Kajian Percepatan Penjadwalan Pembangunan Landing Craft Utility (LCU) Dengan Metode Simulasi Monte Carlo

Bustamin, Maulidya Octaviani (2015) Kajian Percepatan Penjadwalan Pembangunan Landing Craft Utility (LCU) Dengan Metode Simulasi Monte Carlo. Masters thesis, Institut Teknologi Sepuluh Nopember.

[thumbnail of 9112202407-Master_Thesis.pdf]
Preview
Text
9112202407-Master_Thesis.pdf - Accepted Version

Download (7MB) | Preview

Abstract

Suatu pelaksanaan konstruksi proyek biasanya mengalami keterlambatan waktu pelaksanaan yang cukup lama sehingga harus pula mengeluarkan biaya lebih. Sesuai dengan perjanjian kerja sebuah pembangunan kapal akan banyak hal yang akan disepakati berkaitan dengan pembangunan kapal tersebut salah satunya proses pembangunan Hull Construction LCU. Untuk tercapainya proses pembangunan pada waktu yang telah ditentukan dan mendapatkan kualitas produksi yang diharapkan, maka urutan dari proses pembangunan sebuah kapal harus ditentukan secara rasional dan disesuaikan dengan fasilitas produksi yang tersedia di galangan. Tujuan dari penyusunan Tesis ini adalah untuk membuat penjadwalan probabilistik yang sifatnya tidak tentu yang mengakibatkan proyek pembangunan melebihi estimasi waktu yang telah direncanakan. Penelitian mengenai penjadwalan probabilistic pada Tesis ini akan diaplikasikan pada proyek pembangunan kapal Landing Craft Utility (LCU). Tahap yang akan dilakukan antara lain dengan cara mengumpulkan data penjadwalan proyek, menentukan hubungan antar aktivitas proyek, melakukan estimasi durasi aktivitas proyek serta melakukan simulasi dengan mengunakan Monte Carlo Simulation. Dari hasil simulasi didapatkan pengerjaan pembangunan Landing Craft Utiliy pada bagian Hull Construction, yang semula selama 102 hari dipercepat menjadi 99 hari dengan tingkat keyakinannya sebesar 100%, 94 hari tingkat keyakinannya hingga sebesar 60%, dan untuk percepatan menjadi 90 hari tingkat keyakinannya hanya sebesar 3%. Berdasarkan hasil tersebut didapatkan durasi optimal selama 94 hari dengan percepatan penjadwalan pembangunan kapal LCU selama 8 hari dengan penambahan biaya tenaga kerja yang harus dikeluarkan sebesar Rp 27.300.000,- atau sekitar 9,8% dari keseluruhan biaya tenaga kerja pembangunan konstruksi badan kapal.
====================================================================================================
The implementation of the project usually have a time delay implementation for long time enough, so it must also spend much cost. In an employment agreement a ship construction will many things that will be agreed upon with regard to the construction of the vessel one Hull Construction LCU development process. For the achievement of the development process at a predetermined time and get quality production is expected, then the order of the process of ship building should be determined rationally and be adopted with the production facilities available in the shipyard. The purpose of this thesis is to make probabilistic scheduling that are not necessarily the result of development projects exceeds the estimated time has been planned. Research on probabilistic scheduling in this thesis will be applied to the construction of the ship Landing Craft Utility (LCU). Stage that would be done, among others, by collecting data project scheduling, determining the relationship between project activities, to estimate the duration of the project activities and conduct simulations using the Monte Carlo Simulation Method. From the simulation results obtained Landing Craft utiliy construction workmanship in the Hull Construction, which had accelerated during the 102 days to 99 days with its confidence level of 100%, 94 day rate of conviction of up to 60%, and to accelerate the rate of convictions to 90 days amounted to only 3%. Based on the results obtained during the optimal duration of 94 days with the acceleration of the construction scheduling LCU for 8 days with the addition of labor costs amounted to USD 27.3 million or about 9.8% of the total cost.

Item Type: Thesis (Masters)
Additional Information: RTMT 518.282 Bus k
Uncontrolled Keywords: Landing Craft Utility, Monte Carlo Simulation, Hull Construction, Percepatan Penjadwalan
Subjects: H Social Sciences > HD Industries. Land use. Labor > HD69.T54 Time management. Scheduling
H Social Sciences > HT Communities. Classes. Races > HT133 City and Towns. Land use,urban
Divisions: 61101-Magister Management Technology
Depositing User: Yeni Anita Gonti
Date Deposited: 03 Apr 2020 09:32
Last Modified: 03 Apr 2020 09:32
URI: http://repository.its.ac.id/id/eprint/75681

Actions (login required)

View Item View Item