., Fadllan (2017) Analisis Optimasi Waktu Dan Biaya Dengan Metode Time Cost Trade Off Pada Proyek Pembangunan Kapal: Studi Kasus Pembangunan Kapal Kelas I Kenavigasian Di Galangan Kapal Batam, Kepulauan Riau. Undergraduate thesis, Institut Teknologi Sepuluh Nopember.
Preview |
Text
4212100123-Undergraduate_Theses.pdf - Published Version Download (7MB) | Preview |
Abstract
Keterlambatan proyek merupakan permasalahan yang sudah sering terjadi. Dalam proyek pembagunan kapal, keterlambatan penyelesaian proyek pembangunan kapal berarti pihak galangan kapal harus membayar denda keterlambatan sesuai perjanjian kontrak dengan pemilik kapal. Pembangunan proyek Pembangunan Kapal Kelas I Kenavigasian ini mengalami keterlambatan. Berdasarkan laporan pencapaian progress fisik yang dirilis pada bulan Agustus 2016, kinerja total proyek mencapai 10% dari target awal sebesar 11%. Proyek ini diperkirakan mengalami keterlambatan selama 1 bulan. Pihak galangan kapaldituntut oleh pemilik kapal untuk menyelesaikan proyek tepat waktu. Salah satu solusi yang bisa dilakukan untuk mengatasi keterlambatan proyek adalah dengan melakukan percepatan durasi pengerjaan proyek. Akan tetapi, percepatan durasi harus diperhitungkan secara teliti agar proyek dapat selesai tepat waktu dan biaya tambahan yang dikeluarkan sebagai konsekuensi dari pengurangan durasi tidak membengkak. Tugas Akhir ini menggunakan metode Time Cost Trade Off (TCTO) sebagai solusi untuk mengatasi keterlambatan, yaitu metode penjadwalan proyek dengan melakukan pertukaran waktu dan biaya. Metode ini bertujuan untuk mempercepat waktu penyelesaian proyek yang sedang berjalan dengan penambahan biaya yang optimum terhadap kegiatan yang dipercepat waktu pekerjaannya melalui penerapan alternatif percepatan. Metode ini akan diterapkan pada proses pengerjaan Hull dan Outfitting pembangunan Kapal Kelas 1 Kenavigasian dengan alternatif percepatan yang diterapkan pada Tugas Akhir ini yaitu menambah jam kerja atau lembur dan menambah jumlah pekerja. Dari hasil analisis dengan metodeTime Cost Trade Off ini didapatkan hasil bahwa pada pembangunan Kapal Kelas I Kenavigasian dilakukan percepatan selama 23 hari, dari total durasi proyek yang normalnya selama 225 hari menjadi 201 hari dengan penambahan biaya sebesar Rp 767. 198.468,28. ===================================================================================================== Delay is a common problem in a project. In case of shipbuilding project, the delay in project completion means that the shipyard has to pay a penalty corresponding to contractual agreement with the ship owner.
The Construction of The Class I Navigation Ship Building Project has delayed. Based on the physical progress
report on August 2016, the total of project performance reached 10% from the initial target of 11%.
The project was estimated to be delayed for 1 month. The shipyard was expected to complete the project on time by ship owner. One of the solutions to overcome project
delay problem is to accelerate the project completion time. However, time acceleration must be done carefully so the project can be completed on time with less additional cost. Time Cost Trade Off (TCTO) is proposed
to reduce potential construction delay. The method will try to find the most efficient construction schedule
by trading off time and cost. The objective of Time Cost Trade Off is to accelerate project completion time. It can be achieved by adjusting the activities and their associate cost. This method will be implemented in
Class 1 Navigation Ship Hull and Outfitting process. Issue
s to be considered are executing overtime and labor additiion as acceleration alternatives. The results of the case study showed that the construction of The Class I Navigation Ship Building Project could be accelerated for 23 days. The construction project could be finished in 232 days by addding cost of Rp 767. 198.468,28. It reduced the delay by 23 days from previously estimated 30 days to only 3 days delay.
Item Type: | Thesis (Undergraduate) |
---|---|
Uncontrolled Keywords: | Proyek pembangunan kapal; percepatan penyelesaian proyek; TCTO; Shipbuilding project; accelerated project completion |
Subjects: | V Naval Science > VM Naval architecture. Shipbuilding. Marine engineering |
Divisions: | Faculty of Marine Technology (MARTECH) > Marine Engineering > 36202-(S1) Undergraduate Thesis |
Depositing User: | FADLLAN . |
Date Deposited: | 04 Apr 2017 06:38 |
Last Modified: | 04 Apr 2017 06:38 |
URI: | http://repository.its.ac.id/id/eprint/2850 |
Actions (login required)
View Item |