Evaluasi Keterlambatan Pada Proyek Pembangunan Jacket Structure "Madura Bd" Pt Pal Indonesia

Rangga, Fitri (2018) Evaluasi Keterlambatan Pada Proyek Pembangunan Jacket Structure "Madura Bd" Pt Pal Indonesia. Undergraduate thesis, Institut Teknologi Sepuluh Nopember.

[thumbnail of 04311040000013-Undergraduate_Theses.pdf]
Preview
Text
04311040000013-Undergraduate_Theses.pdf - Accepted Version

Download (2MB) | Preview

Abstract

Dalam proses pembangunan jacket structure terkadang tidak sesuai dengan jadwal yang telah ditetapkan. Banyak faktor yang mempengaruhi diantaranya, waktu atau penjadwalan, peralatan, material yang dibutuhkan, sumber daya manusia serta biaya. Maka untuk menganalisis begitu banyak faktor yang melatar belakangi keterlambatan suatu proyek dibutuhkan sebuah metode pendekatan yang sistematis. Pada Tugas Akhir ini untuk mengevaluasi faktor keterlambatan pada proyek EPCC jacket structure Madura BD di PT.PAL Indonesia digunakan metode FTA (fault tree analysis). Setelah mengetahui faktor keterlambatan menggunakan FTA, selanjutnya adalah mencari kombinasi dari faktor-faktor keterlambatan tersebut dengan Minimal Cut Set. Berdasarkan data-data yang diperoleh dari PT.PAL Indonesiadari proyek EPCC Madura BD diketahui bahwa 3 faktor utama penyebab keterlambatan adalah Proses Procurement Lama, Jadwal Perakitan Struktur Mundur, dan Manajemen Buruk. Sedangkan probabilitas dari masing-masing kejadian secara berurutan adalah 0.156, 0.043, dan 0.12. Jadi total peluang kejadian puncak untuk Top Event “Perakitan Jacket Struktur Madura BD Terlambat” adalah 0.383
====================================================================================================
Construction process of the jacket structure sometimes is not in accordance with a predetermined schedule. Many factors that affect them, time or scheduling, equipment, materials required, and cost of human resources. Then to analyze so many background factors delay a project requires a systematic approach. In this final project to evaluate the delay factor at EPCC projects of Madura BD jacket structure in PT.PAL Indonesia used FTA (Fault Tree Analysis) method. After knowing the delay factor using FTA, the next is to find a combination of factors delays with Minimal Cut Sets. Based on the data PT.PAL Indonesia obtained from EPCC projects Madura BD is known that 3 main factors causing the delay is the Old Procurement Process, Structure Backward Assembly Schedule, and Bad Management. While the probability of occurrence of each sequence is 0.156, 0.043, and 0.12. So the total peak incidence opportunities for the Top Event "Jacket Assembly Structure Madura BD Late" is 0.383

Item Type: Thesis (Undergraduate)
Uncontrolled Keywords: Evaluasi Keterlambatan Proyek, Fault Tree Analysis, Jacket Structure, Minimal Cut Set, PT PAL INDONESIA
Subjects: T Technology > TS Manufactures > TS155 Production control. Production planning. Production management
Divisions: Faculty of Marine Technology (MARTECH) > Ocean Engineering > 38201-(S1) Undergraduate Thesis
Depositing User: Rangga Fitri Suryandono
Date Deposited: 02 Aug 2021 22:37
Last Modified: 02 Aug 2021 22:37
URI: http://repository.its.ac.id/id/eprint/57711

Actions (login required)

View Item View Item