Perhitungan Waktu Dan Biaya Pelaksanaan Pembangunan Hotel Ibis Budget Surabaya Dengan Menggunakan Perth Construction Hire (PCH)

Basuki, Amir (2022) Perhitungan Waktu Dan Biaya Pelaksanaan Pembangunan Hotel Ibis Budget Surabaya Dengan Menggunakan Perth Construction Hire (PCH). Other thesis, Institut Teknologi Sepuluh Nopember.

[thumbnail of 10111710010085-Undergraduate_Thesis.pdf] Text
10111710010085-Undergraduate_Thesis.pdf - Accepted Version
Restricted to Repository staff only until 1 April 2024.

Download (15MB) | Request a copy

Abstract

Proyek pembangunan Hotel Ibis Budget Surabaya ini
berlokasi di Jl. Biliton No. 24- 26, Kota Surabaya, Jawa Timur. Proyek
ini dibangun dengan luas bangunan ± 1.122,75 meter yang terdiri dari
1 lantai basement dan 16 lantai hunian. Dalam pembangunannya,
proyek ini menggunakan struktur beton bertulang. Tulangan yang
digunakan difabrikasi di lokasi proyek. Secara keseluruhan sistem
struktur gedung ini memiliki bentang yang cukup lebar. Sehingga
memerlukan beberapa perhatian khusus pada daerah-daerah yang
mengalami konsentrasi gaya seperti pada daerah balok dan kolom
pada bentang yang lebar tersebut. Untuk bekisting beton yang akan
digunakan pada proyek ini adalah perth construction hire (PCH).
Dalam proses pengecorannya akan dilakukan menggunakan metode
cast in situ (pengecoran di tempat).
Data yang diperoleh dari proyek ini adalah gambar struktur
dan arsitektur. Data diolah untuk dijadikan analisa bentuk, ukuran dan
volume. Dari hasil pengolahan data, dapat dibuat perhitungan waktu
pelaksanaan dan anggaran biaya pelaksanaan yang dibutuhkan. Untuk
iv
hasil akhir adalah penjadwalan yang dilakukan dengan membuat
Network Planning dan Kurva S. Adapun alat bantu yang digunakan
dalam menyusun penjadwalan proyek ini dengan menggunakan
program Microsoft Project. Penjadwalan proyek sangat penting
sebagai tolak ukur apakah proyek tersebut selesai sesuai dengan waktu
yang telah direncanakan atau lebih dari waktu perencanaan.
Untuk hasil durasi dan produktivitas tiap pekerjaan digunakan
sebagai penjadwalan yang dapat dilakukan dengan membuat Network
Planning dan Kurva S. Adapun alat bantu yang digunakan dalam
menyusun penjadwalan proyek beserta dengan metode
pelaksanaannya dapat dilakukan dengan menggunakan program
Microsoft Project 2013. Dari perencanaan yang telah disusun
didapatkan hasil durasi pelaksanaan proyek tersebut adalah 159 hari
dengan total biaya sebesar Rp 4.908.102.315,11. Untuk biaya
Keselamatan dan Kesehatan Kerja (K3) diambil 2.19% dari total biaya
sehingga diperoleh Rp 107.487.440,70. Maka total biaya pelaksanaan
sebesar Rp 5.015.589.755,81.
=======================================================================================================
The project of the Ibis Budget Surabaya Hotel is located on Jl.
Biliton No. 24-26, City of Surabaya, East Java. This project was built
on a building area of ± 1,122.75 metersquare consisting of 1 basement
floor and 9 residential floors. In its construction, this project used a
reinforced concrete structure. The reinforcement used is fabricated at
the project site. The overall structural system of this building has a
fairly wide span. So that it requires some special attention to areas that
experience a concentration of forces such as the beam and column
areas in these wide spans. Concrete formwork to be used in this project
is a perth construction hire (PCH). In the casting process, it will be
carried out using the cast in situ method (casting in place).
The data obtained from this project are structural and
architectural drawings. The data is processed to be used as shape, size
and volume analysis. From the results of data processing, a calculation
of the implementation time and budget for the required
implementation costs can be made. The final result is a scheduling that
is done by creating a Network Planning and S Curve. The tools used
in preparing this project scheduling are using the Microsoft Project
program. Project scheduling is very important as a measure of whether
the project is completed in accordance with the planned time or more
than the planning time.
vi
For the results of the duration and productivity of each job, it is used
as a schedule that can be done by making Network Planning and S
Curves. The tools used in preparing project scheduling along with the
implementation method can be done using the program. Microsoft
Project 2013 the duration of the project implementation is 159 days
with a total cost of Rp 4.908.102.315,11. For the cost of Occupational
Safety and Health (OSH) 2.19% of the total cost was taken to obtain
Rp. 107.487.440,70. Then the total cost of implementation is Rp.
5.015.589.755,81

Item Type: Thesis (Other)
Uncontrolled Keywords: Perth Construction Hire, PCH, Waktu dan Biaya Pelaksanaan, Network Planning, Kurva S., Perth Construction Hire, PCH, Implementation of Time and Cost, Network Planning, S Curve.
Subjects: T Technology > T Technology (General) > T56.8 Project Management
T Technology > TF Railroad engineering and operation > TF193 Estimates, costs, etc.
Divisions: Faculty of Vocational > Civil Infrastructure Engineering (D4)
Depositing User: Amir Basuki
Date Deposited: 22 Feb 2022 03:31
Last Modified: 31 Oct 2022 02:23
URI: http://repository.its.ac.id/id/eprint/94704