Perencanaan Perbaikan dan Perkuatan Tanah pada Lahan Reklamasi (Studi Kasus : Perluasan Container Yard Terminal Teluk Lamong, Surabaya, Jawa Timur)

Iswanto, Almaretha Mevia Azizah Putri (2020) Perencanaan Perbaikan dan Perkuatan Tanah pada Lahan Reklamasi (Studi Kasus : Perluasan Container Yard Terminal Teluk Lamong, Surabaya, Jawa Timur). Other thesis, Institut Teknologi Sepuluh Nopember.

[thumbnail of 03111640000032_Undergraduate_Thesis.pdf]
Preview
Text
03111640000032_Undergraduate_Thesis.pdf

Download (15MB) | Preview
[thumbnail of 03111640000032_Undergraduate_Thesis.pdf]
Preview
Text
03111640000032_Undergraduate_Thesis.pdf

Download (15MB) | Preview

Abstract

PT. Pelabuhan Indonesia (Pelindo) III mengelola beberapa terminal yang tersebar dalam 7 Provinsi di Indonesia. Pada tahun 2018, Pelindo III mengalami peningkatan arus peti kemas sebesar 8,5% dari tahun sebelumnya. Dari kenaikan tersebut menjadi alasan besar bahwa diperlukan lapangan penumpukan peti kemas (container yard) baru; container yard tersebut direncanakan berada di sebelah container yard yang lama di Terminal Teluk Lamong, Surabaya. Perluasan container yard tersebut akan dibangun di atas lahan reklamasi seluas 655 x 648,7 m.
Berdasarkan proses penyelidikan yang dilakukan pada
April 2018 meliputi hasil bore-log dan N-SPT serta pengecekan undisturbed soil pada laboratorium, didapatkan kondisi tanah dasar berupa lapisan tanah lunak yang compressible setebal 4-18 meter. Hal–hal tersebut menjadi permasalahan utama dalam perencanaan reklamasi sehingga perlu dilakukan perbaikan pada tanah dasarnya. Perbaikan tanah dasar yang digunakan pada lahan reklamasi ini menggunakan gabungan dari dua metode yaitu metode preloading dan pemasangan Prefabricated Vertical Drain (PVD). Kedua metode tersebut digunakan untuk meningkatkan daya dukung tanah dan mempercepat pemampatan.
Untuk metode preloading, yang dilakukan adalah memberikan beban awal secara bertahap sebesar 5,7 m untuk area A, untuk area B adalah 10,1 m, untuk area C adalah 6,4 m, dan untuk area D adalah 7,4 m. Pemasangan PVD hanya pada area yang tertentu yang memiliki waktu pemampatan > 1 tahun yaitu area A dipasang sepanjang 5 meter dan area B dipasang sepanjang 15 meter dengan jarak antar PVD sebesar 1 m. Sedangkan untuk area D tidak menggunakan PVD namun dengan mengganti tanah dasar dengan tanah timbunan. Pondasi untuk Automatic Stacking Crane direncanakan dengan menggunakan pondasi tiang pancang sepanjang 30 m untuk area B dan 15 m untuk area A dan area C.

============================================

PT. Pelabuhan Indonesia (Pelindo) III manages several
terminals that spread in 7 Provinces in Indonesia. In 2018, Pelindo III had an increase in container flow by 8,5% from the previous year. From that condition, there is a big reason that a new container yard is needed and planned on the next of the old container yard at the Terminal Teluk Lamong, Surabaya. The expansion of the container yard will be built on a reclamation area within a size of 655 m x 648,7 m.
Based on the investigation process in April 2018 that includes results of bore-log and N-SPT also checking the undisturbed soil in the laboratory, found the based soil condition is formed of compressible soft soil layer within 4 – 18 meter. These things become the main problems in the planning of the reclamation area, so it needs to have soil improvement. Soil improvement on a reclamation area uses a combination of two methods that is preloading and installation of Prefabricated Vertical Drain (PVD). Both methods used to increase the soil bearing capacity and accelerate the consolidation.
For the preloading method, which was to provide a gradually initial charge of 5.7 m for Area A, for Area B was 10.1 m, for Area C was 6.4 m, and for Area, D was 7.4 m. The installation of PVD is only in certain areas that have a time of consolidation > 1 year, in Area A is installed along 5 meters and Area B was 15 meters with a distance between of PVD is 1 m. Whereas for Area D it does not use PVD but by replacing the based soil with landfill soil. Foundations for Automatic Stacking Crane use a pile foundation along 30 m for Area B and 15 for Area A and Area C.

Item Type: Thesis (Other)
Additional Information: RSS 624.151 363 Isw p-1
Uncontrolled Keywords: container yard, perkuatan tanah, pondasi ASC, prefabricated vertical drain, reklamasi, reclamation, soil improvement
Subjects: T Technology > TA Engineering (General). Civil engineering (General) > TA455.S6 Soil (Materials of engineering and construction)
Divisions: Faculty of Civil Engineering and Planning > Civil Engineering > 22201-(S1) Undergraduate Thesis
Depositing User: ALMARETHA MEVIA AZIZAH PUTRI ISWANTO
Date Deposited: 11 Aug 2020 03:29
Last Modified: 26 May 2023 15:08
URI: http://repository.its.ac.id/id/eprint/77396

Actions (login required)

View Item View Item