Biaya Dan Waktu Pekerjaan Girder Erection Dengan Metode Launcher Pada Bentang Tengah Proyek Pembangunan Jembatan Mastrip Surabaya

Rahmawati, Rizky (2017) Biaya Dan Waktu Pekerjaan Girder Erection Dengan Metode Launcher Pada Bentang Tengah Proyek Pembangunan Jembatan Mastrip Surabaya. Diploma thesis, Institut Teknologi Sepuluh Nopember.

[thumbnail of 3113041045-Undergraduate_thesis.pdf]
Preview
Text
3113041045-Undergraduate_thesis.pdf - Published Version

Download (8MB) | Preview

Abstract

Metode pelaksanaan dalam sebuah proyek merupakan salah satu hal yang paling penting dalam kelancaran suatu proyek. Segala sesuatu yang mengatur dari segi teknis, pertimbangan lokasi proyek, kebutuhan pekerja, analisa waktu proyek, hingga pada analisa biaya masuk dalam metode pelaksanaan. Metode pelaksanaan yang baik adalah yang sesuai dengan kondisi medan yang akan dikerjakan dengan mempertimbangkan dari segi biaya maupun waktu. Metode pelaksanaan dapat digunakan dalam segala aspek proyek, tidak terkecuali dalam dunia sipil, seperti untuk membangun gedung, jembatan, jalan, bendungan, bandara, dan segala hal yang berkaitan dengan infrastruktur.
Pada penulisan tugas akhir ini meninjau proyek pembangunan Jembatan Mastrip Surabaya yang menghubungkan Jalan Jambangan dan Jalan Mastrip. Jembatan yang membentang sepanjang 54 meter ini menggunakan struktur PCI girder pada bentang tengah sepanjang 30 meter yang metode pemasangannya sering disebut girder erection. Metode yang digunakan dalam penulisan tugas akhir ini khususnya dalam pekerjaan girder erection adalah dengan metode launcher, sedangkan dalam pelaksanaannya di lapangan direncanakan menggunakan metode service crane. Pemilihan metode pelaksanaan dalam penulisan tugas akhir ini menggunakan beberapa pertimbangkan, seperti lokasi proyek, pendukung akses proyek (lalu lintas sekitar lokasi proyek), hingga lingkungan yang terkena dampak adanya pekerjaan pembangunan jembatan ini. Output dari penulisan tugas akhir tentang metode pelaksanaan girder erection ini adalah waktu dan biaya yang berupa Rencana Anggaran Pelaksanaan (RAP).
Hasil yang didapat setelah melalui proses pengolahan dan perhitungan dengan menggunakan metode launcher pada pekerjaan girder erection pada bentang tengah pembangunan jembatan Mastrip Surabaya sepanjang 30 meter didapatkan bahwa biaya yang dihasilkan lebih mahal. Pada metode service crane didapatkan biaya sebesar Rp. 1.779.437.050,00, sedangkan jika menggunakan metode launcher didapatkan biaya sebesar Rp. 2.193.471.841,00. Dari segi waktu, penggunaan metode service crane lebih cepat dari pada penggunaan metode launcher. Dengan menggunakan metode service crane, pekerjaan girder erection dapat dilaksanakan selama 14 hari, sedangkan jika menggunkan metode launcher dapat dilaksanakan selama 20,96 hari.

=========================================================================

The method of implementation in a project is one of the most important things in case to run a project. Everything that relates in terms of technical, project location considerations, worker needs, project time analysis, and the cost analysis is included in the method of implementation. A good execution method is appropriate to the present conditions to be worked out in terms of both cost and time. The method of implementation can be used in all aspects of the project, especially in the civil world, such as in the development of buildings, bridges, roads, dams, airports and everything related to the infrastructure.
In this thesis, will be discussed about the construction project in Surabaya Mastrip Bridge which connects Jambangan Street and Mastrip Street. This bridge is 54 meter long and will be using PCI girders structure in a 30-meter-long in central span whose installation method is often called a girder erection.
The method that is used in this thesis of this final task, especially in the girder erection is launcher method, while in the implementation of this project is planned using the service crane method. The selection of this methods uses several considerations, such as project sites, supporting project access (traffic around the project site), and the environment that will be affected by the construction work of this bridge. The output of this thesis of girder erection implementation method is to have the analysis result of time and cost in the form of Budget Plan of Implementation (RAP).
The results of this thesis after going through the process of calculation by using the launcher method of the girder erection on the central span of Mastrip Surabaya bridge construction in 30-meters-long obtained that the cost generated more expensive. In service crane method obtained cost of Rp. 1.779.437.050,00, whereas if using launcher method obtained cost equal to Rp. 2.193.471.841,00. In terms of time, the use of service crane method faster than the use of launcher method. By using service crane method, girder erection can be done for 14 days, whereas if using launcher method can be implemented for 20,96 days.

Item Type: Thesis (Diploma)
Uncontrolled Keywords: The girder erection of a bridge using launcher method.
Subjects: T Technology > T Technology (General) > T56.8 Project Management
T Technology > TG Bridge engineering
Divisions: Faculty of Vocational
Depositing User: Rizky Rahmawati
Date Deposited: 02 Oct 2017 03:23
Last Modified: 08 Mar 2019 06:23
URI: http://repository.its.ac.id/id/eprint/45449