Analisa Kapasitas Tampungan Waduk Promenade Di Citraland Surabaya Provinsi Jawa Timur

Mujibadi, Julian Khoidir (2016) Analisa Kapasitas Tampungan Waduk Promenade Di Citraland Surabaya Provinsi Jawa Timur. Diploma thesis, Institut Teknologi Sepuluh Nopember.

[thumbnail of 3113030149-Non_Degree_Thesis.pdf]
Preview
Text
3113030149-Non_Degree_Thesis.pdf - Accepted Version

Download (2MB) | Preview

Abstract

Waduk promenade berfungsi sebagai pengendali banjir
untuk kawasan sekitar waduk. Permasalahan utama yang dihadapi
Waduk Promenade adalah banjir yang terjadi di daerah sekitar
waduk ini. Waduk promenade mempunyai luas DAS kurang lebih
seluas 0.550 Km2 dan memiliki 3 saluran yang masuk ke waduk
ini. Kondisi existing waduk pada saat ini memiliki 18.024 m2.
Namun, lahan waduk promenade ini akan diperkecil luas area
tampungannya menjadi 7.000 m2 dikarenakan lahan tersebut
digunakan untuk area perumahan.
Untuk mengetahui kapasitas tampungan waduk
promenade perlu dilakukan analisa data hujan, perhitungan debit
rencana, perhitungan inflow dan outflow, analisa kapasitas
tampungan waduk eksisting serta flood routing pada waduk.
Dari hasil analisa diperoleh debit banjir rencana untuk
periode ulang 2 tahun sebesar 5.58 m3/det, periode ulang 5 tahun
sebesar 6,49 m3/det, dan periode ulang 10 tahun 7,28 m3/det. Pada
analisa penelusuran banjir untuk waduk dengan luas 18.024 m2
didapat hasil bahwa kapasitas tampungan waduk masih belum
memenuhi. Sehingga saluran lidah kulon harus dinormalisasi. Jika,
luasan waduk diperkecil menjadi 7000 m2 maka akan terjadi banjir
di saluran Lidah Kulon dengan ketinggian 1 m, sehingga luasan
waduk tidak direkomendasikan untuk diperkecil menjadi 7000 m2
========================================================================================================================
Reservoir promenade serves as flood control for the
area around the reservoir. The main problem facing the
Promenade Reservoir is a flood that occurred in the area around
this reservoir. Promenade reservoir basin area has an area of
approximately 0.550 km2 and has 3 channels that go into this
reservoir. Existing condition reservoir currently has 18 024 m2.
However, this promenade reservoir land area will be reduced to
7,000 m2 because the land is used for residential area.
To find the reservoir storage capacity promenade
necessary rainfall data analysis, calculation of discharge plans,
calculation of inflow and outflow, reservoir analysis of existing
storage capacity and flood routing in reservoirs.
From the results of the analysis of flood discharge plan
for a return period of 2 years at 5.58 m3 / sec, the 5-year period
amounted to 6.49 m3 / sec, and a 10-year return period of 7.28 m3
/ sec. In the analysis of flood search for reservoirs with an area of
18.024 m2 got the result that the storage capacity of the dam is still
not meet. Lidah Kulon so that the channel should be normalized.
If, reservoir area reduced to 7000 m2, there will be a flood channel
Lidah Kulon with a height of 1 m, so the extent of the reservoir is
not recommended to be reduced to 7000 m2.

Item Type: Thesis (Diploma)
Additional Information: RSS 551.482 Muj a
Uncontrolled Keywords: Kapasitas tampungan; banjir; waduk
Subjects: T Technology > TD Environmental technology. Sanitary engineering > TD395 Reservoirs (water supply)
Divisions: Faculty of Civil Engineering and Planning > Civil Engineering > 22401-(D3) Diploma 3
Depositing User: ansi aflacha
Date Deposited: 14 Sep 2020 02:59
Last Modified: 14 Sep 2020 02:59
URI: http://repository.its.ac.id/id/eprint/81894

Actions (login required)

View Item View Item