Pasar turi merupakan pusat perdagangan yang
cukup vital untuk masyarakat kota Surabaya serta Jawa
Timur. Sejak diresmikan oleh Walikota Surabaya pada
tanggal 21 Juni 1971 pasar turi bukan saja menjadi
kepentingan perdagangan antara Surabaya dan Jawa Timur
tapi juga merupakan menjadi pasar interinsuler, pasar antar
pulau Indonesia bagian timur. Pasar turi sempat mengalami
kebakaran berkali-kali. Namun, kebakaran hebat terjadi pada
tahun 2007 mengakibatkan banyak kerugian terjadi pada
para pedagang. Kebakaran kembali melanda pasar turi tahap
III pada tahun 2012 yang mengakibatkan seluruh gedung
pasar terbakar habis. Bangunan sisa kebakaran dari pasar
turi tersebut direncanakan akan dibongkar untuk menjadi
suatu bangunan baru yang lebih bernilai.
Masalah penelitan pembongkaran bangunan
menjadi suatu yang hal yang menantang dalam perspektif
management konstruksi. Suatu pembongkaran yang
dilaksanakan dengan metode yang sesuai akan menghasilkan
biaya pembongkaran yang efisien serta membantu
mengurangi limbah hasil dari pembongkaran bangunan . Hal
ini yang melatarbelakangi adanya penelitian mengenai
pembongkaran dengan mengambil lokasi studi pada
bangunan Pasar Turi tahap III Surabaya dengan
menggunakan metode yang mengacu pada Code of Practice
for Building Demolition tahun 2004 yakni metode to down
manual, top down by machine dan mekanikal. Dari ketiga
metode tersebut dianalisa dengan menggunakan traffic light
analysis untu mendapatkan metode yang sesuai untuk
diterapkan pada pembongkaran Pasar Turi Tahap III
Surabaya. Dari hasil inilah akan didapat suatu perhitungan
biaya yang efisien.
Dari studi yang sudah dilakukan, diharapkan bisa
menambah suatu informasi baru mengenai suatu perhitungan
biaya pembongkaran bangunan dari suatu metode yang sesuai
dengan keadaan banguan yang akan dibongkar, bagi peneliti
dan pelaku konstruksi di Indonesia.
=================================================================================
Pasar Turi is a vital trade centre for Surabaya and East Java
citizen. After inaugurate by the major of Surabaya City on June
21, 1971 Pasar Turi not only become the interests of trade
between Surabaya and East Java but also the interinsuler market,
the inter-island market of eastern Indonesia. Pasar Turi got a fire
many times. However, a devastating fire in 2007 resulted in many
losses occur on traders. And again fire struck Pasar Turi phase
III in 2012 which resulted in the entire building burned down.
The building which is the rest of the fire is planned to be
demolished to be a new building that is more valuable
Research about demolition of a building have been a
challenging matter in construction management perspective. The
demolition which is carried out with the appropriate method will
give an efficient demolition cost and helps reduce the waste
produced from the demolition. These reason brings an idea to
conduct a reasearch regarding demolition by taking study case at
the building phase III Surabaya Pasar Turi by using the method
refers to the Code of Practice for the Building Demolition 2004,
Hongkong, manual method top down, top down by machine
method and mechanical method. Those three methods were
analyzed by using the traffic light analysis to obtain the
appropriate method to be applied to the demolition of Pasar Turi
phase III Surabaya
From the studies that have been conducted, is
expected to add some new information regarding the
calculation of the cost of demolition building by a method in
accordance with the building condition which will be
demolished, for the researchers and actors in the Indonesian
construction.
Item Type: | Thesis (Undergraduate) |
---|---|
Additional Information: | RSS 658.404 Muh a |
Uncontrolled Keywords: | Pembongkaran, metode pembongkaran, analisa biaya, Demolition, Demolition method, Cost analysis |
Subjects: | T Technology > T Technology (General) > T56.8 Project Management |
Divisions: | Faculty of Civil Engineering and Planning > Civil Engineering > 22201-(S1) Undergraduate Thesis |
Depositing User: | Anis Wulandari |
Date Deposited: | 10 Jul 2017 06:12 |
Last Modified: | 10 Jul 2017 06:12 |
URI: | http://repository.its.ac.id/id/eprint/41964 |
Actions (login required)
View Item |