Perhitungan Waktu dan Biaya Pelaksanaan Pembangunan Apartemen Grand Stand Surabaya Lantai 7-19 Menggunakan Metode Half Slab Precast

Haq, Yusfira Afrianti (2021) Perhitungan Waktu dan Biaya Pelaksanaan Pembangunan Apartemen Grand Stand Surabaya Lantai 7-19 Menggunakan Metode Half Slab Precast. Undergraduate thesis, Institut Teknologi Sepuluh Nopember.

[thumbnail of 10111710013064_YUSFIRA AFRIANTI HAQ.pdf] Text
10111710013064_YUSFIRA AFRIANTI HAQ.pdf - Accepted Version
Restricted to Repository staff only until 1 October 2023.

Download (16MB)

Abstract

Penyusunan proyek akhir terapan yang berjudul “Perhitungan Waktu dan Biaya Pelaksanaan Pembangunan Apartemen Grand Stand Surabaya Lantai 7-19 Menggunakan Metode Half Slab Precast” ini menggunakan data bangunan Gedung Apartemen Grand Stand Surabaya yang berlokasi di Jl. Raya Darmo Permai Selatan No. 90, Surabaya. Proyek ini memiliki luas lahan 4.781,58 m² dan luas bangunan 1063,68 m² dengan 30 lantai yang terdiri dari 4 lantai parkir, 1 lantai podium parkir, 1 lantai lobi, 1 lantai fasilitas umum, 22 lantai hunian dan 1 lantai atap. Dalam proyek ini seluruh pekerjaan elemen struktur beton menggunakan metode cor konvensional (in situ). Sedangkan metode pelaksanaan yang digunakan dalam penyusunan proyek akhir terapan adalah dengan metode precast half slab.
Biaya pelaksanaan dihitung berdasarkan analisa yang sesuai antara literatur yang digunakan maupun peraturan yang berlaku untuk mendapatkan kesesuaian dengan kondisi pelaksanaan lapangan. Sedangkan pada perhitungan waktu pelaksanaan dilakukan analisa mulai dari kapasitas produksi, produktivitas, durasi dan penyusunan jadwal setiap pekerjaan dimana hal ini dilakukan dengan menggunakan alat bantu Microsoft Project.
Berdasarkan hasil analisa perhitungan tersebut diketahui waktu pelaksanaan proyek tersebut dengan total biaya pelaksanaan pembangunan Apartemen Grand Stand Surabaya dengan menggunakan half slab precast didapatkan durasi pelaksanaan 243 hari dengan biaya pelaksanaan Rp 17.676.653.056,45
=======================================================================================================
The final project entitled "Time and Cost Estimation of Grand Stand Apartment Surabaya 7-19 Floor Using Half Slab Precast Method" uses data on the building of Grand Stand Surabaya Apartment located on Jl. Raya Darmo Permai Selatan No. 90, Surabaya. The project has a land area of 4,781.58 m² and a building area of 1063.68 m² with 30 floors consisting of 4 parking floors, 1 floor parking podium, 1 lobby floor, 1 floor of public facilities, 22 residential floors and 1 roof floor. The whole work of concrete structure elements of this project used conventional cast method (in situ). While, the implementation method is by the precast half slab method.
The cost of implementation is calculated based on the appropriate analysis between the literature and the applicable regulations to obtain conformity with the conditions of field implementation. While the calculation of implementation time is carried out analysis such as production capacity, productivity, duration and schedule of each work using Microsoft Project tools.
It can conclude that the time of implementation of the project with the total cost of the Grand Stand Apartment Surabaya using half slab precast takes 243 days with the cost of implementation Rp 17.676.653.056,45

Item Type: Thesis (Undergraduate)
Uncontrolled Keywords: Half slab precast, waktu pelaksanaan proyek, biaya pelaksanaan, dan kurva S
Subjects: T Technology > TA Engineering (General). Civil engineering (General)
Divisions: Faculty of Civil Engineering and Planning > Civil Engineering > 22301-(D4) Diploma 4
Depositing User: Yusfira Afrianti Haq
Date Deposited: 28 Aug 2021 03:31
Last Modified: 28 Aug 2021 03:31
URI: http://repository.its.ac.id/id/eprint/91165

Actions (login required)

View Item View Item