Perhitungan Waktu dan Biaya Pelaksanaan Struktur Menara PT. Bank Rakyat Indonesia (Persero) Tbk Jakarta

Setyaningrum, Fransiska (2021) Perhitungan Waktu dan Biaya Pelaksanaan Struktur Menara PT. Bank Rakyat Indonesia (Persero) Tbk Jakarta. Undergraduate thesis, Institut Teknologi Sepuluh Nopember.

[thumbnail of 10111910015017_Undergraduate_Thesis.pdf] Text
10111910015017_Undergraduate_Thesis.pdf - Accepted Version
Restricted to Repository staff only until 1 April 2023.

Download (9MB) | Request a copy

Abstract

Menara BRI yang berlokasi di Jl. Gatot Subroto Jakarta merupakan bangunan 37 lantai dan 5 basement yang menempati lahan seluas 8.589 m2 dengan luas konstruksi 95.437 m2. Pada Proyek akhir ini membahas mengenai perhitungan waktu dan biaya pelaksanaan sesuai dengan metode yang direncanakan.

Pembangunan Proyek ini menggunakan struktur beton bertulang. Adapun lantai yang ditinjau pada Proyek Akhir ini yaitu lantai 1 – 10. Metode yang digunakan untuk material bekisting yaitu menggunakan bekisting konvensional untuk lantai 1 - 5 dan Aluminium Formwork untuk lantai 6 – 10, sedangkan metode pengecoran yang digunakan yaitu metode cor in situ dengan beton ready mix.

Analisis yang dilakukan pada Proyek Akhir ini didahului dengan menghitung volume yang didapat dari gambar teknik yang ada. Volume tersebut digunakan untuk menghitung produktivitas dan kebutuhan sumber daya setiap pekerjaan sehingga diperoleh durasi pekerjaan dan biaya yang diperlukan. Sedangkan untuk penyusunan penjadwalan pada proyek ini menggunakan bantuan Microsoft Project.

Berdasarkan hasil Analisa diperoleh Rencana Anggaran Pelaksanaan untuk struktur beton lantai 1-10 pada proyek Menara BRI ini yaitu sebesar Rp.63.995.995.995 dan waktu pelaksanaan proyek selama 291 hari kalender.

===================================================================================================

BRI Tower, located on Jl. Gatot Subroto Jakarta is a building of 37 floors and 5 basement which has an area of 8.589 m2 with construction area of 95.437 m2. This Final Project discusses about the calculation of time and implementation cost according to the planned method.

The construction of this Project using reinforced concrete structures. The floors reviewed in this Final Project is 1st – 10th floor. The method used for formwork materials is conventional formwork on the 1st – 5th floors and Aluminium Formwork on the 6th – 10th floors, while the casting method used is the cast in situ method with concrete ready mix.

The analysis is carried out inthis Final Project is preceded by calculating the volume obtained from the existing engineering drawing. This volume is used to calculate the productivity and resource requirements of each job so that the required work duration and cost are obtained. Meanwhile for the preparation of scheduling in this project using the help of Microsoft Project.

Based on the result of the analysis, it is obtained that the implementation budget plan for concrete structures 1st – 10th floors in the BRI Tower Project is Rp.63.995.995.995 and the project implementation time is 291 calendar days.

Item Type: Thesis (Undergraduate)
Uncontrolled Keywords: waktu, biaya, metode konvensional, metode aluminium formwork, kurva s, time, cost, conventional formwork method, aluminium formwork method, S curve.
Subjects: H Social Sciences > HD Industries. Land use. Labor > HD69.T54 Time management. Scheduling
T Technology > TH Building construction > TH437 Building--Cost control.
Divisions: Faculty of Vocational > Civil Infrastructure Engineering (D3)
Depositing User: Fransiska Setyaningrum
Date Deposited: 08 Mar 2021 03:09
Last Modified: 08 Mar 2021 03:10
URI: http://repository.its.ac.id/id/eprint/83722