Analisis Optimasi Waktu Dan Biaya Dengan Metode Time Cost Trade Off (TCTO) Pada Proyek Pembangkit Listrik Tenaga Panas Bumi (PLTP) Ulubelu Unit 3&4, Lampung

Fauzan, Rifqi (2016) Analisis Optimasi Waktu Dan Biaya Dengan Metode Time Cost Trade Off (TCTO) Pada Proyek Pembangkit Listrik Tenaga Panas Bumi (PLTP) Ulubelu Unit 3&4, Lampung. Undergraduate thesis, Institut Technology Sepuluh Nopember.

[thumbnail of 3112100126-Undergraduate Thesis.pdf]
Preview
Text
3112100126-Undergraduate Thesis.pdf - Published Version

Download (4MB) | Preview

Abstract

Pembangunan proyek Pembangkit Listrik Tenaga Panas Bumi Ulubelu Unit 3&4, Lampung ini khususnya pada unit 3 mengalami keterlambatan. Berdasarkan laporan pada tanggal 20 November 2015 kinerja total proyek mencapai 42.55% dari target awal sebesar 51.63%. Disisi lain pihak owner meminta dilakukannya percepatan agar dapat mereduksi keterlambatan yang terjadi sehingga proyek bisa selesai pada waktu yang sudah direncanakan. Percepatan akan dilakukan pada pekerjaan Cooling Tower Unit 4.
Tugas Akhir ini menggunakan metode Time Cost Trade Off (TCTO) yaitu metode penjadwalan proyek dengan melakukan pertukaran waktu dan biaya. Metode ini bertujuan untuk mempercepat waktu penyelesaian proyek dengan penambahan biaya yang optimum terhadap kegiatan yang dipercepat waktu pekerjaannya. Alternatif percepatan yang digunakan pada Tugas Akhir ini yaitu menambah jam kerja atau lembur dan menambah jumlah pekerja,
Dari hasil analisis dengan metoda Time Cost Trade Off ini didapatkan hasil bahwa pada pembangunan Cooling Tower Unit 4 dilakukan percepatan selama 42 hari dengan penambahan biaya sebesar Rp3.518.293.530,00. Total durasi proyek yang normalnya selama 209 hari menjadi 167 hari dengan biaya total proyek setelah percepatan sebesar Rp23.642.856.246,49.
=============================================================================================================
Construction of Ulubelu Unit 3&4 Geothermal Power Plan Project, Lampung especially on unit 3 has been delayed. Based on the report on 20 November 2015 the performance of the total project reaches 42.55% from the initial target of 51.63%. On the other hand the owner requesting the acceleration in order to reduce delays so that the project could be completed in the time planned. Acceleration will be done on construction of Cooling Tower Unit 4.
This final project using Time Cost Trade Off (TCTO). It is the method of project scheduling by exchanging time and cost. This method aims to accelerate project completion time with the addition of optimum cost for the activity being accelerated time job. Acceleration alternative in this final project is add working hours or overtime and increased the number of workers.
From the analysis by the method Time Cost Trade Off, This showed that the construction of Cooling Tower Unit 4 to be accelerated for 42 days by adding a fee of Rp3.518.293.530,00. The total duration of the project, which is normally for 209 days to 167 days at a total cost of the project after the acceleration of Rp23.642.856.246,49.

Item Type: Thesis (Undergraduate)
Additional Information: RSS 333.793 2 Fau a
Uncontrolled Keywords: Cooling Tower Unit 4, percepatan penyelesaian proyek, TCTO
Subjects: T Technology > TK Electrical engineering. Electronics Nuclear engineering > TK1322.6 Electric power-plants
Divisions: Faculty of Civil Engineering and Planning > Civil Engineering > 22201-(S1) Undergraduate Thesis
Depositing User: Mr. Tondo Indra Nyata
Date Deposited: 02 Jan 2020 04:50
Last Modified: 02 Jan 2020 04:50
URI: http://repository.its.ac.id/id/eprint/72492