Putri, Tiar Anindya (2016) Penerapan Goal Programming Pada Optimasi Penjadwalan Proyek Pelebaran Jalan (Studi Kasus: Balai Besar Pelaksanaan Jalan Nasional V Kementrian Pekerjaan Umum Dan Perumahan Rakyat). Undergraduate thesis, Institut Teknologi Sepuluh Nopember Surabaya.
Preview |
Text
5212100086-Undergraduate_Thesis.pdf - Published Version Download (1MB) | Preview |
Abstract
Beberapa teknik untuk melakukan optimasi pernjadwalan proyek
telah dikembangkan dengan tujuan meminimalkan durasi proyek.
Akan tetapi pada situasi sebenarnya, penjadwalan proyek memiliki
beberapa tujuan yang bertentangan yang harus diatasi oleh seorang
Project Manager (PM). Melalui tugas akhir, metode Goal
Programming digunakan untuk menyelesaikan berbagai macam
masalah optimasi, termasuk salah satunya adalah masalah
penjadwalan proyek dengan tujuan yaitu meminimalkan durasi
penyelesaian proyek, meminimalkan biaya total proyek, dan
memaksimalkan capaian tiap-tiap aktivitas dengan acuan batasan
anggaran yang telah di tetapkan.
Penggunaan model Goal Programming untuk masalah-masalah
penjadwalan proyek ini banyak digunakan dikarenakan oleh
kemampuannya untuk bisa mengolah penyelesaian yang memiliki
banyak obyektif secara bersamaan. Kemudian diterapkan pula
metode PERT untuk mengukur tingkat ketepatan estimasi durasi
penyelesaian suatu proyek. Hasil keluaran yang didapatkan yaitu
berupa rekomendasi pengambilan keputusan terhadap kontrak
penjadwalan berupa alternative penjadwalan sesuai durasi yang
optimal dengan memperhatikan anggaran, waktu selesai, dan capaian
tiap aktivitas. Hasil akhir yang didapatkan berupa jadwal optimal
pengerjaan aktivitas proyek yang disajikan dalam bentuk Gantt Chart
agar lebih mudah dipahamidengan penyajian aktivitas-aktivitas
proyek dan durasi penyelesaian dengan urutan aktivitas yang
dikerjakan sesuai dengan kontrak awal
==========================================================================================Some techniques for optimizing the scheduling of the project has been
developed with the aim of minimizing the duration of the project [1].
in a real situation, project scheduling has several conflicting
objectives that must be overcome by a Project Manager (PM).
Through the final project, the method Goal Programming is used to
solve a wide range of optimization problems, one of them is the
problem of scheduling a project with the goal of minimizing the
completion time of the project, minimizing the total cost of the project,
and maximize the performance of each activity by reference to the
budget constraint that has been set.
The amount of use of this model for optimization problems scheduling
the project, due to its ability to process the settlement has many
objectives simultaneously. PERT is then applied on a method to
measure the level of reliability of the estimated time of completion of
a project.
The output is expected in the form of recommendations to the decisionmaking
contracts optimal scheduling by considering the budget, end
time, and the outcomes of each activity. The output gained is an
optimal schedull with total completion time of the project the most
minimal presented in the form of Gantt Chart to make it more easily
understood
Item Type: | Thesis (Undergraduate) |
---|---|
Additional Information: | RSIf 006.382 4 Put p-1 |
Uncontrolled Keywords: | Proyek, Penjadwalan Proyek, Optimasi, Goal Programming, teknik PERT |
Subjects: | Q Science > Q Science (General) > Q337.3 Swarm intelligence |
Divisions: | Faculty of Information Technology > Information System > 57201-(S1) Undergraduate Thesis |
Depositing User: | EKO BUDI RAHARJO |
Date Deposited: | 21 Feb 2020 06:52 |
Last Modified: | 21 Feb 2020 06:52 |
URI: | http://repository.its.ac.id/id/eprint/75105 |
Actions (login required)
View Item |