Analisa Termodinamika Pengaruh Aliran Massa Ekstraksi Turbin Uap Bagian High Pressure Untuk Feedwater Heater Terhadap Performa Pembangkit Listrik Tenaga Uap 200 Mw Pt. Pjb Gresik

Simamora, Rizky Yusuf Fernando (2015) Analisa Termodinamika Pengaruh Aliran Massa Ekstraksi Turbin Uap Bagian High Pressure Untuk Feedwater Heater Terhadap Performa Pembangkit Listrik Tenaga Uap 200 Mw Pt. Pjb Gresik. Undergraduate thesis, Institut Teknologi Sepuluh Nopember.

[thumbnail of 2108100099-undergraduate thesis.pdf]
Preview
Text
2108100099-undergraduate thesis.pdf - Published Version

Download (2MB) | Preview

Abstract

Salah satu jenis pembangkit yang banyak di gunakan
adalah pembangkit listrik tenaga uap (PLTU) yang bekerja
dengan siklus Rankine. Salah satu cara meningkatkan effisiensi
dari sebuah PLTU adalah dengan menambahkan feedwater
heaters (FWH) ke dalam sistem, yang bermaksud meningkatkan
temperatur air yang akan dipanaskan di dalam boiler, sehingga
uap keluaran dari boiler bias memiliki temperatur yang lebih
tinggi dibandingkan tanpa FWH. Energi yang digunakan FWH
berasal dari ekstraksi turbin uap, dengan jumlah aliran massa
dan tekanan tertentu. Proses ektraksi yang kurang tepat dapat
mengakibatkan effisiensi turbin menurun dan dapat
mengakibatkan efesiensi pembangkit menurun. Sehingga
diperlukan studi lebih lanjut untuk mengetahui komposisi yang
tepat pada ekstraksi turbin uap.
Penilitian mengenai pengaruh aliran massa dan tekanan
ekstraksi turbin uap ini dilakukan dengan perhitungan yang
digunakan menggunakan standar ASME PTC 6 untuk Performa
Turbin Uap dan. Perhitungan performa pertama dilakukan pada
model PLTU 200 MW dengan 3 buah turbin (high pressure,
intermediate pressure, dan low pressure) dengan 8 FWH. Metode
variasi persentase ekstraksi steam dilakukan berdasarkan standar
General Electric yaitu aliran massa untuk FWH1 dan FWH2
yang diambilkan dari ekstrasi uap turbin high pressure
divariasikan diawali dengan persentase 5% HPH1 dan 11%
HPH2. Kemudian, 6% HPH1 dan 10% HPH2, 8% HPH1 dan 8%
HPH2(kondisi eksisting), dan variasi dibalik untuk HPH1 dan
HPH2 secara berurutan.
Kondisi eksisting PLTU unit tiga PT. PJB Gresik
memiliki efisiensi boiler 89.21% , heat rate 8554.15 kJ/kW.hr,
dan suhu flue gas adalah 130.29 0C. Pengaruh variasi jumlah
ekstraksi aliran massa uap terhadap performa pembangkit adalah
apabila ekstraksi uap untuk HPH1 sedikit dan HPH2 banyak
berdampak heat rate naik (buruk) karena bahan bakar yang
diperlukan lebih banyak untuk memanaskan air menjadi uap
walaupun daya yang dihasilkan tinggi, misal variasi ekstraksi 5-
11, dan sebaliknya apabila ekstraksi uap untuk HPH1 banyak
dan HPH2 sedikit berdampak heat rate juga naik karena daya
yang dihasilkan pembangkit turun, misal variasi 11-5. Oleh
karena itu, pemilihan pembangkit berdasarkan nilai heat rate
adalah pembangkit dengan ekstraksi 8-8 sebagai pembangkit
yang terbaik.
============================================================================================
One of the most type of plant is the steam power plant
(PLTU) which works with the rankine cycle. One way to improve
the efficiency of the power plant is addedfeedwater heaters
(FHW) into the system. So that the steam output of the boiler can
have a higher temperature than before. The energy which used by
FHW comes from steam turbine with certain mass flow and
pressure. Wrong extraction process can decreased turbine
efficiency and the result will make the plant efficiency
decrease.So that further study is needed to determine the exact
composition of the extraction steam turbine.
The research about the effect of mass flow and pressure
from steam turbine extraction is done by using a standart
calculation ASME PTC 6 for steam turbine and the first
performance calculation performed on the model plant of 200
MW with three tubines (high pressure, intermediate pressure, and
low pressure) with 8 FWH. Percentage variation of steam
extraction method is based on standard General Electric mass
flow for HPH1and HPH2 were taken from the extraction of high
pressure steam turbine varied begins with a percentage of HPH1
5% and HPH2 11%. Then, HPH1 6% and HPH2 10%, HPH1 8%
and HPH2 8% (as an existing condition), and the variation is
reversed for HPH1 and HPH2 sequentially.
The existing condition of power plant unit III PT. PJB
Gresik has 89.21% boiler efficiency, heat rate 8554.15 kJ/kW.hr.
the flue gas temperature 130.29 oC.The influence of variations in
the amount of extraction steam mass flow to the plant's
performance in bad condition when steam extraction for HPH1
less then HPH2 so that the impact heat rate will increase because
needed more fuel to converting the water become steam
eventough its have high power, eg extraction 5-11. Therefore, the
best plant is the plant which have extraction value 8-8 because its
have the lowest value of heat rate.

Item Type: Thesis (Undergraduate)
Additional Information: RSM 621.402 2 Sim a
Uncontrolled Keywords: Mass Flow,Steam Turbine Extraction, Feedwater Heaters, Plant performance
Subjects: T Technology > TJ Mechanical engineering and machinery
T Technology > TJ Mechanical engineering and machinery > TJ164 Power plants--Design and construction
T Technology > TJ Mechanical engineering and machinery > TJ230 Machine design
Divisions: Faculty of Industrial Technology > Mechanical Engineering > 21201-(S1) Undergraduate Thesis
Depositing User: Mr. Tondo Indra Nyata
Date Deposited: 08 Jun 2017 05:26
Last Modified: 24 Aug 2018 06:53
URI: http://repository.its.ac.id/id/eprint/41531

Actions (login required)

View Item View Item