Studi Kelayakan Pemasangan PLTS 80 kW Pada Sistem Kelistrikan PT. Indonesia Kendaraan Terminal

Ray, Pius Aditya Kurnia (2020) Studi Kelayakan Pemasangan PLTS 80 kW Pada Sistem Kelistrikan PT. Indonesia Kendaraan Terminal. Other thesis, Institut Teknologi Sepuluh Nopember.

[thumbnail of 07111340000122-Undergraduate_Thesis.pdf]
Preview
Text
07111340000122-Undergraduate_Thesis.pdf

Download (2MB) | Preview

Abstract

PLTS sebagai salah satu pembangkit listrik terdistribusi adalah jenis pembangkit yang paling efisien untuk di terapkan pada lahan industri. Banyak industri menengah hingga besar di Indonesia yang tertarik untuk mulai menerapkan PLTS pada lahan usaha mereka. PT. Indonesia Kendaraan Terminal menjadi salah satu pelaku industri besar yang tertarik untuk menerapkan PLTS pada jaringan listrik mereka. Namun sebelum menjalankan menerapkan hal tersebut harus dilakukan analisa terlebih dahulu terhadap kelayakan investasinya. Pada tugas akhir ini akan dianaliasa alternatif-alternatif investasi, untuk mendapatkan alternatif investasi seperti apa yang paling cocok dan paling menguntungkan dalam penerapan rencana ini. Oleh karena itu analisa kelayakan ekonomi teknik perlu dilakukan.
Pada tugas akhir ini penulis merencakan penggunaan 195 buah panel surya untuk diterapkan, dengan energi yang dihasilkan 89.83 MWh per tahun dan penghematan sebesar Rp 110.051.317,00. Metode ekonomi Teknik diterapkan untuk mendapatkan kelayakan dari investasi ini. Pada analisa ekonomi yang dilakukan didapatkan alternatif investasi terbaik dengan nilai NPV Rp 81.346.406,00, nilai IRR sebesar 0,54%. Sehingga proyek ini layak untuk dijalankan.
============================================================

==================================================================================================
PV as a distributed power plant is the most efficient type of generator to be applied to industrial land. Many medium to large industries in Indonesia are interested in starting to implement PV on their business lands. PT. Indonesia Kendaraan Terminal is one of the major industrial players who are interested in implementing PV in their electricity network. However, before implementing this plan, an analysis must be carried out first of the feasibility of the investment. In this final project, investment alternatives will be analyzed, to find which investment alternatives is the most suitable and most profitable to implement in this plan. Therefore, a economic feasibility analysis needs to be done.In this final project, the writer plans to use 195 solar panels to be implemented, with the energy produced by 89.83 MWh per year and savings of Rp. 110,051,317.00 from electrical bills. Economic feasibility analysis methods are applied to get the feasibility of this investment. In the economic analysis carried out, it was found that the best investment alternative with an NPV value of Rp. 81,346,406.00, an IRR value of 0.54%. So that this project is feasible to run.

Item Type: Thesis (Other)
Uncontrolled Keywords: Panel Surya, PV, Net Present Value (NPV), Internal Rate of Return (IRR), RETScreen, Ekonomi Teknik, Solar Cell, PV, Net Present Value (NPV), Internal Rate of Return (IRR), RETScreen, economic feasibility.
Subjects: T Technology > TK Electrical engineering. Electronics Nuclear engineering > TK1056 Solar powerplants
T Technology > TK Electrical engineering. Electronics Nuclear engineering > TK1087 Photovoltaic power generation
Divisions: Faculty of Intelligent Electrical and Informatics Technology (ELECTICS) > Electrical Engineering > 20201-(S1) Undergraduate Thesis
Depositing User: Pius Aditya Kurnia Ray
Date Deposited: 23 Dec 2020 21:24
Last Modified: 18 Jan 2024 13:03
URI: http://repository.its.ac.id/id/eprint/82328

Actions (login required)

View Item View Item