Evaluasi Kebutuhan Luasan Apron Pada Rencana Pengembangan Bandar Udara Internasional Ahmad Yani Semarang

Nursalim, Muhammad (2017) Evaluasi Kebutuhan Luasan Apron Pada Rencana Pengembangan Bandar Udara Internasional Ahmad Yani Semarang. Undergraduate thesis, Institut Teknologi Sepuluh Nopember.

[thumbnail of 3114106034-Undergraduate-Theses.pdf]
Preview
Text
3114106034-Undergraduate-Theses.pdf - Accepted Version

Download (7MB) | Preview

Abstract

Bandar Udara Ahmad Yani akan memiliki terminal yang lebih luas di sebelah Utara runway, lahan parkir yang luas, apron seluas 61.344 m2 serta dua buah taxiway. Pengembangan tahap II akan menjadikan Bandar Udara Ahmad Yani memiliki apron seluas 72.522 m2 dan 10 buah taxiway serta 1 buah parallel taxiway.
Tugas Akhir ini akan mengevaluasi kebutuhan apron Bandar Udara internasional Ahmad Yani Semarang saat ini dan 20 tahun kedepan. Pada evaluasi ini akan diprediksi jumlah pergerakan pesawat pada tahun rencana yang kemudian akan dikonversi menjadi jumlah pesawat pada jam sibuk. Hasil prediksi jumlah pesawat ini akan dianalisis terhadap kebutuhan apron Bandar Udara Ahmad Yani di tahun rencana.
Dengan adanya pengembangan apron dapat memenuhi kebutuhan lalu lintas udara. Pertambahan luasan apron berarti bertambahnya beban sehingga perlu perencanaan ulang tebal perkerasan. Untuk perencanaan perkerasan apron menggunakan rigid pavement dengan software FAARFIELD.
Dari hasil perhitungan didapatkan, kebutuhan total jumlah gerbang landas parkir untuk tahun rencana (2035) adalah 51 pesawat, yang terdiri dari 35 kelas C dan 16 kelas D. Selanjutnya didapatkan dimensi gerbang landas parkir pada tahun rencana (2035) adalah untuk kelas C dengan panjang 2096,50 m dan lebar 98,37 m sedangkan untuk kelas D dengan panjang 1547,20 m dan 104,78 m. Tebal perkerasan landas parkir ini adalah 670 mm. Dalam penulangan perkerasan landas parkir tahun rencana (2035) dibutuhkan wiremesh dengan D14-100 dan Dowel dengan diameter 50 mm, panjang 610 mm, dan jarak 460 mm.

=================================================================

Ahmad Yani Airport a wider space in the north runway, large parking space, covering an area of 61 344 m2 apron and two taxiways. Development of the second phase will make the Ahmad Yani Airport has the 72 522 m2 of apron area and 10 taxiways with 1 parallel taxiway.
This study attempts to evaluate the apron need of the international Ahmad Yani Airport in Semarang today and for the next 20 years. This evaluation predicted the number of aircraft movements in the planed year which will then be converted into the number of aircraft at peak hours. The results of the predicted number of these aircrafts will be analyzed in relation to the need of the airport apron of Ahmad Yani in the year plan.
The development of apron is expected to serve the needs of air traffic. Bulge area of the apron means increasing burden that needs to replan pavement thickness. For the planning of the apron pavement using rigid pavement method using FAARFIELD software.
From the obtained calculation results, the total number of gates need to park off in year plan (2035) was 51 aircraft, consisting of 35 class C and 16 class D. Subsequently dimensions obtained landing gate parking in the plan (2035) was for a class C with a length 2096,50 m and a width of 98,37 m, while for class D with a length of 1547,20 m and 104,78 m. Parking off pavement thickness is 670 mm.In the reinforcement of parking landing pavement for year plan (2035) takes wiremesh with D14-100 and diameters Dowel 50 mm, length 610 mm, and space of Dowel 460 mm.

Item Type: Thesis (Undergraduate)
Uncontrolled Keywords: Kebutuhan Apron; Kapasitas Apron; Pergerakan Pesawat Tahun Rencana; Perkerasan dengan Software FAARFIELD; Apron Capacity; Aircraft Movements Year Plan
Subjects: T Technology > TA Engineering (General). Civil engineering (General)
T Technology > TE Highway engineering. Roads and pavements > TE7 Transportation--Planning
Divisions: Faculty of Civil Engineering and Planning > Civil Engineering > 22201-(S1) Undergraduate Thesis
Depositing User: MUHAMMAD NURSALIM
Date Deposited: 18 Apr 2017 08:24
Last Modified: 08 May 2020 06:36
URI: http://repository.its.ac.id/id/eprint/3573

Actions (login required)

View Item View Item