., Dadin (2014) Analisa Keandalan Sistem Kelistrikan Jawa Bali Akibat Proyek Percepatan 10.000 MW. Undergraduate thesis, Institut Teknologi Sepuluh Nopember.

[thumbnail of 2211106065-Paper.pdf]
Preview
Text
2211106065-Paper.pdf - Published Version

Download (1MB) | Preview
[thumbnail of 2211106065-Undergraduate_Theses.pdf]
Preview
Text
2211106065-Undergraduate_Theses.pdf - Published Version

Download (4MB) | Preview
[thumbnail of 2211106065-Presentation.pdf]
Preview
Text
2211106065-Presentation.pdf - Presentation

Download (1MB) | Preview

Abstract

Penambahan kapasitas pembangkit yang disebut dengan proyek
percepatan 10.000 MW sistem kelistrikan Jawa Bali 500kV belum tentu
handal, hal ini disebabkan adanya pengaruh dari nilai Forced Outage
Rated (FOR) dan nilai dari daya mampu netto setiap pembangkitan [7].
Loss of Load Probability (LOLP) merupakan suatu metode untuk
menghitung indeks keandalan pembangkit dan energi yang tidak dapat
terpenuhi oleh sistem selama periode waktu tertentu dapat dihitung
dengan Expected Energy not Supplied (EENS). Dengan masuknya daya
dari proyek percepatan sebesar 3.942,2MW, total dari kapasitas daya
mampu netto untuk sistem kelistrikan Jawa Bali 500kV sebesar
16.780,5MW. Berdasarkan hasil simulasi, dengan menggunakan skenario
beban puncak pada tahun 2012 sebesar 13.309,035MW dan nilai dari daya
mampu netto sebesar 12.838,3MW didapatkan nilai dari LOLP
10,83724695 hari/tahun. Jika skenario proyek percepatan digunakan, nilai
dari LOLP yang dihasilkan pada tahun 2012 adalah sebesar 7,15984E-08
hari/tahun dan EENS sebesar 0,043561 MWh/tahun. Dengan skenario
kenaikan beban 7,6% pertahun[1], pada tahun 2013 didapatkan nilai dari
LOLP sebesar 6,56092E-05 hari/tahun dan EENS 46,3857 MWh/tahun,
sedangkan untuk tahun 2014 didapatkan nilai dari LOLP 0,028811071
hari/tahun dan EENS 24.956,7793 MWh/tahun. Dengan menggunakan
skenario kenaikan beban yang sama, pada tahun 2015 didapatkan nilai
dari LOLP sebesar 4,075578638 hari/tahun dan EENS 4.846.600
MWh/tahun. Nilai dari LOLP sebesar 0,028811071 hari/tahun
mengindikasikan bahwa pada tahun 2014 sistem kelistrikan Jawa Bali
500kV tetap handal, hal ini dikarenakan nilai dari indeks keandalan
pembangkit yang digunakan oleh PT.PLN sebesar 1 hari/tahun [1]. ========== Addition of generation capacity that be called as 10000MW
acceleration project of Java Bali power system 500kV is not certainly
reliable yet, this is caused by Forced Outage Rated (FOR) value and
capability power net effect for each generation [7]. Loss of Load
Probability (LOLP) is a method to calculate reliability index of
generation and unfulfilled energy by system for a certain period can be
calculated by Expected Energy not Supplied (EENS). Caused of power
addition from acceleration project by 3.942,2MW, total capacity of
capability power net Java Bali power system is 16.780,5MW. Based on
simulation results using peak load scenario at 2012 by 13.309,035MW
and capability power net value is 12.838,3MW, resulting LOLP value is
10,83724695 day/year. If acceleration project scenario is used, LOLP
value become 7,15984E-08 day/year and EENS is 0,043561 MWh/year.
With 7,6% increase of load scenario per year, in 2013 LOLP value is
6,56092E-05 day/year and EENS is 46,3857 MWh/year , while in 2014
LOLP value is 0,028811071 day/year and EENS is 24.956,7793
MWh/year. With using the same scenario,in 2015 LOLP value is
4,075578638 day/year and EENS is 4.846.600 MWh/year. LOLP value
0,028811071 day/year indicate that in 2014 Java Bali power system is
still reliable, it is caused by reliability index of generation value that
used by PT.PLN is 1 day/year [1].

Item Type: Thesis (Undergraduate)
Additional Information: RSE 621.319 Dad a
Uncontrolled Keywords: Expected Energy not Supplied, Forced Outage Rated, Loss of Load Probability, Proyek Percepatan 10.000 MW, Expected Energy not Supplied, Forced Outage Rated, Loss of Load Probability, 10000MW Acceleration Project
Subjects: T Technology > TK Electrical engineering. Electronics Nuclear engineering > TK1010 Electric power system stability. Electric filters, Passive.
Divisions: Faculty of Industrial Technology > Electrical Engineering > 20201-(S1) Undergraduate Thesis
Depositing User: - Davi Wah
Date Deposited: 22 May 2019 02:43
Last Modified: 22 May 2019 02:43
URI: http://repository.its.ac.id/id/eprint/63056

Actions (login required)

View Item View Item