Perbandingan Perhitungan Estimasi Waktu Dan Biaya Pelaksanaan Dengan Metode Manual dan Permodelan BIM [Studi Kasus: Apartemen Tower B2 Mahata Serpong]

Rofiqi, Muhammad Mukzon (2021) Perbandingan Perhitungan Estimasi Waktu Dan Biaya Pelaksanaan Dengan Metode Manual dan Permodelan BIM [Studi Kasus: Apartemen Tower B2 Mahata Serpong]. Undergraduate thesis, InstitutTeknologi Sepuluh Nopember.

[thumbnail of 10111710013079-Undergraduate_Theses.pdf] Text
10111710013079-Undergraduate_Theses.pdf - Accepted Version
Restricted to Repository staff only until 1 October 2023.

Download (3MB) | Request a copy

Abstract

Proyek konstruksi merupakan suatu kegiatan yang kompleks, kesalahan-kesalahan didalamnya dapat mengakibatkan terjadinya penambahan biaya maupun anggaran yang terbuang dikarenakan material yang dipesan lebih dari kebutuhan lapangan. Pada era digital ini, pemanfaatan teknologi juga digunakan pada sektor konstruksi yaitu dengan diterapkannya BIM untuk membantu perhitungan kebutuhan konstruksi yang lebih efisien dalam dalam segi waktu pengerjaan serta keakuratan perhitungan.
Tugas akhir ini difokuskan untuk membandingkan perhitungan antar manual dan basis perangkat lunak BIM dalam perhitungan kebutuhan biaya proyek. Pada penelitian ini digunakan keduanya menggunakan metode pelaksaan yang sama. Pada tugas akhir ini perhitungan dil-akukan secara manual lalu dihitung menggunakan basis perangkat lunak BIM dan dibandingkan dari segi biaya serta durasi yang dibu-tuhkan dari keduanya.
Hasil dari tugas akhir ini didapatkan adanya reduksi dengan menggunakan basis perangkat lunak BIM dalam segi biaya sebesar 1.06% serta durasi sebesar 1.28%. sehingga dapat disimpulkan bahwa perhitungan biaya serta durasi konstruksi dengan bantuan perangkat lunak BIM memiliki kelebihan dibandingkan dengan perhitungan menggunakan metode Konvensional/manual
=====================================================================================================
Construction projects are complex activities, where small mistakes may cause unnecessary costs for material resulting in waste of material. In today's digital era, the use of technology also played a role in the construction sector by implementing BIM for increasing its efficiency in terms of time and calculation accuracy.
This final project is focused on the comparison between manual/traditional costs estimation and the BIM-based approach, and both use the same method of construction. The final project cost estimation calculated using the manual/conventional method and the BIM-based and then com-
pared in terms of the final cost needed and duration of the project.
The conclusion from this final project is there's a reduction with BIM-assisted cost estimation in terms of the costs and duration needed by 1.06% and 1.28%, respectively. It is thus concluded that the BIM-assisted cost estimation has a better performance in comparison to the manual/conventional cost estimation method

Item Type: Thesis (Undergraduate)
Uncontrolled Keywords: anggaran biaya, bim, konvensional, penjadwalan waktu, cost estimation, manual/conventional, time schedule
Subjects: T Technology > TA Engineering (General). Civil engineering (General)
Divisions: Faculty of Vocational > Civil Infrastructure Engineering (D4)
Depositing User: Muhammad Mukzon Rofiqi
Date Deposited: 31 Aug 2021 02:18
Last Modified: 31 Aug 2021 02:18
URI: http://repository.its.ac.id/id/eprint/90747