Building and Poli RSUD Syarifah Ambemi Rato Ebu, heavy equipment is used to work the concrete structure is Tower Crane and Concrete Pump. While Mobile Crane Crane Tower is planned as a replacement for the implementation of the work structure. Step calculation is divided into two stages, namely the calculation of the execution time of equipment and calculation of the cost of equipment. To calculate the time of execution of the steps taken is to calculate and determine the work load of tools, capacity and productivity of the equipment used. Whereas in determining the costs of implementation are taken into account is the cost of the rental, mobilization and demobilization costs, equipment costs and operating costs of supporting tools which include fuel, lubricants, maintenance and operator. From the timing and cost of implementation tools and in terms of time and cost of implementation.
From the results of calculations have been done a long time it was found that using a combination of structural work Tower crane + Concrete Pump is 191 hours with costs of implementation of Rp.367.972.958. whereas the length of time the job structure by using a combination of Mobile cranes + Concrete Pump is 199 hours with costs of implementation of Rp.134.252.745. It concluded that the fastest time for the implementation of foundry work and the removal of material is a combination of the use of Tower crane + Concrete pump with a time difference of 8 hours usage, while for the lowest cost is a combination of the use of Mobile cranes + Concrete pump with Rp.232.720.213 cost difference.
Item Type: | Thesis (Undergraduate) |
---|---|
Uncontrolled Keywords: | Alat Berat, Biaya dan Waktu, Tower Crane, Mobil Crane, Concrete Pump, Mobilisasi dan Demobilisasi. |
Subjects: | T Technology > T Technology (General) T Technology > TA Engineering (General). Civil engineering (General) |
Divisions: | Faculty of Civil Engineering and Planning > Civil Engineering > 22201-(S1) Undergraduate Thesis |
Depositing User: | Ilham Prakasa Putra |
Date Deposited: | 01 Mar 2017 03:49 |
Last Modified: | 05 Mar 2019 02:35 |
URI: | http://repository.its.ac.id/id/eprint/1968 |
Actions (login required)
View Item |