Alternatif Perencanaan Struktur Scale Pit Dan Metode Pelaksanaannya Pada Project Pabrik Baja PT Gunawan Dianjaya Steel Tbk Margomulyo Surabaya

Desianto, Muhammad Alfa Rizal (2016) Alternatif Perencanaan Struktur Scale Pit Dan Metode Pelaksanaannya Pada Project Pabrik Baja PT Gunawan Dianjaya Steel Tbk Margomulyo Surabaya. Undergraduate thesis, Institut Teknologi Sepuluh Nopember.

[img]
Preview
Text
3113105036-Undergraduate-Theses.pdf

Download (5MB) | Preview

Abstract

Direncanakan kedalaman scale pit -8m panjang 56,7m dan lebar 6,8m. mengingat lokasi proyek ini terletak berdekatan dinding pembatas lahan (lahan terbatas) berada di atas tanah lempung yang memiliki sifat kembang susut, dan kandungan air yang tinggi, serta daya dukung yang rendah maka perlunya perencanaan yang tepat untuk menentukan alterntif perencanaan yang efesian dan metode pelaksanaan baik dari segi mutu, biaya. Melihat kondisi yang harus dipertimbangkan seperti di atas, maka diperlukan adanya dinding penahan tanah sekaligus mampu menahan beban yang terjadi. Pada tugas akhir ini direncanakan alternatif konstruksi scale pit dan konstruksi pelaksanaan serta merencanakan metode pelaksaannya. Alternatif konstruksi yang pertama adalah dinding penahan tanah diaphragm wall tanpa menggunakan PVD sebelumnya, dan Alternatif konstruksi yang kedua adalah dinding penahan tanah diaphragm wall dengan menggunakan PVD sebelumnya. Struktur tersebut dapat berperan sebagai dinding penahan tekanan tanah lateral (dinding scale pit). Dari kedua alternatif yang direncanakan, diperoleh Alternatif 1 (Diaphragm Wall tanpa PVD) kedalaman total dinding sedalam 21 m dengan tebal 60 cm. Menggunakan Tulangan Utama D22 – 150, Tulangan Melintang D19 – 150 dan Tulangan geser Ø10 dengan jarak 150. Alternatif 2 (Kombinasi Diaphragm Wall dan PVD) kedalaman total dinding sedalam 21 m dengan tebal 50 cm. Menggunakan Tulangan Utama D22 – 200, Tulangan Melintang D19 – 150, dan Tulangan geser Ø10 dengan jarak 150. Dipilih pola pemasangan PVD segitiga dengan jarak 0,8 meter dengan waktu yang diperlukan untuk konsolidasi adalah 11 minggu. Dalam merencanakan tebal pelat lantai basement ini harus mempertimbangkan gaya uplift dan tekanan air yang diterima oleh pelat lantai ini. Tebal pelat 70 cm, dengan menggunakan tulangan arah x D22-250 mm dan tulangan y D19- 200 mm. Perencanaan Balok Penyangga diaphragm wall. Balok ukuran 70 x 50 cm dengan Tulangan Utama D22 – 200 dan Tulangan geser Ø12 dengan jarak 150. Balok ukuran 50 x 50 cm dengan Tulangan Utama D19 – 200 dan Tulangan geser Ø12 dengan jarak 150. Adapun metode konstruksi yang dipakai adalah Top- Down Construction. ================================================================================= Design of scale pit, -8m depth, 56,7m long and 6,8m wide. considering the project site is located adjacent boundary wall of land (limited area) is above the clay has properties growth shrinkage, and high water content, and low bearing capacity, the need for proper planning to determine alterntif planning efesian and implementation methods well in terms of quality, costs. Look the conditions that must be considered as above, it is necessary for retaining wall at the same time able to withstand the loads that occur. In this final planned pit alternative scale construction and construction execution and implementation is planned method. The first alternative is the construction of the retaining wall diaphragm wall without using PVD before, and the second is the construction of an alternative retaining wall diaphragm wall using PVD earlier. Such structures can act as a retaining wall lateral earth pressure (scale pit wall). Of the two alternatives are planned, acquired Alternative 1 (Diaphragm Wall without PVD) total depth of the wall as deep as 21 m with a thickness of 60 cm. Using the Main Reinforcement D22 - 150, D19 Transverse Reinforcement - Reinforcement shear 150 and 150. Ø10 with a distance of Alternative 2 (combination of Diaphragm Wall and PVD) total depth of the wall as deep as 21 m with a thickness of 50 cm. Using the Main Reinforcement D22 - 200, Transverse Reinforcement D19 - 150, and sliding Reinforcement Ø10 with a distance of 150. Selected triangle pattern PVD installation with a distance of 0.8 meters with the time required for consolidation is 11 weeks. In planning the basement floor slab thickness must consider the uplift force and pressure of the water received by this floor plate. Slab thickness of 70 cm, using reinforcement directions x D22-250 mm and reinforcement y D19- 200 mm. Planning beam diaphragm wall mountings. The block size of 70 x 50 cm with Main Reinforcement D22 - 200 and Reinforcement shear Ø12 with a distance of 150 beams of size 50 x 50 cm with Main Reinforcement D19 - 200 and Reinforcement shear Ø12 with a distance of 150. The construction method used is a Top-Down Construction.

Item Type: Thesis (Undergraduate)
Additional Information: RSS 624.164 Des a
Uncontrolled Keywords: Diaphragma Wall; Metode Top-Down; PVD; Scale Pit.
Subjects: T Technology > T Technology (General) > T56.8 Project Management
T Technology > TA Engineering (General). Civil engineering (General) > TA645 Structural analysis (Engineering)
Divisions: Faculty of Civil Engineering and Planning > Civil Engineering > (S1) Undergraduate Theses
Depositing User: Mrs Anis Wulandari
Date Deposited: 22 Jun 2017 03:10
Last Modified: 26 Dec 2018 07:15
URI: http://repository.its.ac.id/id/eprint/41814

Actions (login required)

View Item View Item