Penjadwalan Pelaksanaan Ditinjau Dari Segi Biaya Dan Waktu Pada Gedung Lab. PAUD Universitas Negeri Surabaya

Syahputra, Hasan Eka and Alfi, Muhsinah (2015) Penjadwalan Pelaksanaan Ditinjau Dari Segi Biaya Dan Waktu Pada Gedung Lab. PAUD Universitas Negeri Surabaya. Diploma thesis, Institut Technology Sepuluh Nopember.

[thumbnail of 3112030041-3112030077-Undergraduate Thesis.pdf]
Preview
Text
3112030041-3112030077-Undergraduate Thesis.pdf - Published Version

Download (5MB) | Preview

Abstract

Proyek pembangunan gedung LAB. PAUD Universitas
Negeri Surabaya dengan luas bangunan ± 1740 m2 memerlukan
penjadwalan pelaksanaan yang di tinjau dari perhitungan waktu
dan biaya pelaksanaan. Perhitungan waktu dan biaya
pelaksanaan menggunakan sumber referensi buku dan
pengalaman kontraktor karena dalam perhitungan RAB
pelaksana biaya yang dibutuhkan harus real. Maka tugas akhir
ini membahas mengenai penjadwalan pelaksanaan di tinjau dari
segi biaya dan waktu.
Analisa yang dilakukan pada perhitungan waktu dan
biaya pelaksanaan ini meliputi gambar desain bangunan,
perhitungan volume tiap pekerjaan, metode pelaksanaan yang
digunakan, kebutuhan sumber daya seperti pekerja, material dan
alat berat yang digunakan, produktifitas pekerjaan. Setelah
analisa sudah didapatkan maka dapat menghitung waktu
pelaksanaan dan biaya pelaksanaan yang diperlukan.
Dengan menggunakan metode AOA pada proyek Gedung
Lab. PAUD UNESA (Universitas Negeri Surabaya) dapat
dioptimalisasikan. Sehingga dalam analisa perhitungannya
mengadopsi dari analisa harga satuan dan metode pelaksanaan
vi
yang ada. Data tersebut di kelola kembali dengan metode AOA
sehingga menghasilkan waktu dan biaya optimal. Hasil yang
diperoleh berdasarkan analisa perhitungan didapatkan waktu
pelaksanaan selama 9 bulan 19 hari atau 259 hari. Biaya
pelaksanaan dibutuhkan sebesar Rp 13.096.268.072,-.
=========================================================================================================
LAB building project. ECD State University of Surabaya
with a building area of + 1740 m2 require scheduling
implementation in the revie of the calculation of the time and cost
of implementation. Timing and cost of implementation using
reference books and experience of the contractor because in the
calculation of the cost of implementing the required RAB must be
real. So the task is to discuss the scheduling review the
implementation in term of cost and time.
The analysis used in this calculation of time and
implementation cost consist of building design drawing,
calculation of the volume each jobs, implementation m ethods are
used, resource needs as labors, materials and heavy machine are
used and work productivity. After the analysis has been obtained,
it can compute implementation time and cost project that used.
In the preparation of planning network using AOA on
building projects Lab. ECD UNESA (State University of
Surabaya) for this project is very simple method that in adopting
the calculation analysis of unit price analysis and implementation
method that exist. The data which is managed by the AOA method
viii
can produce the optimal time and cost.The result obtained by the
analysis found the project time is nine months and eighteen days
or 259 days. The implementation cost found Rp 13.096.268.072,-.

Item Type: Thesis (Diploma)
Additional Information: RSS 692.5 Sya p
Uncontrolled Keywords: Penjadwalan Pelaksanaan , Waktu and Biaya Pelaksana.
Subjects: T Technology > TH Building construction > TH437 Building--Cost control.
Divisions: Faculty of Civil Engineering and Planning > Civil Engineering > 22401-(D3) Diploma 3
Depositing User: Mr. Tondo Indra Nyata
Date Deposited: 20 Jun 2019 06:58
Last Modified: 20 Jun 2019 06:58
URI: http://repository.its.ac.id/id/eprint/63174

Actions (login required)

View Item View Item