Analisa perbandingan biaya dan waktu bangunan konstruksi baja sistem pre-engineering building dan sistem konvensional pada proyek pabrik fiber cement boards - Mojosari

Putra, Rahmat Kurniawan Eka (2015) Analisa perbandingan biaya dan waktu bangunan konstruksi baja sistem pre-engineering building dan sistem konvensional pada proyek pabrik fiber cement boards - Mojosari. Undergraduate thesis, Institut Teknologi Sepuluh Nopember.

[thumbnail of 3112106052-Undergraduate_Theses.pdf]
Preview
Text
3112106052-Undergraduate_Theses.pdf - Published Version

Download (3MB) | Preview
[thumbnail of 3112106052-presentation.pdf]
Preview
Text
3112106052-presentation.pdf - Presentation

Download (1MB) | Preview
[thumbnail of 3112106052-paper.pdf]
Preview
Text
3112106052-paper.pdf - Published Version

Download (683kB) | Preview

Abstract

Bangunan konstruksi baja pada umumnya menggunakan
sistem konvensional dengan elemen utama adalah hot rollet wf
standar yang biasa kita jumpai dipasaran yang lebih berat dari
non prismatic yang kemudian dilakukan fabrikasi dilapangan.
Metode ini sudah banyak diterapkan dalam pelaksanaan
konstruksi baja. Seiring berkembangnya teknologi dan inovasi
dibidang konstruksi terdapat alternatif metode konstruksi lain
yang dikembangkan untuk menghasilkan konstruksi baja yang
lebih murah, implementasi yang efisien dan cepat dengan
meminimal resiko kesalahan (akurasi), serta menghasilkan
metode erection yang dilakukan secara bertahap, relatif mudah
dan cepat. Metode yang dapat diterapkan ini yaitu dinamakan
dengan metode konstruksi baja pre-engineering building.
Tujuan untuk melakukan perbandingan metode konstruksi
baja konvensional dan pre-engineering building dari aspek biaya
dan waktu. Proyek yang djadikan objek penelitian adalah
Pembangunan Pabrik Fibre Cement Board Mojosari. Masingmasing
metode akan dihitung biaya dan waktu pelaksanaan
berdasarkan pelaksanaan teknis metode tersebut. Dari hasil
perbandingan akan didapat biaya dan waktu yang diperlukan
untuk metode konvensional dan pre-engineering building.
Dari analisa perhitungan biaya dan waktu pada proyek
pembangunan pabrik fibre cement boards didapat hasil untuk
pekerjaan bangunan konstruksi baja dengan sistem preengineering
building dengan biaya sebesar Rp. 1.674.677.166,65
dalam waktu 40 hari dan sistem konvensional dengan biaya
sebesar Rp. 2.269.651.094,- dalam waktu 78 hari. =========== Steel construction building that typically use a
conventional system with the main element is the hot rollet wf
standard which is heavier than non Prismatic then conducted
fabrication in field. This method has widely been applied in steel
construction. As the technology development and innovation in
construction field, there is another alternative of the construction
method that is developed to produce steel construction cheaper,
efficient and rapid implementations to minimize the risk of
errors (accuracy), and resulted in the erection method that is
conducted gradually, relatively easy and fast. This method is
called steel construction method of pre-engineering building.
The purpose of doing the comparison of conventional steel
construction and pre-engineering building method in cost and
time aspect. The researched-project object is Fibre Cement
Board factory - Mojosari. Each method will be calculated based
on the cost and time of the technical implementation. From the
results of the comparison will be obtained cost and time that are
needed for conventional and pre-engineering building method.
From the analysis of the cost and time calculations on the
construction project of fibre cement boards factory are obtained
results that are steel construction work with the pre-engineering
building system costs Rp. 1,674,677,166.65 and takes 40 days
while the conventional system costs Rp. 2269651094 and takes
78 days.

Item Type: Thesis (Undergraduate)
Additional Information: RSS 692.5 Put a
Uncontrolled Keywords: konstruksi baja, pre-engineering building, konvensional, steel construction, pre-engineering building, conventional
Subjects: T Technology > TH Building construction > TH437 Building--Cost control.
Divisions: Faculty of Civil Engineering and Planning > Civil Engineering > 22201-(S1) Undergraduate Thesis
Depositing User: - Davi Wah
Date Deposited: 23 Apr 2019 06:24
Last Modified: 23 Apr 2019 06:24
URI: http://repository.its.ac.id/id/eprint/62808

Actions (login required)

View Item View Item