Analisis stabilitas transien dan pelepasan beban di PT. Petrokimia Gresik menggunakan metode rate of change of frequency

Sucahyo, Riski Arif (2015) Analisis stabilitas transien dan pelepasan beban di PT. Petrokimia Gresik menggunakan metode rate of change of frequency. Undergraduate thesis, Institut Teknologi Sepuluh Nopember.

[thumbnail of 2213105050-Undergraduate_Thesis.pdf]
Preview
Text
2213105050-Undergraduate_Thesis.pdf

Download (1MB) | Preview

Abstract

PT.PETROKIMIA Gresik mengoperasikan Gas Turbine Generator
(GTG Plant-I) 1x33 MW, Steam Turbine Generator (STG Plant-III)
1x11.5 MW dan 1x8.5 MW serta Daya dari PLN dengan kontrak 20
MVA. Pada tahun 2010 Petrokimia akan meningkatkan keandalan
dengan menambahkan satu unit pembangkit Steam Turbine Generator
(STG KEBB Plant) sebesar 1x32 MW. Untuk meningkatkan keandalan
dan spining reserve, Unit-unit pembangkit tersebut akan diintegrasikan
langsung ke sistem tegangan 20 KV. Dengan kondisi normal 4 unit
beroperasi. Kapasitas total beban listrik yang dipergunakan adalah 53,7
MW.Pada tugas akhir ini difokuskan pada Analisis Stabilitas transien
yang meliputi Kestabilan tegangan dan kestabilan frekuensi , serta
pelepasan beban (load shedding) saat terjadi gangguan generator lepas /
trip . Pelepasan beban secara otomatis dengan menggunakan Relay
Frekuensi dapat mencegah penurunan frekuensi dan mengembalikan ke
kondisi frekuensi yang normal .Kasus ini akan dianalisa dengan
menggunakan bantuan software ETAP 12.6 Power station . Dari jenis
gangguan penyebab stabilitas transien yang hanya dianalisa pada tugas
akhir ini di fokuskan saat terjadi gangguan generator lepas/trip yang
memerlukan pelepasan beban (load shedding ) sebesar 17.2 MW untuk
mengembalikan respon frekuensi dan tegangan agar sistem berada
dalam kondisi stabil .

=================================================================================================

PT.PETROKIMIA Gresik Gas Turbines operate Generator ( GTG Plant
- I) 1x33 MW Steam Turbine Generator ( STG Plant - III ) 1x11.5 MW
and 1x8.5 MW And Power Of Contract with PLN 20 MVA . On Year
2010 ,PT.PETROKIMIA will increase reliability by adding one Steam
Turbine Generating Unit Generator ( STG KEBB Plant ) of 1x32 MW .
To improve the reliability and spining reserve , units of the power plant
will be integrated directly into the system voltage 20 KV . The four units
are operating under normal conditions . Total capacity of the electrical
load used is 53.7 MW. This it’s focused on transient stability analysis
covering the voltage stability and frequency stability , as well as the
release of the load ( load shedding ) in the event of disturbance
generator off / trip . to release the load shedding by automatically using
Frequency Relay can prevent a decrease in the frequency and return to
the normal frequency conditions . This case will be analyzed with the
help of software ETAP Power station 12.6 . From the type of disorder
causes only transient stability analysis in this final in the event of
disruption generator focused freelance / trip that requires the release of
the load ( load shedding ) of 17.2 MW to restore the frequency response
and voltage for the system to be in stable condition .

Item Type: Thesis (Undergraduate)
Additional Information: RSE 621.319 21 Suc a
Uncontrolled Keywords: stabilitas transien; pelepasan beban
Subjects: T Technology > TK Electrical engineering. Electronics Nuclear engineering > TK1010 Electric power system stability. Electric filters, Passive.
Divisions: Faculty of Electrical Technology > Electrical Engineering > 20201-(S1) Undergraduate Thesis
Depositing User: - Taufiq Rahmanu
Date Deposited: 28 Oct 2019 03:58
Last Modified: 28 Oct 2019 06:36
URI: http://repository.its.ac.id/id/eprint/71445

Actions (login required)

View Item View Item