Manajemen Pelaksanaan Ditinjau Dari Penjadwalan Sumberdaya Dan Rencana Anggaran Biaya Pada Pembangunan Apron Bandar Udara Abdul Rachman Saleh Malang

Azzam, Abdullah (2017) Manajemen Pelaksanaan Ditinjau Dari Penjadwalan Sumberdaya Dan Rencana Anggaran Biaya Pada Pembangunan Apron Bandar Udara Abdul Rachman Saleh Malang. Diploma thesis, Institut Teknologi Sepuluh Nopember.

[thumbnail of 3115040613-Undergraduate_Theses.pdf]
Preview
Text
3115040613-Undergraduate_Theses.pdf

Download (31MB) | Preview

Abstract

Pada pelaksanaan konstruksi proyek pembangunan apron bandar udara Abdulrachman Saleh Malang dengan luas bangunan 11000 m², pekerjaan utamanya adalah pekerjaan pondasi timbunan tanah, pekerjaan kosntruksi beton, pekerjaan drainase, dan pekerjaan finishing.
Pada pengerjaan Proyek Akhir ini, penulis menghitung atau melakukan estimasi waktu dan biaya pada pembangunan apron bandar udara Abdulrachman Saleh Malang.
Berdasarkan hasil analisa proyek akhir ini pekerjaan yang tidak boleh terlambat (kritis) adalah pembuatan direksi keet, pekerjaan pengukuran, pekerjaan pembutan pagar, mobilisasi alat, pekerjan clearing, pekerjaan urugan tanah dasar, pekerjaan sirtu dan subbase, pekerjaan base courses, pekerjaan union pipa cap, pekerjan begesting pelat besi, pekerjan beton K400, pekerjaan curing beton, pekerjaan marking, dan join sealant dapat diselesaikan selama ± 5 bulan dan membutuhkan biaya sebesar Rp. 13,293,585,873.17

===============================================================================================
On the implementation of construction Apron in Abdulrachman Saleh Malang airport with an area. Construction is 11000 m2, concentrated work is worked fill, concreated work, drain work and finishing work.
In theFinal Project, writer calculate estimate time and cost Apron in Abdulrachman Saleh Malang airport.
Based on the analysis of this final project, the work can’t late (Critical) is makes keet, work measurement, the manufacture of the fence, the mobilization of heavy equipment, Clearing Area, the work of the earthwork base, the sub-base work, the base courses work, the union pipe cap work, the formwork iron plates, the concrete K400 work, watering concrete, marking and join sealant. The Apron project Can finish in 5 months and need cost Rp.13,293,585,873.17

Item Type: Thesis (Diploma)
Uncontrolled Keywords: Apron, biaya, konstruksi, waktu
Subjects: T Technology > TA Engineering (General). Civil engineering (General)
T Technology > TH Building construction > TH437 Building--Cost control.
Divisions: Faculty of Civil Engineering and Planning > Civil Engineering > 22301-(D4) Diploma 4
Depositing User: ABDULLAH AZZAM
Date Deposited: 11 Apr 2017 06:42
Last Modified: 16 Apr 2024 06:19
URI: http://repository.its.ac.id/id/eprint/3291

Actions (login required)

View Item View Item