Awaluddin, La ode Muhammad Iqbal (2019) Analisa Percepatan Waktu dengan Menggunakan Metode Trade Cost Trade Off (TCTO) pada Proyek Apartemen Puncak Merr Surabaya. Undergraduate thesis, Institut Teknologi Sepuluh Nopember.
Preview |
Text
03111440000036-Undergraduate_Theses.pdf Download (10MB) | Preview |
Abstract
Pada pembangunan sebuah proyek tidak selamanya akan berjalan sesuai waktu rencana yang telah ditentukan. Keterlambatan bisa saja terjadi dan merugikan kedua belah pihak dari segi biaya dan waktu. Oleh karena itu, pekerjaan proyek tepat waktu adalah suatu keberhasilan kontraktor maupun pemilik. Pada proyek Apartemen Puncak MERR yang terletak di Kelurahan Wonorejo, Kecamatan Rungkut, Surabaya, Jawa Timur. Proyek ini dikerjakan oleh PT. Wika Gedung dengan nilai kontrak sebesar Rp 522.679.450.000 akan tetapi proyek ini mengalami keterlambatan pada pelaksanaan. Berdasarkan data Kurva S (PT. Wika Gedung, 2018) pada perencanaan di Bulan Februari 2018 adalah 34,5% tetapi, pengerjaan di lapangan masih 14,7% sehingga total waktu keterlambatan proyek ini adalah 19,8 %.
Tugas akhir ini dilakukan untuk mengetahui percepatan waktu akibat proyek yang mengalami keterlambatan dengan menggunakan metoda Time Cost Trade Off (TCTO) dengan penambahan jam kerja. Metoda ini diterapkan pada proyek Apartemen Puncak MERR yang terletak di Kelurahan Wonorejo, Kecamatan Rungkut, Surabaya, Jawa Timur. Berdasarkan hasil analisa yang telah dilakukan maka didapatkan beberapa kesimpulan yaitu durasi normal pada pekerjaan struktur perlantainya adalah 41 hari dengan biaya normal setiap lantainya sebesar Rp 2.341.233.195 dan Durasi percepatan proyek perlantai setelah setelah dilakukan analisa Time Cost Trade Off (TCTO) adalah 32 hari dengan biaya percepatan setiap lantai sebesar Rp 4.126.475.359.
================================================================================================
On the construction of the project will not always go according to plan time. Delays may occur and is detrimental to both parties in terms of cost and time. Therefore, the project work on time is a success the contractor or owner. At the height of the Apartment Project located in Kelurahan MERR Wonorejo Rungkut, Surabaya, East Java. The project was implemented by PT. Wika with contract value amounting to Rp 522,679,450,000 but the project suffered delays in implementation.
Based on data from the S-curve (PT. Wika, 2018) on planning in February 2018 34.5%, however, working in the field still 14.7% bringing the total delay time of the project was 19.8%.
The final project is done to know the acceleration of time due to delays in projects that are experienced with using the method of the time cost Trade Off (TCTO) with additional hours of work. This method is applied to the top of the Apartment Project located in Kelurahan MERR Wonorejo Rungkut, Surabaya, East Java.
Based on the results of the analysis that has been done then the conclusion that is the duration of the normal work on the structure was 41 days with normal cost each floor of Rp 2,341,233,195 and duration of the acceleration of the project each floor after doing analysis of time cost Trade Off (TCTO) is 32 days with each floor acceleration costs Rp 4,126,475,359.
Item Type: | Thesis (Undergraduate) |
---|---|
Additional Information: | RSS 658.403 2 Awa a-1 2019 |
Uncontrolled Keywords: | Kata kunci : TCTO, (Time Cost Trade Off), Pertukaran Biaya dan Waktu, Percepatan Waktu, Puncak Apartemen, Surabaya |
Subjects: | H Social Sciences > HD Industries. Land use. Labor > HD1391 Apartment houses T Technology > TH Building construction > TH437 Building--Cost control. |
Divisions: | Faculty of Civil Engineering and Planning > Civil Engineering > 22201-(S1) Undergraduate Thesis |
Depositing User: | La Ode Muhammad Iqbal Awaluddin |
Date Deposited: | 30 Jul 2021 10:44 |
Last Modified: | 30 Jul 2021 10:44 |
URI: | http://repository.its.ac.id/id/eprint/61177 |
Actions (login required)
View Item |