Perencanaan Jalan Jalur Lintas Selatan Desa Sindurejo – Desa Tumpakrejo STA 16+125 S/D 21+125 Kabupaten Malang Provinsi Jawa Timur

Yayang, Dherika Rachmania (2018) Perencanaan Jalan Jalur Lintas Selatan Desa Sindurejo – Desa Tumpakrejo STA 16+125 S/D 21+125 Kabupaten Malang Provinsi Jawa Timur. Undergraduate thesis, Institut Teknologi Sepuluh Nopember.

[thumbnail of 10111715000014-Undergraduate_theses (2).pdf]
Preview
Text
10111715000014-Undergraduate_theses (2).pdf - Accepted Version

Download (6MB) | Preview

Abstract

Dalam tugas akhir ini perencanakan geometrik jalan menggunakan literatur tata cara perencanaan jalan antar kota tahun 1997, perhitungan analisis kapasitas jalan dengan metode Manual kapasitas Jalan Indonesia(MKJI) 1997 jalan perkotaan, perencanaan tebal perkerasan struktur perkerasan lentur dengan menggunakan metode SNI 1723-1989-F sesuai petunjuk DPU Bina Marga dalam buku Perencanaan Tebal Struktur Perkerasan Lentur oleh Silvia Sukirman, perencanaan saluran tepi jalan (drainase) berdasarkan SNI 03-3424-1994, perhitungan dimensi dinding penahan menggunakan literatur Braja M Das, Mekanika Tanah 1994, perhitungan rencana anggaran biaya menggunakan Standard Satuan Harga Dasar Konstruksi Tahun 2017 dan Analisis Harga Satuan pekerjaan Dinas Pekerjaan Umum Kabupaten Malang Provinsi Jawa Timur Tahun 2015.
Hasil perencanaan Jalan Jalur Lintas Selatan Desa Sindurejo – Desa Tumpakrejo STA 16+125 s/d 21+125 didapat alinyemen geometrik pegunungan dengan lebar jalan 7 meter dan bahu jalan 2 meter. Ruas jalan ini membutuhkan lapis perkerasan AC-WC sebesar 5 cm dan lapis perkerasan AC-BC sebesar 7 cm. Perencanaan saluran tepi (drainase) berbentuk trapesium menggunakan bahan dari pasangan batu kali. Saluran tepi (drainase) menggunakan lebar dasar saluran sebesar 0,5 – 1,1 meter dan tinggi saluran 0,7 – 1,3 meter. Total estimasi biaya Rp 70.417.163.000 (Terbilang tujuh puluh milyar empat ratus tujuh belas juta seratus enam puluh tiga ribu rupiah)
=========================================================================================================
This final project concentrates on designing the road geometric based on the intercity-road planning procedure in 1997, the assessment to road capacity analysis with ‘Manual Kapasitas Jalan Indonesia’ (MKJI) methods in 1997. The design of flexible pavement thickness using SNI 1723-1989-F methods based on DPU Bina Marga, etc.
The result of the southern track road design of Sindurejo – Tumpakrejo village from STA 16+125 to 21+125 is the geometric alignments on mountain area were 7 meters road width, and side road were 2 meters. The road needs the AC-WC pavements of 5 cm and AC-BC pavements of 7 cm. The form of drainage is a trapezoidal using river stone. The base of drainage width is 0.5 – 1.1 meters and the height is 0,7 – 1,3 meters. The total of cost estimation is Rp 73.713.187.000 (seventy three billion and seven hundred and thirteen million and one hundred and eighty seven thousand rupiahs).

Item Type: Thesis (Undergraduate)
Additional Information: RSIS 625.7 Rac p-1 3100018075623
Uncontrolled Keywords: Perencanaan Jalan, Tebal Perkerasan, Dimensi Saluran, RAB, Road Design, Pavement thickness, Drainage dimension, BoQ
Subjects: T Technology > TE Highway engineering. Roads and pavements
Divisions: Faculty of Vocational > Civil Infrastructure Engineering (D3)
Depositing User: Yayang Dherika Rachmania
Date Deposited: 15 Aug 2018 09:03
Last Modified: 13 Oct 2020 01:02
URI: http://repository.its.ac.id/id/eprint/52426

Actions (login required)

View Item View Item