Economic dispatch Pada Sistem Transmisi Jawa-Bali 500KV Berdasarkan RUPTL Tahun 2015-2024 Menggunakan Metode Time Varying Acceleration Berbasis Particle Swarm Optimization (TVAC-PSO)

Oktawijaya, Tommy Andre (2016) Economic dispatch Pada Sistem Transmisi Jawa-Bali 500KV Berdasarkan RUPTL Tahun 2015-2024 Menggunakan Metode Time Varying Acceleration Berbasis Particle Swarm Optimization (TVAC-PSO). Undergraduate thesis, Institut Teknologi Sepuluh Nopember.

[thumbnail of 2214105046-Undergraduate_Thesis.pdf]
Preview
Text
2214105046-Undergraduate_Thesis.pdf - Accepted Version

Download (2MB) | Preview

Abstract

Dengan proyeksi pertumbuhan ekonomi negara Republik Indonesia
sebesar 6 hingga 7 persen pertahun serta pusat kegiatan ekonomi dan
industri masih berada di kawasan Jawa – Bali. Dalam dalam lima tahun
kedepan penambahan kapasitas sebesar 35.000 MW menjadi suatu
kebutuhan, jumlah tersebut telah dikukuhkan dalam dokumen RUPTL
PLN 2015-2024. Dalam RUPTL tersebut disebutkan bahwa pada sistem
jawa bali akan ditambah unit pembangkitnya. Dengan adanya
penambahan unit pembangkit serta pertumbuhan beban, akan mengubah
biaya pembangkitan energi listik, maka perlu dicari solusi untuk
mengoperasikan unit-unit pembangkit secara optimal dengan menekan
biaya bahan bakar seminimum mungkin yang disebut juga dengan
economic dispatch (ED), banyaknya unit pembangkit termal tentu
menibulkan permasalahan lingkungan akibat emisi NOx yang disebut
juga dengan economic emission dispatch (EED). Pada tugas akhir ini data
yang digunakan tanpa mempertimbangkan kerugian transmisi.
Permasalahan economic dispatch diselesaikan dengan menggunakan
metode Time Variying Acceleration Berbasis Particle Swarm
Optimization (PSO). Dari hasil simulasi didapatkan ED maupun EED
menggunakan TVAC-PSO menunjukkan bahwa metode ini lebih unggul
dari PSO konvensional, selain menunjukkan waktu konvergen yang
relatif lebih cepat. Program akan disimulasi dan ditampilkan
menggunakan software Matlab
========================================================================================================================
With economic growth projections of the Republic Indonesia by
6 to 7 percent per year as well as the center of economic and industrial
activity still in the area of Java - Bali. In the next five years by 35,000
MW additional capacity becomes a necessity, that number has been
confirmed in the document RUPTL PLN 2015-2024. In RUPTL
mentioned that the Java Bali system will be added some of generator unit.
With the addition of generating units and load growth, will change the
cost of generating electric energy, it is necessary to find a solution to
operate the generating units optimally to reduce the cost of fuel to a
minimum which is also called the economic dispatch (ED), the number of
units of thermal power plant would menibulkan environmental problems
due to emissions of NOx emission is also called the economic dispatch
(EED). The data that used in this final project are without considering
transmission losses. Economic dispatch problems solved using the
method called Time variying Acceleration - Based on Particle Swarm
Optimization (PSO). From the simulation results obtained using the EED
or ED with TVAC-PSO shows, that this method is superior to the
conventional PSO, in addition to showing the time convergent relatively
faster. The program will be simulated and displayed using Matlab
software

Item Type: Thesis (Undergraduate)
Additional Information: RSE 621.310 151 Okt e
Uncontrolled Keywords: Economic Dispatch, PSO, PSOTVAC,Matlab
Subjects: T Technology > TK Electrical engineering. Electronics Nuclear engineering > TK3226 Transients (Electricity). Electric power systems. Harmonics (Electric waves).
Divisions: Faculty of Industrial Technology > Electrical Engineering > 20201-(S1) Undergraduate Thesis