Studi Koordinasi Proteksi Rele Arus Lebih, Diferensial Dan Ground Fault Pada PT. Linde Indonesia, Cilegon

Dewangga, Ananta Setia (2015) Studi Koordinasi Proteksi Rele Arus Lebih, Diferensial Dan Ground Fault Pada PT. Linde Indonesia, Cilegon. Undergraduate thesis, Institut Technology Sepuluh Nopember.

[thumbnail of 2210100071-Undergraduate-Theses.pdf]
Preview
Text
2210100071-Undergraduate-Theses.pdf - Published Version

Download (2MB) | Preview

Abstract

Sistem proteksi sangat dibutuhkan untuk menjaga kontinuitas dan
meningkatkan keandalan dalam suatu sistem kelistrikan. Hal ini
dikarenakan konsumsi energi listrik oleh beban beban industri
berlangsung secara terus menerus. Untuk menjamin keandalan dan
kontinuitas tersebut diperlukan pengaman pengaman tenaga listrik. PT.
Linde Indonesia, Cilegon, merupakan anggota dari Grup Linde, yang
memasok gas industri jangka panjang untuk PT. Krakatau Posco, dimana
sangat memerlukan pengamanan dari gangguan gangguan yang paling
sering terjadi yaitu gangguan hubung singkat antar fasa dan satu fasa ke
tanah. Melalui tugas akhir ini dilakukan studi koordinasi proteksi pada
PT. Linde Indonesia, Cilegon yang tepat dalam mendeteksi dan mengatasi
gangguan sehingga tidak mengganggu sistem dan mencegah kerusakan
yang mungkin terjadi pada peralatan listrik.
Dari hasil kurva arus kondisi eksisting di dapatkan kesalahan
kesalahan pada koordinasi yang ada pada rele arus lebih, dan ground fault,
baik itu kesalahan pada setting pick up arus lebih dan juga kesalahan pada
time delay yang ada dimana tidak sesuai dengan standar IEEE 242
grading time yaitu 0.2 – 0.4. Dan juga terdapat beberapa kesalahan pada
setting rele diferensial baik itu minimum setting dan %Slope yang ada.
Berdasarkan kesalahan kesalahan tersebut maka perlu dilakukan setting
ulang pada rele yang ada sehingga setting an tersebut sesuai dengan
standar yang ada dan dapat bekerja dengan aman dan secepat mungkin.
======================================================================================================
Protection system is needed to maintain continuity and improve the
ability in electrical system. Protection is crucial because the consumption
of electrical energy by industrial continues overtime. To guarantee the
realibility and continuity of electrical power required protection system.
PT Linde Indonesia, Cilegon, a member of The Linde Group, is the
supplier of long term industrial gasses for PT. Krakatau Posco, which is
required a protection from faults like short circuit phase to phase and
phase to ground. Through this final project, protection coordination
studies in PT. Linde Indonesia, Cilegon, will be doing a correction in
order to detecting and isolating the fault that not disturbing the system
and prevent damage to electrical equipment.
The results of the current curves in exsisting condition, showed that
some misscoordination protection in overcurrent relay, and ground fault.
There are some misscoordination in pick up setting overcurrent and
misscoordination in time delay which is not fit with IEEE 242 standart
grading time ( 0.2s – 0.4s ). And besides there are some mistake of
differential relay setting in minimum setting and %slope. Based on that
misscoordination it is necessary to resetting the existing relay and can
work safely and quickly as possible.

Item Type: Thesis (Undergraduate)
Additional Information: RSE 621.317 Dew s
Uncontrolled Keywords: Koordinasi proteksi, Rele arus lebih, Rele ground fault, Rele diferensial
Subjects: T Technology > TK Electrical engineering. Electronics Nuclear engineering
Divisions: Faculty of Industrial Technology > Electrical Engineering > 20201-(S1) Undergraduate Thesis
Depositing User: Mr. Tondo Indra Nyata
Date Deposited: 03 Jul 2018 07:45
Last Modified: 03 Jul 2018 07:45
URI: http://repository.its.ac.id/id/eprint/52088

Actions (login required)

View Item View Item