Abstract

Pada pelaksanaan suatu proyek, alat berat memegang
peranan penting karena dapat mempermudah dan membantu
pekerja dalam menyelesaikan proyek terutama untuk proyek
dengan skala besar. Alat berat yang akan digunakan pada suatu
proyek harus dianalisa untuk optimalisasi waktu dan biaya
pelaksanaan proyek. Peralatan berat yang digunakan pada Tugas
akhir ini meliputi alat berat untuk pekerjaan basement dan
pekerjaan struktur seperti wheel loader, excavator, dump truck,
bore machine, tower crane, concrete pump dan truk mixer.
Penelitian ini dilakukan untuk menganalisa kebutuhan
pemakaian alat berat meliputi analisa produktivitas alat berat,
waktu pelaksanaan dan perhitungan biaya peralatan. Khusus
untuk tipe alat berat sudah ditentukan terlebih dahulu..Alat berat
yang digunakan pada eksisting yaitu Excavator Caterpillar 320d,
Dump Truk Mitshubishi FE 73HD, Wheel Loader Komatsu
WF350-3, Bore Pile Machine Kobelco BM500, Tower Crane
Tengda TC6018, Concrete Pump IPF90B-5N21, Truk Mixer Hino
7m.3.Waktu pelaksanaan ditentukan dari beban kerja alat dan
produktivitas dari peralatan yang digunakan. Sedangkan biaya
pelaksanaan yang diperhitungkan adalah biaya sewa, biaya
mobilisasi dan demobilisasi, dan biaya operasi seperti bahan
bakar, pelumas, dan operator.
Dari hasil perhitungan menunjukkan bahwa alat berat
yang dibutuhkan yaitu 1 unit Excavator Kobelco SK-200, 12 unit
ii
Dump Truk Nissan CWA 18T, 1 unit Wheel Loader CAT 950H, 1
unit Tower Crane Potain MC 310 k12, 1 Concrete Pump
Zoomlion 36X-5Z, 679 unit Truk Mixer, dan 1 unit Bore Machine
Jove JVR 180D. Besarnya biaya penggunaan alat berat tersebut
yaitu Rp. 5.888.343.100,00 dengan total waktu penyelesaian yaitu
361 hari
=========================================================================== On project implementation, heavy equipment have an
important role because it can make it easier and help the workers
to complete his work especially for large scale project. Utilization
of heavy equipment should be analize to optimized the time and
cost . In this research, the heavy equipments are applied to
perform basement structure such as wheel loader, excavators,
dump trucks, bore machine, tower crane, concrete pump and
mixer trucks.
This research done to analyze the requirement of the
usage of heavy equipment includes the productivity analysis, to
calculate the time and the cost. The Specification of heavy
equipment has been determined in advance. Heavy equipment is
used on existing is Excavators Caterpillar 320d, Dump Truck
Mitsubishi FE 73HD, Wheel Loader Komatsu WF350-3, Bore
Pile Machine Kobelco BM500, Tower Crane Tengda TC 6018,
Concrete Pump IPF90B said MU-5N21, Truck Mixer Hino 7m.
The implementation of time determined from the workload of the
appliance and the productivity of the company of the equipment
that is used. While the cost of the mobilisation and
demobilisation, and operating costs such as fuel, lubricants and
operator.
iv
The result of the calculation shows that heavy equipment
needed 1 unit Excavators Kobelco SK-200, 12 units Dump Truck
Nissan CWA 18T, 1 units of CAT Wheel Loader 950H, 1 unit
Tower Crane Potain MC 310 k12, 1 Concrete Pump Zoomlion
36X-5Z, 994 units Truck Mixer and 1 unit Bore Machine Jove
JVR 180D. The greatness of the cost of the use of heavy
equipment is Rp 5.888.343.100,00 with total time settlement of
361 days

Item Type: Thesis (Undergraduate)
Additional Information: RSS 624.028 4 Pur a
Uncontrolled Keywords: Alat Berat, Produktivitas, Waktu dan Biaya
Subjects: H Social Sciences > HD Industries. Land use. Labor > HD28 Management. Industrial Management
T Technology > TA Engineering (General). Civil engineering (General) > TA681 Concrete construction
Divisions: Faculty of Civil Engineering and Planning > Civil Engineering > 22201-(S1) Undergraduate Thesis
Depositing User: EKO BUDI RAHARJO
Date Deposited: 13 Jan 2020 02:39
Last Modified: 13 Jan 2020 02:39
URI: http://repository.its.ac.id/id/eprint/72640

Actions (login required)

View Item View Item