Breakwater adalah prasanana yang dibangun sebagai
pemecah ombak / gelombang dengan menyerap
sebagian energi gelombang yang datang. Breakwater digunakan
untuk mengendalikan abrasi yang menggerus garis pantai dan
untuk menenangkan gelombang dipelabuhan sehingga kapal dapat
bermanuver dipelabuhan dengan lebih mudah dan cepat. Pemecah
gelombang harus didesain sedemikian sehingga arus laut tidak
menyebabkan pendangkalan karena pasir yang ikut dalam arus
mengendap di kolam pelabuhan. Bila hal ini terjadi maka
pelabuhan perlu dikeruk secara reguler.
Struktur breakwater waikelo ini runtuh akibat diterjang
gelombang mencapai tinggi 5 meter dengan kecepatan angin
mencapai 23 knot pada 21 Januari 2012. Tercatat bahwa terjadi
gempa sebesar 6,3 SR yang menyebabkan keruntuhan beberapa
bagian breakwater, sehingga beberapa fasilitas dermaga Waikelo
mengalami kerusakan akibat gelombang yang langsung
menghantam dermaga. Mengetahui permasalahan tersebut perlu
dilakukan evaluasi layout dan struktur breakwater yang sesuai
dengan data dilapangan, sehingga fungsi dari breakwater dan
dermaga waikelo dapat terpenuhi untuk kebutuhan transportasi
warga.Breakwater ini direncanakan ulang dengan sepenuhnya
menggunakan tipe monolith. Breakwater ini dibangun dengan
terdiri dari dua segmen yang membentang dari arah barat daya
dengan kedalaman -4mLWS ke arah timur laut sampai kedalaman
–20 mLWS sepanjang 61,19 meter, kemudian membelok ke arah
timur mengikuti kontur -20 mLWS sepanjang 88,50 meter. Satu
segmen breakwater sebelah timur yang sebelumnya sudah ada,
memanjang tegak lurus garis pantai ke arah laut.
Total biaya yang dibutuhkan dalam pembangunan struktur
breakwater waikelo ini adalah sebesar Rp. 86.225.768.000,00.
============================================================================================================
Breakwater is an infrastructure that is build as the wave
breaker which absorbs half of the coming wave. Breakwater is used
to control the abration which erodes the shoreline and also to calm
the wave down at the harbor so that the ship can maneuver easily
and fast. Breakwater must be designed just to prevent the pond of
the harbor be silting up by the sand that carried by the current. If
this happen, the harbor must be dredged up regularly.
The Structure of Waikelo breakwater collapsed because
of the wave that coming in 5 meters high with velocity of the wind
by 23 knots in January, 21st 2012. There was an earthquake, 6,3
SR that make half of the breakwater collapse, which caused the
damage some of the Waikelo harbor facilities by the wave that hit
them directly. As the problems mentioned above, it is important to
evaluate the layout and its structure according to the real data, so
that the function of the breakwater and the harbor of Waikelo be
fulfilled for the citizen transportation.
This breakwater is fully re-designed using monolith type.
This breakwater consist of two segments which stand 61,19 meters
long from elevation -4 mLWS to -20 mLWS north east and then
going along east ward by 88,50 meters long, elevation -20 mLWS.
There is a segment of breakwater in east side that has been build
perpendicular from the shoreline toward the sea.
The total cost required to build this breakwater of
Waikelo is Rp. 86.225.768.000,00.
Item Type: | Thesis (Undergraduate) |
---|---|
Additional Information: | RSS 627.24 Bon e 3100014056249 |
Uncontrolled Keywords: | Breakwater, Waikelo, Monolith, Pemodelan, Struktur, Metode Pelaksanaan, Rencana Anggaran Biaya. |
Subjects: | T Technology > TC Hydraulic engineering. Ocean engineering > TC205 Harbors--Design and construction. T Technology > TC Hydraulic engineering. Ocean engineering > TC333 Breakwaters |
Divisions: | Faculty of Civil Engineering and Planning > Civil Engineering > 22201-(S1) Undergraduate Thesis |
Depositing User: | Yeni Anita Gonti |
Date Deposited: | 12 Oct 2020 03:08 |
Last Modified: | 12 Oct 2020 03:08 |
URI: | http://repository.its.ac.id/id/eprint/82108 |
Actions (login required)
View Item |