Perencanaan Waktu Dan Biaya Proyek Jembatan Blooto-Pulorejo, Kota Mojokerto

Hutomo, Prasetya Pandu and Mawariza, Putri Suci (2015) Perencanaan Waktu Dan Biaya Proyek Jembatan Blooto-Pulorejo, Kota Mojokerto. Diploma thesis, Institut Technology Sepuluh Nopember.

[thumbnail of 3112030105-3112030130-Non Degree.pdf]
Preview
Text
3112030105-3112030130-Non Degree.pdf - Published Version

Download (5MB) | Preview

Abstract

Penyusunan proyek akhir ini membahas tentang
perencanaan waktu dan biaya pada proyek pembangunan
Jembatan Blootoo-Pulorejo, Kota Mojokerto. Jembatan Blooto-
Pulorejo ini merupakan proyek pemerintah Kota Mojokerto dalam
rangka meningkatkan fasilitas publik yang diharapkan nantinya
dapat mempermudah akses dari kecamatan blooto ke kecamatan
Pulorejo atau sebaliknya. Jembatan Blooto-Pulorejo ini
membentang sepanjang 130 m yang terbagi atas 3 span. Span
pertama memiliki bentang 40 meter, sedangkan span kedua
memiliki bentang 50 meter,dan span ketiga 40 meter. Dengan lebar
jembatan sebesar 13,5 meter ,jembatan ini di lengkapi oleh dua
abutmen dan 2 pilar dengan 2 kolom pada masing-masing
pilar.Jembatan Beton ini dibangun dengan PCI girder prestress.
Perhitungan waktu dan biaya pada proyek pembangunan
jembatan Blotoo – Pulorejo, Kota Mojokerto ini menggunakan
gambar desain dari pemerintah kota Mojokerto. Serta untuk
perhitungan biaya di gunakan HSPK kota mojokerto tahun 2014.
Pada pembangunan jembatan ini di pilih metode launching girder
dengan Menggunakan Steel Trust crane.
Penggunaan Metode Launching girder Dari hasil
perhitungan waktu yang dilakukan dengan bantuan software Ms.
Project kami mendapatkan lama waktu penyelesaian
pembangunan bangunan struktur jembatan dari mulai abutmen
hingga slab lantai adalah 361 hari. Sedangkan proyek ini
membutuhkan dana sebesar Rp. 85,445,202,075.24 .
========================================================================================================
Preparation of the final project is about planning time and cost of
the bridge construction project Blootoo-Pulorejo, Mojokerto.
Blooto- Pulorejo Bridge is a Mojokerto’s government project in
order to improve public facilities expected later to facilitate the
access of blooto districts to Pulorejo districts or otherwise. Blooto-
Pulorejo bridge stretches along 130 m and is divided into three
span. The first span is 40 meters, while the second span is 50
meters, and a third span is 40 meters. With a width of 13.5 meter ,
the bridge is equipped by two abutments and two pillars with two
columns on each pilar. This Concrete Bridge is built with PCI
girder prestress.
Timing and cost of the bridge construction project Blotoo -
Pulorejo, Mojokerto using the design drawings of the Mojokerto’s
government. As well as for the calculation of the cost in use HSPK
Mojokerto city in 2014. In the construction of this bridge in the
select method of launching girder crane Using the Steel Trust.
Methods of use Launching girder From the calculation time is done
with the help by Ms. Project software we get 361 days to build the
structure of bridge began from abutment to the floor slab. While
this project needs cost about Rp. 85,445,202,075.24.

Item Type: Thesis (Diploma)
Additional Information: RSS 624.2 Hut p
Uncontrolled Keywords: Waktu, Biaya, Steel Truss Crane
Subjects: T Technology > TF Railroad engineering and operation > TF193 Estimates, costs, etc.
T Technology > TG Bridge engineering
Divisions: Faculty of Civil Engineering and Planning > Civil Engineering > 22401-(D3) Diploma 3
Depositing User: Mr. Tondo Indra Nyata
Date Deposited: 25 Jun 2019 02:47
Last Modified: 25 Jun 2019 02:47
URI: http://repository.its.ac.id/id/eprint/63223

Actions (login required)

View Item View Item