Penjadwalan Pelaksanaan Ditinjau Dari Segi Biaya Dan Waktu Pada Gedung Fakultas Syariah Universitas Islam Negeri Sunan Ampel (Uinsa) Surabaya

Vilyanto, Maulana Ardy (2016) Penjadwalan Pelaksanaan Ditinjau Dari Segi Biaya Dan Waktu Pada Gedung Fakultas Syariah Universitas Islam Negeri Sunan Ampel (Uinsa) Surabaya. Diploma thesis, Institut Teknologi Sepuluh Nopember Surabaya.

[thumbnail of 3113030120-Non_Degree.pdf]
Preview
Text
3113030120-Non_Degree.pdf - Published Version

Download (4MB) | Preview

Abstract

Proyek pembangunan gedung Syariah Universitas Islam
Negeri Sunan Ampel (UINSA) Surabaya memerlukan
penjadwalan pelaksanaan yang ditinjau dari perhitungan biaya dan
waktu pelaksanaan. Perencanaan anggaran biaya dan waktu lebih
ditekankan sesuai dengan kenyataan di lapangan yaitu berdasarkan
harga di lapangan sebenarnya dan sumber referensi buku: Analisa
(cara modern) Anggaran Biaya Pelaksanaan karangan Ir. A
Soedrajat S, dan buku referensi untuk kontraktor karangan PT PP
(Persero) TBK

Untuk menghitung RAP dan Penjadwalan Waktu
pelaksanaan perlu dihitung terlebih dahulu volume dan
produktivitas pada setiap item pekerjaan, tentunya dengan
mempertimbangkan metode yang sesuai yang dapat diterapkan
dilapangan berdasarkan RKS. Setelah perhitungan volume tiap
item pekerjaan selesai dapat diketahui harganya dengan
menggunakan harga yang ada di pasaran/lapangan setempat.
Dalam menentukan durasi setiap item pekerjaan menggunakan
referensi buku yang telah disebutkan diatas ataupun koefisien yang
ada pada di HSPK apabila diperlukan

Hasil akhir dari analisa dan perhitungan pada tugas akhir
ini adalah Rencana Anggaran Biaya Pelaksanaan (RAP) atau Real
Cost dan juga penjadwalan berupa kurva-S yang diperlukan
sebagai acuan realisasi pelaksanaan pembangunan struktur gedung
Fakultas Syariah UINSA Surabaya.
========================================================================================Building project sharia state islamic university sunan
ampel (uinsa) surabaya require scheduling implementation in terms
of cost and time of implementation. Budget planning time and costs
is emphasized in accordance with the reality on the region of this
project that the actual execution price based on primary data in
accordance with the reality on the ground and source of reference
books: analysis (the modern way) budget implementation
arrangements ir. A soedrajat s, and reference books for essay
contractor pt pp (persero) tbk
To analyze the real cost and time schedule needs to be
calculated in advance the volume and productivity at each work
item, of course taking into account the appropriate methods that
can be applied in field. After calculating the volume, price of item
of works can be determined using local price or the contractor
price. Then duration of each work items can be calculated based on
the reference of books mentioned above, or coefficients hspk at
region of this project.
The final results of the analysis and calculations in this
report is the final budget of projects implementation (Real Cost)
and the time schedule implementation as S-Curve of the structure
construction of Sharia Faculty UINSA at Surabaya

Item Type: Thesis (Diploma)
Additional Information: RSS 690.831 Vil p-I
Uncontrolled Keywords: Manajemen Proyek, Proyek Gedung, Proyek Gedung UINSA Surabaya, Biaya Pelaksanaan, Waktu Penjadwalan, Penjadwalan Pelaksanaan, Waktu dan Biaya Pelaksanaan, Kurva-S
Subjects: T Technology > TH Building construction > TH437 Building--Cost control.
Divisions: Faculty of Civil Engineering and Planning > Civil Engineering > 22401-(D3) Diploma 3
Depositing User: EKO BUDI RAHARJO
Date Deposited: 13 Mar 2020 03:13
Last Modified: 13 Mar 2020 03:13
URI: http://repository.its.ac.id/id/eprint/75472