Estimasi Waktu Dan Biaya Pelaksanaan Proyek Pembangunan Jembatan Rementes Pada Proyek Jalan Tol Cibitung – Cilincing Sta 11+044 – Sta 11+072

Martha, Laila Dwi (2021) Estimasi Waktu Dan Biaya Pelaksanaan Proyek Pembangunan Jembatan Rementes Pada Proyek Jalan Tol Cibitung – Cilincing Sta 11+044 – Sta 11+072. Other thesis, Institut Teknologi Sepuluh Nopember.

[thumbnail of 10111610013080-Undergraduate_Thesis.pdf] Text
10111610013080-Undergraduate_Thesis.pdf - Accepted Version

Download (54MB)

Abstract

Proyek pembangunan Jembatan Rementes merupakan bagian dari proyek pembangunan Jalan Tol Cibitung – Cilincing Seksi I yang berada di STA 11+044 – STA 11+072 Kecamatan Cibitung dan Cikarang Barat, Kabupaten Bekasi. Jembatan Rementes ini memiliki panjang 26,64 meter. Girder yang digunakan pada jembatan ini adalah PCI girder dengan bentang 25 meter. Pada tugas akhir ini, Jembatan Rementes akan dianalisa dari segi manajemen konstruksi. Mulai dari analisa item pekerjaan, sumber daya, metode pelaksanaan, metode penjadwalan dan estimasi biaya. Dalam analisa ini digunakan peraturan terkait seperti Peraturan Menteri PU No 28/PRT/M/2016 tentang harga satuan pekerjaan dan buku Analisa (Cara Modern) Anggaran Biaya Pelaksanaan karya Ir. Soedrajat sebagai referensi.
Pada laporan tugas akhir ini, didapatkan hasil analisa estimasi waktu dan biaya pada pembangunan Jembatan Rementes yaitu selama 142 hari kalender dengan biaya sebesar Rp.
27.864.928.893.
==================================================================================================================================
The Rementes Bridge construction project is part of the Cibitung - Cilincing Section I Toll Road construction project which is located at STA 11 + 044 - STA 11 + 072 Cibitung and West Cikarang Districts, Bekasi Regency. This Rementes Bridge has a length of 26.64 meters. The girder used on this bridge is a PCI girder with a span of 25 meters. In this final project, the Rementes Bridge will be analyzed in terms of construction management. Starting from
the analysis of work items, resources, implementation methods, scheduling methods and cost estimation. In this analysis, related regulations are used, such as the Minister of Public Works regulation number 28/PRT/M/2016 concerning the unit price of work and the Analysis book (Modern Way) Budget Implementation of Ir. Soedrajat as a reference. Analysis results of estimated time and cost of the constructions of Rementes bridge are obtained in this final project report. The time and cost needed to construct Rementes bridge are consecutively 142 days long and Rp. 27.864.928.893.

Item Type: Thesis (Other)
Additional Information: RSIS 624.25 Mar e-1
Uncontrolled Keywords: Jembatan, metode pelaksanaan, estimasi waktu, biaya.
Subjects: T Technology > T Technology (General) > T56.8 Project Management
T Technology > TE Highway engineering. Roads and pavements > TE7 TG300 Bridges--Design and construction.
Divisions: Faculty of Vocational > Civil Infrastructure Engineering (D4)
Depositing User: - Davi Wah
Date Deposited: 17 May 2023 08:05
Last Modified: 17 May 2023 08:05
URI: http://repository.its.ac.id/id/eprint/97934