Effendy, Fenny Megawati (2016) Analisis Risiko Proyek Desain Dan Konstruksi Interior Pada New Dizzi Interior. Undergraduate thesis, Institut Teknologi Sepuluh Nopember.
Preview |
Text
9114202314-Master_Theses.pdf Download (4MB) | Preview |
Preview |
Text
9114202314-paperpdf.pdf Download (780kB) | Preview |
Preview |
Text
9114202314-presentationpdf.pdf Download (2MB) | Preview |
Abstract
Industri desain interior mulai berkembang dan dikenal oleh masyarakat luas.
Sehubung dengan perkembangan dunia properti yang marak, perkembangan bisnis
interior di Surabaya juga berkembang pesat. Sejalan dengan perkembangannya, maka
para pesaing pada industri ini juga bermunculan. New Dizzi Interior adalah salah satu
pemain dalam industri ini dan membutuhkan penerapan manajemen proyek terutama
manajemen risiko untuk menangani proyek-proyek desain dan konstruksi interior yang
terus berkmbang. Pada proyek yang ditangani oleh New Dizzi Interior sering dijumpai
proyek yang mengalami keterlambatan waktu atau pembengkakan biaya dan
berpengaruh kepada kualitas produknya. Hal ini diakibatkan oleh beberapa risiko yang
berpotensi tinggi yang tidak diperhitungkan terlebih dahulu.
Penelitian ini dilakukan dengan metode penelitian studi kasus yang merupakan
salah satu jenis penelitian kualitatif deskriptif. Dalam penelitian ini dilakukan
identifikasi risiko dengan tinjauan survey pendahuluan, tinjauan pustaka dan focus
group discussion guna menentukan variabel yang digunakan dalam penelitian. Dari
hasil identifikasi tersebut akan diadakan survey utama untuk menentukan nilai
probabilitas dan dampak kejadian tesebut. Dari hasil analisis yang didapatkan akan
dibuat respon risiko terhadap risiko-risiko yang untuk mengurangi dampak dan
probabilitas risiko terebut.
Hasil dari penelitian ini menghasilkan 68 variabel risiko yang relevan pada
proyek residensial dengan 50 variabel risiko dengan tingkat rendah dan 18 variabel
risiko dengan tingkat medium. Pada proyek perkantoran dan komersial dihasilkan 72
variabel risiko yang relevan. Dari 72 variabel, 23 variabel risiko dengan tingkat medium
dan 49 variabel risiko dengan tingkat rendah pada proyek perkantoran. Sedangkan pada
proyek komerisal, dari 72 variabel resiko, terdapat 30 variabel risiko dengan tingkat
medium dan 42 varaibel dengan tingkat rendah. Respon risiko yang dilakukan pada
probablitas dari 18 variabel risiko dengan tingkat medium pada proyek residensial:
respon probabilitas untuk 5 variabel diterima dan 13 variabel dikurangi, sedangkan
respon terhadap dampak 2 variabel risiko ditransfer, 5 dampak variabel risiko diberi
respon untuk menerima dan mengurangi dan 11 variabel risiko yang lain dampak dari
risiko tersebut akan dikurangi. Untuk kategori proyek perkantoran, dari 23 variabel
risiko, 2 variabel mendapat respon probabilitas untuk diterima dan 21 variabel risiko
untuk dikurangi. Sedangkan respon terhadap dampak 2 variabel risiko ditransfer, 1
variabel resiko diberi respon menerima dan transfer, 3 variabel mentransfer dan
mengurangi, 4 variabel mengurangi dan menerima, dan mengurangi dampak pada 13
variabel risiko. Pada proyek komersial, dari 30 variabel risiko tingkat medium respon
probabilitas pada 3 variabel risiko dengan menerima dan 27 variabel risiko yang lainnya
dengan mengurangi. Sedangkan respon terhadap dampak pada 30 variabel risiko: 4
variabel risiko ditransfer, 5 variabel risiko diberi respon untuk menerima dan
mengurangi, 1 variabel resiko diberi respon menerima dan transfer, 3 variabel transfer
dan mengurangi, dan 17 variabel risiko mengurangi. ========== Interior design has been a growing industry and has been known widely in the
society. In Surabaya, the rapid development of real estate business has brought up the
development pace of interior design industry. In line with its development, the
competitors in interior industry are emerging. Project management, specifically risk
management, is crucial for this company to manage the projects and ultimately to attract
more customers. New Dizzi Interior also suffers from delays in their projects, cost
overrun, and quality deterioration, which most likely resulted from the lack of risk
calculation and management.
This study will be conducted with the case study method, which is one type of
descriptive qualitative research. In this research will identifiedy risks with preliminary
surveys, literature review and focus group discussion to determine the variables used in
the study. Main survey is conducted on those variables to determine the probability of
the risk occurrence and the extent of damage caused by the risk event. Responses
against risk events are analyzed in order to reduce the probability and damage of the
event.
Results of this study identified 68 variables relevant for residential projects, 50
variables are low level risk and 18 variables are medium level risks. For office projects,
72 variables were identified its relevancy, 23 variables are medium risk levels and 49
variables are low level risks. Whereas for commercial projects, 72 variables were
identified its relevancy, 30 variables are medium level and 43 variables are low level
risk. Risk responses for 18 medium level risk variables for residential pojects: risk
responses for risk probability are: accept 5 variables and mitigate 13 variables. While
risk responses for risk impact are: transfer 2 variables, accept and mitigate 5 variables,
mitigate 11 variables. Risk responses for 23 medium level risk variables for office
projects, risk responses for risk probability are: accept 2 variables, and mitigate 21
variables. While risk responses for risk impact are: transfer 2 variables, accept and
transfer 1 variable, transfer and mitigate 3 variables, mitigate and accept 4 variables,
and mitigate 13 variabels. Risk responses for 30 medium level risk variables for
commercial projects, risk responses for risk probability are: accept 3 variables, mitigate
27 variables. While risk responses for risk impact are: transfer 4 variables, accept and
mitigate 5 variables, accept and transfer 1 variable, transfer and mitigate 3 variables,
and mitigate 17 variables.
Item Type: | Thesis (Undergraduate) |
---|---|
Additional Information: | RTMT 658.155 4 Eff a 3100016067846 |
Uncontrolled Keywords: | analisis risiko, respon risiko, desain interior, konstruksi interior, risk analysis, risk response, interior design, interior construction |
Subjects: | H Social Sciences > HD Industries. Land use. Labor > HD61 Risk Management |
Divisions: | 61101-Magister Management Technology |
Depositing User: | - Davi Wah |
Date Deposited: | 20 Nov 2019 03:17 |
Last Modified: | 20 Nov 2019 03:17 |
URI: | http://repository.its.ac.id/id/eprint/71909 |
Actions (login required)
View Item |