Penempatan posisi dan pemilihan jenis Tower Crane
dapat meningkatkan kinerja konstruksi pada gedung bertingkat.
Seperti pada Proyek Pembangunan Tunjungan Plaza 5 Surabaya
yang memiliki wilayah luas dan aktifitas pengangkutan material
konstruksi yang banyak, maka satu tower crane tidak bisa
menjangkau semua wilayah proyek dan tidak memenuhi semua
kebutuhan aktifitas pengangkutan oleh karena itu tower crane
digunakan lebih dari satu, yaitu 2 unit tower crane. Selanjutnya
dengan kondisi seperti ini perlu direncanakan titik – titik yang
paling penting seperti supply point (titik penyediaan) dan titik
lokasi penempatan tower crane.
Dari penelitian ini direncanakan 3 skenario, yaitu
skenario 1 menunjukkan kondisi sebenarnya atau kondisi
eksisting pada Tower Crane dengan menggunakan radius 70 m
dan 60 m, skenario 2 menunjukkan penambahan penempatan
titik supply dengan menggunakan radius yang sama dengan
skenario 1, yaitu 70 m dan 60 m, dan skenario 3 sama dengan
skenario 2 tetapi radius yang digunakan diperkecil, yaitu 65 m
dan 50 m. Ketiga skenario dihitung masing-masing waktu
siklusnya dan dicari waktu siklus yang paling minimum.
Hasil Penelitian menunjukkan dari ketiga skenario
didapatkan penempatan Tower Crane dengan waktu siklus yang
minimum adalah skenario 3 dimana penempatan Tower crane 1
berada pada titik koordinat (16;59) dengan radius, yaitu 65 m mempunyai total waktu siklus 254,83 jam dan Tower crane 2
berada pada titik koordinat (65;54) dengan radius, yaitu 50 m mempunyai total waktu siklus 343,39 jam dengan total waktu siklus seluruh, yaitu 598,12 jam. Dengan skenario ini
penghematan waktu siklus dibandingkan dengan kondisi
Eksisting proyek adalah 149,45 jam (1,49 %)

======================================================================================

Positioning and type election of tower crane can
improve the performance of buildings construction. As in the
construction project of Tunjungan Plaza 5 Surabaya that has a
vast territory and a lot of transporting construction materials
activities, so the tower crane can not reach all areas of the
project and do not meet all the needs of the activities haulage.
Therefore it used more than one, namely 2 units tower crane.
These conditions need to make an important point to plan, such
as supply point (the point of supply) and the point where to place
the tower crane.
This research was develop on 3 scenarios, the
scenario 1 shows the actual condition or existing condition of
tower Crane by using a radius of 70 m and 60 m, scenario 2
shows the additional placement of the supply point by using the
same radius with scenario 1, which is 70 m and 60 m and
scenario 3 the same as scenario 2 but the radius used is reduced,
which is 65 m and 50 m. The third scenario is calculated each
time the cycle and look for the minimum cycle time.
Research shows placement of these three scenarios
obtained Tower Crane with a minimum cycle time is the third
scenario where placement Tower crane 1 located at the
coordinates (16; 59) with a 65 m radius and has a total cycle time of 254,83 hours and Tower crane 2 located at the coordinates
(65; 54) with a radius of 50 m and has a total cycle time of 343,39 hours with a total cycle time of the whole is 598,12 hours.
With this scenario compared to the cycle time savings Existing
conditions of the project by 149,45 hours (1,49%).

Item Type: Thesis (Undergraduate)
Additional Information: RSS 621.873 Yur o
Uncontrolled Keywords: Tower Crane, Titik Supply, Waktu Siklus, Tower cranes, Supply Point, Time Cycle
Subjects: T Technology > TA Engineering (General). Civil engineering (General)
Divisions: Faculty of Civil Engineering and Planning > Civil Engineering > 22201-(S1) Undergraduate Thesis
Depositing User: Anis Wulandari
Date Deposited: 06 Jul 2017 03:07
Last Modified: 28 Dec 2018 02:25
URI: http://repository.its.ac.id/id/eprint/41885

Actions (login required)

View Item View Item