Anshori, Muhammad Hafidz (2020) Perhitungan Waktu dan Biaya Konstruksi Pembangunan Mall Lagoon Avenue Sungkono Grand Sungkono Lagoon Surabaya. Diploma thesis, Institut Teknologi Sepuluh Nopember.
Preview |
Text
10111610013027-Undergraduate_Thesis.pdf Download (60MB) | Preview |
Abstract
Proyek Pembangunan Mall Lagoon Avenue Sungkono terletak di Jl. Abdul Wahab Siamin, Blok RA, Surabaya. Proyek ini merupakan salah satu bagian dari pembangunan Superblock Grand Sungkono Lagoon milik PT. PP (Properti) yang tediri dari 1 mall dan 5 tower (3 tower apartemen, 1 tower hotel dan 1 tower perkantoran) di lahan seluas 3,5 Ha. Mall Lagoon Avenue Sungkono dikerjakan oleh PT. PP (Persero), Tbk. melalui PP Divisi Gedung 2 dengan panjang 118.5 m, lebar 18,5 m dan tinggi 22 m. Bangunan tersebut memiliki 5 lantai termasuk atap dan 4 buah lantai basement dengan total luas bangunan ± 52.305 m2.
Proyek pembangunan Mall Lagoon Avenue Sungkono terbagi dalam dua jenis pekerjaan struktur utama yaitu struktur bawah dan struktur atas. Struktur bawah pada proyek ini menggunakan pondasi bored pile, sedangkan untuk struktur atas menggunakan beton bertulang. Proyek ini menggunakan metode pengecoran in-situ untuk membangun struktur utamanya. Pembangunan Mall Lagoon Avenue Sungkono memiliki volume pekerjaan yang sangat besar sehingga diperlukan perencanaan metode pelaksanaan kontruksi yang baik dan perhitungan waktu serta biaya pelaksanaan yang efektif. Pada proposal tugas akhir ini akan terfokus pada pelaksanaan pekerjaan struktur beton bertulang dari lantai basement 3 sampai lantai 5 (Rooftop).
Perhitungan waktu dan biaya pelaksanaan dihitung berdasarkan metode pelaksanaan yang digunakan sesuai dengan teori dari berbagai referensi dan dikaitkan dengan kondisi proyek. Sehingga dengan metode pelaksanaan yang tepat maka menghasilkan perhitungan waktu dan biaya pelaksanaan yang efektif. Dalam menghitung waktu, dimulai dengan menghitung kapasitas produksi, produktivitas, durasi dan kebutuhan sumber daya setiap item pekerjaan. Kemudian untuk penyusunan jadwal tiap item pekerjaan, dilakukan dengan menggunakan bantuan software Microsoft Project. Hasil akhir pada tugas ini adalah rekapitulasi durasi pelaksanaan proyek, biaya pelaksanaan proyek, metode pelaksanaan yang digunakan, serta Kurva S pada Proyek Pembangunan Mall Lagoon Avenue Sungkono.
Dari perhitungan, didapatkan durasi pekerjaan selama 562 hari kerja dan biaya pelaksanaan sebesar Rp. 97,622,606,790.57.
=========================================================================================
The Lagoon Avenue Sungkono Mall Development Project is located on Jl. Abdul Wahab Siamin, Blok RA, Surabaya. This project is one part of the construction of the Grand Sungkono Lagoon Superblock owned by PT. PP (Property) consisting of 1 mall and 5 towers (3 apartment towers, 1 hotel tower and 1 office tower) in an area of 3.5 hectares. Lagoon Avenue Sungkono Mall is done by PT. PP (Persero), Tbk. through PP Building Division 2 with a length of 118.5 m, width 18.5 m and height 22 m. The building has 5 floors including a roof and 4 basement floors with a total building area of ± 52,305 m2.
The Lagoon Avenue Sungkono Mall construction project is divided into two main types of structural works namely the lower structure and the upper structure. The bottom structure of this project uses a bored pile foundation, while the upper structure uses reinforced concrete. This project uses in-situ casting methods to build its main structure. The construction of the Lagoon Avenue Sungkono Mall has a very large volume of work, so planning for a good construction method and calculating time and efective cost implementation is needed. This final project proposal will focus on carrying out reinforced concrete structures from basement 3 to 5 (rooftop).
The calculation of the time and cost of implementation is calculated based on the implementation method used in accordance with the theories of various references and is linked to the project conditions. So with the right implementation method, it results in the calculation of time and cost effective implementation. In calculating time, it starts with calculating the production capacity, productivity, duration and resource requirements of each work item. Then to schedule each work item, done using Microsoft Project software. The final result of this assignment is a recapitulation of the duration of the project implementation, the cost of the project implementation, the method of implementation used, and the S Curve in the Lagoon Avenue Sungkono Mall Development Project.
From the analysis results, obtained the duration of work for 562 working days and the implementation cost of Rp97,622,606,790.57.
Item Type: | Thesis (Diploma) |
---|---|
Uncontrolled Keywords: | Implementation Method, Time of Implementation, Implementation Costs, Curve S, Metode Pelaksanaan, Waktu Pelaksanaan, Biaya Pelaksanaan, Kurva S |
Subjects: | T Technology > TA Engineering (General). Civil engineering (General) T Technology > TH Building construction T Technology > TH Building construction > TH437 Building--Cost control. |
Divisions: | Faculty of Vocational > Civil Infrastructure Engineering (D3) |
Depositing User: | Muhammad Hafidz Anshori |
Date Deposited: | 27 Aug 2020 01:47 |
Last Modified: | 23 Dec 2023 15:08 |
URI: | http://repository.its.ac.id/id/eprint/81373 |