Perhitungan Rencana Anggaran Pelaksanaan Proyek Gedung Perkantoran The Royal 55 Surabaya Menggunakan Bekisting Aluminium

Kusma, Alham Indradi (2021) Perhitungan Rencana Anggaran Pelaksanaan Proyek Gedung Perkantoran The Royal 55 Surabaya Menggunakan Bekisting Aluminium. Undergraduate thesis, Institut Teknologi Sepuluh Nopember.

[thumbnail of 10111710010102-Undergraduate_Thesis.pdf] Text
10111710010102-Undergraduate_Thesis.pdf - Accepted Version
Restricted to Repository staff only until 1 October 2023.

Download (33MB) | Request a copy

Abstract

Proyek gedung perkantoran The Royal 55 Surabaya dalam pembangunannya menggunakan bekisting konvensional yang berbahan dasar dari kayu. Bekisting konvensional memiliki beberapa kelemahan yaitu waktu pengerjaan yang lama dan tidak ramah lingkungan. Untuk meminimalisir kelemahan itu maka dalam pengerjaan tugas akhir ini bekisting konvensional akan dirubah menjadi bekisting aliminium. Bekisting aluminium adalah salah satu metode bekisting yang mulai berkembang di Indonesia pada tahun 2017 yang diakui memiliki beberapa keunggulan yaitu lebih cepat dalam pelaksanaannya, ramah lingkungan, dan membutuhkan tenaga kerja yang sedikit, selain itu Aluminium formwork juga memiliki kelemahan yaitu lamanya proses fabrikasi dan hanya efektif apabila digunakan pada struktur yang typical.
Pada tugas akhir ini akan dilakukan perhitungan rencana anggaran pelaksanaan dengan menggunakan bekisting aluminium. Rencana Anggaran Pelaksanaan (RAP) adalah estimasi biaya pelaksanaan proyek yang dihitung dengan menggunakan harga setempat proyek Gedung perkantoran The Royal 55 surabaya. Perhitungan Rencana Anggaran Pelaksanaan pada tugas akhir ini menggunakan metode kontraktor yang perhitungannya berdasarkan pada pengalaman. Dalam pengerjaan tugas akhir ini menggunakan aplikasi bantu Ms.project guna menggambarkan kurva S dan barchart.
Perhitungan Rencana Anggaran Pelaksanaan menggunakan bekisting aluminium di dapatkan biaya sebesar Rp 14,319,175,528, sedangkan untuk bekisting konvensional di dapatkan harga sebesar Rp 13,315,511,302. Durasi yang di dapatkan untuk pelaksanaan menggunakan bekisting aluminium yaitu 304 Hari, sedangkan untuk bekisting konvensional di dapatkan 318 hari. Untuk kebutuhan bahan, alat dan pekerja dibuat sama yaitu untuk Kebutuhan bahan yang digunakan 2029.44 m3 beton, 16821.07 m2 bekisting, 17060 batang tulangan, 1206 lembar tulangan wiremesh, dan 93,28 m baja profil. Kebutuhan pekerja yang digunakan 121 pekerja dengan waktu yang telah di tentukan dan menggunakan alat berat sejumlah 4 unit.
================================================================================================
The Royal 55 Surabaya office building’s project in its construction uses conventional formwork made from wood. Conventional formwork has several disadvantages such as long processing times and doesn’t friendly for environment. To minimize this weakness, in this final project, conventional formwork will be converted into aluminum formwork. Aluminum formwork is one of the formwork methods that began to develop in Indonesia in 2017 which is recognized having several advantages, such as the implementation is faster than the conventional one, environmentally friendly, and requires less manpower. Besides that, Aluminum formwork also has some weakness such as the fabrication process is longer than the conventional one, and it’s effective when used in a specific typical structure.
In this final project, the calculation of the implementation budget plan will be carried out using aluminum formwork. The Implementation of Budget Plan (RAP) is the estimated cost of implementing the project which is calculated using the local price of The Royal 55 Surabaya office building project. The calculation of the Implementation Budget Plan in this final project uses the contractor method whose calculations are based on experiences. In the process of working on this final project, Ms.project is used to describe the S curve and barchart.
The calculation of Implementation Budget Plan using aluminum formwork is obtained around Rp 14,319,175,528, for conventional formwork, the price is Rp 13,315,511,302. The duration that obtained for the implementation using aluminum formwork is 304 days, while for conventional formwork is 318 days. For material requirements, tools and workers are same, the material requirements used 2029.44 m3 of concrete, 16821.07 m2 of formwork, 17060 reinforcing bars, 1206 wiremesh reinforcement sheets, and 93.28 m profile steel. The requirements for workers are 121 with a predetermined time and using 4 units of heavy equipment.

Item Type: Thesis (Undergraduate)
Uncontrolled Keywords: Bekisting, Aluminium, Konvensional, Biaya, Waktu, Formwork, Conventional, Cost, Time
Subjects: T Technology > TH Building construction > TH437 Building--Cost control.
Divisions: Faculty of Vocational > Civil Infrastructure Engineering (D4)
Depositing User: Alham indradi kusma
Date Deposited: 03 Sep 2021 06:42
Last Modified: 03 Sep 2021 06:42
URI: http://repository.its.ac.id/id/eprint/91241

Actions (login required)

View Item View Item