Saksono, Bintar Suryo (2021) Analisa Perhitungan Waktu Dan Biaya Pada Proyek Elevated Tol KLBM Seksi 2 STA.17+978 – STA.18+318 Dengan Metode Pelaksanaan Erection Girder Non Standard Bentang 50.8 M’. Undergraduate thesis, Institut Teknologi Sepuluh Nopember.
| ![[thumbnail of 10111710010008-Udergraduate_Theses.pdf]](http://repository.its.ac.id/style/images/fileicons/text.png) | Text 10111710010008-Udergraduate_Theses.pdf - Accepted Version Restricted to Repository staff only until 1 October 2023. Download (47MB) | Request a copy | 
Abstract
Penyusunan proyek akhir ini membahas tentang 
perhitungan waktu dan biaya pada proyek pembangunan jalan 
tol Krian – Legundi – Bunder - Manyar (disingkat jalan Tol 
KLBM). Jalan Tol KLBM membentang sepanjang 
38,39kilometer yang menghubungkan daerah Krian, 
Kabupaten Sidoarjo dengan Manyar, Kabupaten Gresik, 
Provinsi Jawa Timur. Pada tugas akhir ini batasan yang 
digunakan adalah seksi 2 Sta.17+978 – Sta.18+318 dengan 
panjang bentang 340,3 meter. Tol Elevated ini dibangun 
dengan PCI Girder prestress 40,8 m’ dan girder non standard 
50,8 m’, sedangkan lebar jalan adalah sepanjang 25.2 m’. 
Perhitungan waktu dan biaya pada proyek pembangunan 
jalan tol Krian – Legundi – Bunder - Manyar (KLBM) ini 
menggunakan gambar proyek yang didapat dari PT. Waskita 
Beton Precast (WBP) selaku kontraktor pelaksana seksi 2. Serta 
perhitungan biaya pelaksanaan berdasarkan data analisa 
dilapangan melalui survei harga, literatur/ brosur dan Harga 
Satuan Pokok (HSPK) kota Surabaya tahun 2020. 
iv 
Pada proyek ini waktu pelaksanaan didasarkan pada 
perencanaan metode pelaksanaan, salah satunya adalah 
metode pelaksanaan erection girder non standar bentang 50.8 
m’ dengan crawler crane 250 ton. Untuk penyusunan jadwal 
tiap item pekerjaan dilakukan dengan program bantu software 
Microsoft Project. 
Dari hasil perhitungan yang dilakukan penulis, 
didapatkan durasi pekerjaan 423 hari kerja dengan biaya 
Rp.128.336.556.583,00-
======================================================================================================
The preparation of this final project discusses the 
calculation of time and costs for the Krian – Legundi – Bunder 
- Manyar toll road construction project (abbreviated KLBM 
Toll Road). The KLBM Toll Road stretches for 38.39 kilometers 
that connects the Krian area, Sidoarjo Regency with Manyar, 
Gresik Regency, East Java Province. In this final project, the 
boundary used is section 2 Sta.17+978 – Sta.18+318 with a 
span of 340.3 meters. This Elevated Toll Road was built with 
PCI Girder prestress using 40,8 m' girder and 50.8 m' non�standard girder while the width of the road is 25.2 m'. 
The calculation of time and costs for the Krian – 
Legundi – Bunder - Manyar (KLBM) toll road construction 
project uses project drawings obtained from PT. Waskita Beton 
Precast (WBP) as the implementing contractor for section 2. As 
well as the calculation of implementation costs based on field 
vi 
analysis data through price surveys, literature/ brochures, and 
Basic Unit Prices (HSPK) for the city of Surabaya in 2020. 
In this project, the implementation time is based on the 
planning of the training method, one of which is the 
implementation method of non-standard erection girders 
spanning 50.8 m' with a 250-ton crawler crane. The 
preparation of the schedule for each work item is carried out 
with the Microsoft Project software program. 
From the results of calculations carried out by the 
author, the duration of the work is 423 working days at a cost 
of Rp.128.336.556.583,00-
| Item Type: | Thesis (Undergraduate) | 
|---|---|
| Uncontrolled Keywords: | Tol Elevated, Erection Girder, Durasi, Biaya | 
| Subjects: | T Technology > T Technology (General) T Technology > T Technology (General) > T56.8 Project Management T Technology > TA Engineering (General). Civil engineering (General) T Technology > TA Engineering (General). Civil engineering (General) > TA683 Precast concrete construction. Prestressed concrete construction. T Technology > TA Engineering (General). Civil engineering (General) > TA780.C29 Piling (Civil engineering) T Technology > TF Railroad engineering and operation > TF193 Estimates, costs, etc. | 
| Divisions: | Faculty of Vocational > Civil Infrastructure Engineering (D4) | 
| Depositing User: | BINTAR SURYO SAKSONO | 
| Date Deposited: | 31 Aug 2021 06:54 | 
| Last Modified: | 21 May 2025 02:38 | 
| URI: | http://repository.its.ac.id/id/eprint/90669 | 