Analisa Anggaran Biaya Pelaksanaan, Mutu Beton Dan Waktu Pada Proyek Hotel Swiss-Belinn Juanda Kota Surabaya

Afrizal, Dimas (2017) Analisa Anggaran Biaya Pelaksanaan, Mutu Beton Dan Waktu Pada Proyek Hotel Swiss-Belinn Juanda Kota Surabaya. Diploma thesis, Institut Teknologi Sepuluh Nopember Surabaya.

[thumbnail of 3113041090-Undergraduate_Theses.pdf]
Preview
Text
3113041090-Undergraduate_Theses.pdf - Published Version

Download (9MB) | Preview

Abstract

Proyek pembangunan ini dibangun 8 lantai dengan luas tanah 5578.45 m2 dan luas bangunan 1466.25 m2 yang berada di Jl. Raya Juanda Kota Surabaya. Proyek ini menggunakan metode pengecoran di tempat atau yang sering di kenal dengan cast in-situ yang terdiri dari pekerjaan pondasi dan pekerjaan struktur utama beton yaitu balok, kolom dan plat lantai.
Dalam tugas akhir ini membahas mengenai perhitungan anggaran biaya pelaksanaan, mengawasi mutu material, pekerja dan alat yang digunakan pada proyek dan yang terakhir perhitungan waktu pelaksanaan pada pekerjaan struktur beton pembangunan gedung tersebut.
Dari perhitungan biaya dan waktu yang telah dilakukan, diperoleh durasi pekerjaan selama 402 hari kalender dan biaya pekerjaan senilai Rp 14.182.564.065,-. Penyajian penjadwalan pekerjaan pembangunan hotel Swiss-belinn Juanda Kota Surabaya ini menggunakan kurva ‘S’ pekerjaan.
====================================================================
The construction project was built 8 floors with a land area of 5578.45 m2 and a building area of 1466.25 m2 located on Jl. Raya Juanda City of Surabaya. The project uses in-situ casting methods, often known as in-situ cast consisting of foundation work and main concrete structural work of beams, columns and floor plates.
In this final project discuss about budget calculation of implementation cost, supervise material quality, worker and tools used in the project and lastly the calculation of execution time on the work of concrete structure of the building construction
From the calculation of the cost and time has been done, obtained the duration of work for 402 calendar days and the cost of work worth Rp 14.182.564.065, -. Presentation of the scheduling of hotel construction work Swiss-belinn Juanda Surabaya City uses curve 'S' job.

Item Type: Thesis (Diploma)
Uncontrolled Keywords: Anggaran Biaya Pelaksanaan, Mutu Beton, Durasi pekerjaan, Construction Cost, Concrete Quality, Time Management
Subjects: T Technology > TH Building construction > TH437 Building--Cost control.
T Technology > TS Manufactures > TS156 Quality Control. QFD. Taguchi methods (Quality control)
Divisions: Faculty of Vocational > Civil Infrastructure Engineering (D3)
Depositing User: Dimas Afrizal .
Date Deposited: 09 Oct 2017 05:13
Last Modified: 08 Mar 2019 02:36
URI: http://repository.its.ac.id/id/eprint/44959

Actions (login required)

View Item View Item